Explain all parts
Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin.
Activity | Description | Immediate Predecessor |
Time (weeks) |
---|---|---|---|
A | Survey building site | 5 | |
B | Develop initial design | 9 | |
C | Obtain board approval | A, B | 13 |
D | Select architect | C | 3 |
E | Establish budget | C | 5 |
F | Finalize design | D, E | 14 |
G | Obtain financing | E | 11 |
H | Hire contractor | F, G | 9 |
A) Draw a project network. (Submit a file with a maximum size of 1 MB.)
B) Identify the critical path. (Enter your answers as a comma-separated list.)
C)
Develop the activity
Activity | Earliest Start |
Latest Start |
Earliest Finish |
Latest Finish |
Slack |
---|---|---|---|---|---|
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G | |||||
H |
D) Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?
The expected completion time is ____ weeks, which is (less /greater) than 1 year
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 3 images
- 8.35 Emerson Electric is considering the purchase of equipment that will allow the company to manufacture a new line of wireless devices for home appliance control. The first cost will be $80,000 and the life estimated is 6 years with a salvage value of $10,000. Three different salespeople have provided estimates regarding the added revenue the equipment will generate. Salespersons 1,2, and 3 have made estimates of $10,000, $16,000, and $18,000 per year, respectively. If the company's MARR is 8% per year, use a PW=based relation to perform a sensitivity analysis to assist in the decision to purchase the equipment. This question is in four parts. Part 4: Based on the results of the sensitivity analysis using three different salespeople's estimate of added revenue, what can you conclude about this purchase? The decision to purchase the equipment is sensitive to revenue estimates. Recommend the purchase of the equipment.. Do not recommend the purchase of the equipment..arrow_forwardI need answer typing clear urjent no chatgpt used i will give 5 upvotesarrow_forwardSection A - Please answer # 3 & 4 if possible. Thank youarrow_forward
- Create a PERT diagram using the below details,arrow_forwardDifferentiate between Service Projects and Revenue Projects?arrow_forwardMilwaukee Paper Manufacturing will install an advance computerized air pollution control equipment in its facility. It had identified eight activities that needs to be performed for the project to be completed. Refer to the table below for the details of the activities. Activity Description Immediate Duration Predecessor (Weeks) S A Build internal component 2 B Modify roof and floor 3 с Construct collection stack A D Pour cement and install frame A, B E Build high-temperature burner с F Install pollution control system с G Install air pollution device D, E 5 H Inspect and test F, G 2 Do the following: a. Develop a network diagram for the project using AON convention. b. Determine the project completion time, the critical path, and the slack time for each activity. c. Suppose the plant manager has been given only 12 weeks to install the new pollution control equipment. Determine which activities are to be crashed, and by how much, to meet the 12-week due date. Use the information in the…arrow_forward
- Problem 3: Taken from Exercise 5 from section 8.4 of Wayne Winston Operations Research. Consider the (simplified) list of activities and predecessors that are involved in building a house. Draw a project network and determine the minimal number of days needed to build a house using the Bellman-Ford algorithm. Exhibit a corresponding critical path. Activity A B C D E F G Description Build foundation Build walls and ceilings Build roof Do electrical wiring Put in windows Put on siding Paint house Immediate Predecessors A B B B E C, F Duration (Days) 5 8 11 5 4 6 3arrow_forwardWhat is the purpose of a feasibility study in the initial stages of a project?arrow_forwardConstruct this problem. Draw a network diagram, determine the early start, early finish, late start, late finish, and slack times for each activity (table), determine how long the project will take, and which activities are on the critical path.arrow_forward
- PERT-CPM Yu and Mi Company is planning to computerize its accounting system. Its IT consultant has determined the following activities required to complete this project together with the time estimates and precedence relationships. Time estimates (weeks) Optimistic Most Likely Pessimistic 5 Activity Description Predecessor Recruit project personnel System development System training Equipment training Manual system test Prel. System changeover Computer-personnel interface Equipment redesign Equipment testing J A 8 12 17 B 3 15 C A 4 7 10 D A 8 23 В. С В. С D, E D, E E F 1 1 1 1 4 13 3 H 1 2.5 7 I H 1 1 1 System debugging and installation Equipment changeover F, G G, I K 5 8. 11 a. Determine the expected project completion time and the variance. b. What is the project's critical path? c. Determine the probability that the project will be completed in 40 weeks or less.arrow_forwardb) – Draw the Activity-on-Node (AON) diagram using the following representation for every node: Activity Description Expected Time ES EF LS LF Slack C.) Complete the following table, determine the expected time of completion assuming that the project starts at week 0 (zero) and identify the critical path for this project. Demonstrate all your calculations. On Critical Path? Activity Activity Description ES EF LS LF Slack Yes or No Locate new facilities 2 Order furniture Interview prospective staff Hire and train staff 3 4. Remodel facilities Receive and set up furniture Move in and start up 6 7 a) Complete the following table, calculate the project variance and project standard deviation. Demonstrate all your calculations.arrow_forwardTime Immediate Time Immediate Activity (weeks) Predecessor(s) Activity (weeks) Predecessor(s) A 7 4 7 B 3 11 C, E 1 7 D.F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF 7 B 10 7 E 11 G 22 20 Dave's latest start (LS) and latest finish (LF) are: Activity LS LF H 15 G 11 F 9 E 7 D 14 A The slack times are: Activity Slack A D E F G H The activities on the critical path are The total project completion time for Dave = weeks.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.