Step 1
Network Diagram :
Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)
Early Finish = ES + Duration
|
Early Start |
Early Finish |
A |
0 |
7 |
B |
0 |
7 |
C |
7 |
10 |
D |
7 |
8 |
E |
7 |
11 |
F |
7 |
13 |
G |
11 |
22 |
H |
13 |
20 |
Step by stepSolved in 4 steps with 1 images
Knowledge Booster
Similar questions
- + Recreate the Table with excel. 2. Draw the AON diagram and using Time-Cost Trade-Off concept, determine the optimum cost and optimum duration for the network. Develop an excel sheet to show all your calculations. The overhead cost = $200/day. Activity Predecessors A B C D E F G H I J K A A A B B, C D E F F, G H, I, J Duration (Days) Normal 1 7 6 3 3 7 8 7 5 3 5 Crash 1 4 4 2 1 5 4 6 32 2 4 Cost ($) Normal 800 1000 300 400 100 500 1200 350 700 500 450 Crash 800 1600 500 800 200 800 1400 600 850 1000 800arrow_forwardWork Performance Data: End of Day Oct 3/11 Duratio Task Name System Installation System Analysis 10 System Design 20 System Developme 30 System Testing 3 System Deploymen 5 Project Complete 0 a) $900 +-10 b) -$900 +-10 n (days) 70 c) None of these d) $3.500 +-10 Start Aug 1/11 Aug 1/11 Aug 9/11 Aug 23/11 Oct 4/11 Oct 10/11 Oct 17/11 Finish Oct 17/11 Aug 12/11 Sept 5/11 Oct 3/11 Oct 10/11 Oct 17/11 Oct 17/11 Planned Actual % Value Cost Complete $9,000 $3,500 48.9% D'Arcy is managing a software development project. The Work Performance Report above, shows the project schedule and current performance information. What is the current CV for D'Arcy's project? $500 $700 $1,000 $800 $6,000 $2,000 $1,000 $500 88 100.0% 90.0% 50.0% 0% 0%arrow_forwardStage 2 General Mathematics - Summative Discrete Models Test 1. Nine activities are needed to prepare a delivery of sneakers from the factory to the customers. The duration, in minutes, and immediate predecessors for these activities are shown in the table below. Prerequisite(s) Earliest Start Time Latest Start Time Activity A B C D E F G H Duration 5 3 8 9 I 26534 - ABUSE C, D C, D E F G, H a) Given the information in the first 3 columns, draw the Precedence Network for these activities. Slack Time b) Using the Critical Path Method, complete the table above (with Earliest Start Time, Latest Start Time and Slack Time columns) then state the Critical Path in the space below. c) What is the minimum completion time for the preparation of the delivery?arrow_forward
- Answer A.Figure 1 B. Figure 2 C. Figure 3arrow_forwardGive typed full explanation of botharrow_forwardTask A. High Level Analysis B. Selection of Hardware Platform C. Installation and Commissioning of hardware D. Detailed Analysis of core modules E. Detailed Analysis of supporting Modules F. Programming of core modules 3 H. 1 G. Programming of supporting Modules Quality Assurance of core modules Quality Assurance of supporting Modules J. Core module training I. 1 1 K. 1 1 Development and QA of accounting Report L. Development and QA of Management reporting M. Development of Management Information System N. Detailed Training 1 L 1 I, J, K, M Create a Gantt Chart starting May 1, 2022. No day-offs Duration 1 1 2 2 2 2 Prerequisite A B A D D E F G C, H E Earrow_forward
- Question 1 What is a unique, one-time event that is intended to achieve an objective in a given time period? Oa task Oan event Oan activity O a job Oa project MacBook Air 000 000 08 F5 DD F6 F8arrow_forwardLayout References Mailings Review View Help m、而、和、 三E处 AaBbCcD AaBbCcD AaBbC AaBbCcC AaB T Normal 1 No Spac.. Heading 1 Heading 2 Title Paragraph Styles 4. List the steps in the formal goal-setting process. What are some of the advantages for companies that use this approach? What are some of the problems that may arise from use of this approach? Feb 4, 2022, 10:45 PM nh attention on the achievement 12arrow_forwardTask No. Task Name Task Duration(Days) Immediate Predecessor task 1 Preliminary system description 40 — 2 Develop specifications 100 1 3 Client approval 50 2 4 Develop input-output summary 60 2 5 Develop alarm list 40 4 6 Develop log formats 40 3, 5 7 Software definition 35 3 8 Hardware requirements 35 3 9 Finalize input-output summary 60 5, 6 10 Analysis performance calculations 70 9 11 Automatic turbine startup analysis 65 9 12 Boiler guides analysis 30 9 13 Fabricate and ship 200 10, 11, 12 14 Software preparation 80 7, 10, 11 15 Install and check 130 13, 14 16 Termination and wiring lists 30 9 17 Schematic wiring lists 60 16 18 Pulling terminals and cables 60 15, 17 19 Operational test 125 18 20 First firing 1 19 Therefore, Critical Path = 1-2-4-5-6-9-10-13-15-18-19-20 Note: tj is the original duration of task j; dj is the minimum duration of task j. Expediting Costs ($1,000) and Limits Task no.…arrow_forward
- Type Precedent Activity Task Length (week) Sequential Sequential A. High level analysis B. Selection of hardware platform C. Installation and commissioning of hardware D. Detailed analysis of core modules E. Detailed analysis of supporting modules F. Programming of core modules G. Programming of supporting modules H. Quality assurance of core modules 1. Quality assurance of supporting modules J. Core module training K. Development and QA of accounting reporting L. Development and QA of management reporting M. Development of Management Information System N. Detailed training 1 1 A 2 Parallel B |Sequential Sequential Sequential Sequential Sequential Sequential A 2 D D 3 E 1 G 1 Parallel C,H 1 Parallel E 1 Parallel E 1 Sequential L 1 Sequential I, J, K, M 1. CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL PATH AND ITS DURATION 4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS 5. WHEN WILL THE PROJECT BE COMPLETED?arrow_forwardQuestion 9arrow_forwardUse legend to answer question.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.