Structural Analysis
6th Edition
ISBN: 9781337630931
Author: KASSIMALI, Aslam.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Question
Estimating & Costing Civil Q Create a rough estimate for the building project with the total
Based on the statistics below, the total building's plinth area is 800 square metres.
i) Plinth area fee is Rs. 4500 per square metre
Water supply costs are 7% of building costs.
Cost of electrical and sanitary installations, each at 7% of the price of
iv) The price of architectural features is 1% of the cost of the structure.
v) The cost of streets and lawns, which is 5% of building costs. vi) P&S and contingency costs at 4% of building costs.
Calculate the project's overall cost.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 3 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- ABC Construction Company enters into a contract with XYZ Municipality to construct a new public library. The project has a strict deadline due to an upcoming community event, and the municipality is keen to have the library completed well in advance. To incentivize ABC Construction for early completion, the parties agree on a fixed price reward contract. As the construction progresses, ABC Construction faces several challenges, such as inclement weather, delayed material deliveries, and unforeseen site conditions. Despite these obstacles, the company manages to complete the project two months ahead of the agreed-upon deadline. In this scenario, how does the fixed price reward contract benefit ABC Construction Company? What are the specific terms and conditions associated with the reward? How can ABC Construction effectively claim and receive the reward from XYZ Municipality? Additionally, what legal considerations should ABC Construction be aware of when entering into a fixed price…arrow_forwardThe preliminary cost for a 51,000 ft2 aircraft hangar must be estimated. The first unit estimate was $101 per square foot. Estimate the cost of the hangar. The cost of the hangar is determined to be $ .arrow_forwardA client plans to construct a manufacturing plant that involves multiple engineering disciplines. Calculate the total engineering fees including taxes based on the following: Mechanical Works, $1,540,000 Electrical Works, $1,780,000 Earth Works, $950,000 Civil Works, $2,125,100 Environmental Works, $1,325,000 Basis B fees = 9% There are no office fees Taxes = 13%arrow_forward
- Develop a programming budget estimate for a 100,000 square-foot warehouse, assuming a square-foot cost factor of $60 per square foot. The site will be about 200,000 square feet with a site development cost of $3 per square foot. Use the following allowances to prepare your budget estimate: - Owner-furnished FFE: $1,000,000 - Owner soft costs: $800,000 - Programming fees: $50,000 - Geotechnical Investigation: $390,000arrow_forwardDo the task according to the given instructions. Show solutions.arrow_forwardA person purchases a plot of land and constructs a building of plinth area 100 sq on this plot of land. The construction cost is Rs. 500000/-. The height of the building upto top of floor is 3.40 m. A parapet wall of height equal to 80 cm is constructed on the terrace. Work out the cost per sq m and cu m of the building. If a similar building of plinth area equal to 140 sq m is to be constructed in nearb locality, what would be its approximate cost of construction?arrow_forward
- Develop a programming budget estimate for a 100,000 square-foot warehouse, assuming a square-foot cost factor of $60 per square foot. The site will be about 200,000 square feet with a site development cost of $3 per square foot. Use the following allowances to prepare your budget estimate: - Owner-furnished FFE: $1,000,000 - Owner soft costs: $800,000 - Programming fees: $50,000 - Geotechnical Investigation: $390,000arrow_forwardProject Z has a current budget of $20 million. The project is working on a 20-month schedule. After month 6, the following performance data is available: Actual Cost (AC) = $6.5 million; Planned Value (PV) = $6.8 million; Earned Value = $7.1 million. What would be the Estimate at Completion, assuming that current cost performance will continue for the rest of the project?arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Structural Analysis (10th Edition)Civil EngineeringISBN:9780134610672Author:Russell C. HibbelerPublisher:PEARSONPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage Learning
- Fundamentals of Structural AnalysisCivil EngineeringISBN:9780073398006Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel LanningPublisher:McGraw-Hill EducationTraffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning