Project Z has a current budget of $20 million. The project is working on a 20-month schedule. After month 6, the following performance data is available: Actual Cost (AC) = $6.5 million; Planned Value (PV) = $6.8 million; Earned Value = $7.1 million. What would be the Estimate at Completion, assuming that current cost performance will continue for the rest of the project?

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Saeed Moaveni
Chapter20: Engineering Economics
Section: Chapter Questions
Problem 19P
icon
Related questions
icon
Concept explainers
Question
Project Z has a current budget of $20 million. The project is working on a 20-month schedule. After month 6, the following performance data is available: Actual Cost (AC) = $6.5 million; Planned Value (PV) = $6.8 million; Earned Value = $7.1 million. What would be the Estimate at Completion, assuming that current cost performance will continue for the rest of the project?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Budget estimating
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning