During the next four months, a construction firm must
complete three projects. Project 1 must be completed within
three months and requires 8 months of labor. Project 2 must
be completed within four months and requires 10 months of
labor. Project 3 must be completed at the end of two months
and requires 12 months of labor. Each month, 8 workers are
available. During a given month, no more than 6 workers can
work on a single job. Formulate a maximum-flow problem
that could be used to determine whether all three projects can
be completed on time. (Hint: If the maximum flow in the
network is 30, then all projects can be completed on time.)
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- I'm trying to find the capacity of a current line (on a conveyor-paced assembly). Each worker must perform at least one task. There are 6 tasks. Time to complete each task, starting with task 1, is 30, 25, 35, 40, 15, and 30 - all in seconds. There are 4 workers. Worker 1 completes Task 1; Worker 2 completes Task 2; Worker 3 completes Tasks 3 and 4; and Worker 4 completes Task 5 and 6.arrow_forwardI need solve this please fastarrow_forwardEmbassy Motorcycles (EM) manufactures two lightweight motorcycles designed for easy handling and safety. The EZ-Rider model has a new engine and a low profile that make it easy to balance. The Lady-Sport model is slightly larger, uses a more traditional engine, and is specifically designed to appeal to women riders. Embassy produces the engines for both models at its Des Moines, Iowa, plant. Each EZ-Rider engine requires 6 hours ofarrow_forward
- Mack's guitar fabrication shop produces low cost, highly durable guitars for beginners. Typically, out of the 100 guitars that begin production each month, only 82 percent are considered good enough to sell. The other 18 percent are scrapped due to quality problems that are identified after they have completed the production process. Each guitar sells for $240. Because some of the production process is automated, each guitar only requires 10 labor hours. Each employee works an average of 160 hours per month. Labor is paid at $10 per hour, materials cost is $40 per guitar, and overhead is $3,800. Part 2 a. The labor productivity ratio for Mack's guitar fabrication shop isarrow_forwardFive to six times a year, Kicker puts on tent sales in various cities throughout Oklahoma and the surrounding states. The tent sales are designed to show Kicker customers new products, engender enthusiasm about those products, and sell soon to be out-of-date products at greatly reduced prices. Each tent sale lasts one day and requires parking lot space to set up the Kicker semitrailer; a couple of show cars; a disc jockey playing music; a tent to sell Kicker merchandise, distribute brochures, and so on. Last year, the Austin, TX tent sale was held in a corner of the parking lot outside the city exhibition hall where the automotive show was in progress. Because most customers were interested more in the new model cars than in the refurbishment of their current cars, foot traffic was low. In addition, customers did not want to carry speakers and amplifiers all the way back to where they had originally parked. Total direct costs for this tent sale were $14,300. Direct costs…arrow_forwardAn entrepreneur is starting up a new bakery featuring a special pastry from an old family recipe. The basic dough recipe requires 5cups of flour, which is 0.75kg, plus another 0.75kg consisting of all the other ingredients, sugar, butter, milk, yeast, fruits, nuts and spices, to make the dough for 15 medium pastries. She runs some tests to scale up her recipe. In her first test batch she creates dough for 300 pastries, how much flour, in kg, was required?arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.