Develop a CPM diagram for the activities/relationships listed below (assume
durations are in months). For each activity calculate the Early Start, Late Start, Early
Finish, Late Finish, Total Float, and Free Float. Clearly identify the critical path for
the project (hint: a highlighter would be a good tool to use)
How do you solve this? I don't understand how it's done.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 5 images
Knowledge Booster
Similar questions
- A T= 4 T= 3 F T= 3 T= 3 D E G T= 1 T= 2 T= 2 The network diagram of a project along with the activity durations (T) is given in the figure. Which activities form one of the critical paths? @orsdemir. Copyrighted Content. Cannot be posted. CDEG O ABF О СВF O CF O None of thesearrow_forwardA key assumption related to the resources needed to complete activities when using the critical path method is?arrow_forwardBased on Table below, discuss how to complete the following project case:a. Create a network model in the form of Activity and Arrow (AoA) and Activity on Node (AoN) for the marketing product project of a company using the CPM method (manual and optimization software)! b. Analyze the critical path and critical duration for the company's project! Activity Description Predecessor Duration (day) A Production Planning — 18 B Market Survey and Market Research — 20 C Production Analysis A 28 D Modeling Product A, B 31 E Sales Brochures A, B 21 F Cost Analysis C, E 33 G Product Experiment D, E 42 H Sales Training B, E 29 I Cost Pricing H 26 J Project Report F, G, I 50arrow_forward
- The activities involved in a project are listed in the following table. Construct the project network and use CPMto find the critical path Ac tivity Content Predece ssor(s) Duration (days) A Initial research B Studysite selection Prepare research plan Contact the surveysite Training staff Prepare the form Field re search Write the re search report Meeting Summary A 2 A 4 B 2 E B, C 3 F C 1 G D, E, F G 5 2 I H 3arrow_forwardOutline the steps involved in identifying the critical path of a project. Briefly describe each step 2. Listed below are tools used for project scheduling. Briefly describe each Time sheets Task lists Shared calendars Automated scheduling tools 3. Answer the following questions about work breakdown structures (WBS). Briefly explain what a WBS is. How does the WBS help determine project deliverables? How does the WBS help determine the sequence of activities on a project?arrow_forwardNeed help don't understand. Please include answers and explanation.arrow_forward
- Give typed full explanation Please answer which figure is correctarrow_forwardProblem 3: Kelly Melford Kelly Melford and her team are working on redesigning a client's home. The client requested Kelly for the project to be completed sooner. Kelly asked her assistant to collect information from her team on the project. Her assistant organized the information she got into a table. The information is given in weeks. Based on the information below, prepare a comprehensive report that includes the following: 3. Your insights on the cost-time trade-off for this project. 4. Your recommended strategy for crashing the project.arrow_forwardI need solve this in project managementarrow_forward
- Your hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table that is attached as an image. a) Draw the network diagram.b) Identify all project paths. Which path is the critical path and why?c) What is the project completion time and total project costs if only normal times are used? Activityarrow_forwardBelow is a project listed in a table with: activity, predecessor, and duration. Activity A B с D E F G H Predecessor none A A с B B D, E, F G Fill in the chart below by filling in: early start (ES), early finish (EF), ☐late start (LS), A late finish (LF), duration (D), and float (F). Then, answer the questions based on the chart. Hint: You can use the Word tools to fill in the chart, or you can draw the chart by hand, then photograph or scan your graph to submit it. 1. Fill in the chart below. B Duration (weeks) C 5 3 8 13 7 9 10 7 - D E F G Harrow_forwardOperation management project management, show all formulas & calculations.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.