a) Calculate each activity duration using the last digit of your student number. For example, if your number is EMBA 2001524, the last digit is 4 and for activity A the duration is 7+1*4=11. b) Draw a project network diagram (AON), given the following information. c) Complete the forward and backward pass, d) Compute free slack and total slack of each activity e) Identify the critical path.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%

Please note that the last digit in the student number is: 4

 

 

Q1) You are creating a customer database for the Lehigh Valley IronPigs
minor league baseball team.
a) Calculate each activity duration using the last digit of your student number.
For example, if your number is EMBA 2001524, the last digit is 4 and for
activity A the duration is 7+1*4=11.
b) Draw a project network diagram (AON), given the following information.
c) Complete the forward and backward pass,
d) Compute free slack and total slack of each activity
e) Identify the critical path.
Activity
Immediate
Duration (Days)
Predecessor
A
7+1*last digit of your student number
В
9+1*Last digit of your student number
A
4+2*Last digit of your student number
D
В, С
5+1*Last digit of your student number
8+1*Last digit of your student number
F
D,E
3+2*Last digit of your student number
G
F
2+1*Last digit of your student number
H
F
1+2*Last digit of your student number
G
8+1*Last digit of your student number
H
10+1*Last digit of your student number
Transcribed Image Text:Q1) You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. a) Calculate each activity duration using the last digit of your student number. For example, if your number is EMBA 2001524, the last digit is 4 and for activity A the duration is 7+1*4=11. b) Draw a project network diagram (AON), given the following information. c) Complete the forward and backward pass, d) Compute free slack and total slack of each activity e) Identify the critical path. Activity Immediate Duration (Days) Predecessor A 7+1*last digit of your student number В 9+1*Last digit of your student number A 4+2*Last digit of your student number D В, С 5+1*Last digit of your student number 8+1*Last digit of your student number F D,E 3+2*Last digit of your student number G F 2+1*Last digit of your student number H F 1+2*Last digit of your student number G 8+1*Last digit of your student number H 10+1*Last digit of your student number
Expert Solution
steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.