Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
Activity |
Time (weeks) |
Immediate Predecessor(s) |
Activity |
Time (weeks) |
Immediate Predecessor(s) |
A |
7 |
− |
E |
4 |
B |
B |
6 |
− |
F |
5 |
B |
C |
4 |
A |
G |
10 |
C, E |
D |
2 |
A |
H |
8 |
D , F |
Part 2
Dave's earliest start (ES) and earliest finish (EF) are:
|
|
|
|
|
|
Part 3
|
|
|
Part 4
|
|
|
Part 5
|
|
|
Part 6
|
|
|
Part 7
|
|
|
Part 8
|
|
|
Part 9
|
|
|
Part 10
Dave's latest start (LS) and latest finish (LF) are:
|
|
|
|
|
|
Part 11
|
|
|
Part 12
|
|
|
Part 13
|
|
|
Part 14
|
|
|
Part 15
|
|
|
Part 16
|
|
|
Part 17
|
|
|
Part 18
The slack times are:
|
|
|
|
Part 19
|
|
Part 20
|
|
Part 21
|
|
Part 22
|
|
Part 23
|
|
Part 24
|
|
Part 25
|
|
Part 26
The activities on the critical path are
B - E - G
.
Part 27
The total project completion time for Dave =
enter your response here
weeks.
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 2 images
- The following estimates of activity times (in days) are available for a small project: Activity Optimistic Most Probable Pessimistic A 4 5.0 6 B 8 9.0 10 C 7 7.5 11 D 7 9.0 10 E 6 7.0 9 F 5 6.0 7 Compute the expected activity completion times and the variance for each activity. An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path.arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B C D Time (weeks) 7 6 2 2 Dave's earliest start (ES) and earliest finish (EF) are: Time Immediate Predecessor(s) Activity (weeks) E 4 6 10 6 A A Activity A B ES 0 0 F G H EF 7 Immediate Predecessor(s) B B C, E D, Farrow_forwardActivities, preceding activities, normal and crashed completion times of each of the activities and crashed costs of activities per week of a project are given in the following table. Activity Preceding Activity Crashed Completion time (week) Normal Crashed Cost Completion Time (week) 7 per week A 7 6. 5 $500 $700 $600 $800 $400 C A 4 3 A, C В, D D, E D 9 E 10 9. F 9 II. Find the slack time of each of the activities and the critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of crashing the project. iv.arrow_forward
- A project consisting of the following activities: Activities predece.Activities day TE M K J H G E C B G KJ G I,F D D E,C B,A| B,A A 1 3 4 6. 5 2 3 9 6 2 4 3 5 1- Draw the network diagram of the project 2- Calculate (Es) and (Lc) the project events 3- Select the critical path 4 - What is the minimum time required to complete the project?arrow_forwardCharlie Cook was able to determine the activity times for constructing his chemical contaminant tracking machine. Cook would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Q Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A B C D 7 8 2 1 Charlie's earliest start (ES) and earliest finish (EF) are: A A Activity A EFGH ES EF 7 5 7 11 8 B B C, E D, Farrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B с D Time (weeks) 5 8 2 1 Immediate Predecessor(s) A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A Activity EFGH ES Time (weeks) 3 EF 5 5 10 7 Immediate Predecessor(s) B B C, E D, Farrow_forward
- Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.arrow_forwardYou lead a family day project for welcoming the arrival of the new students to the campus. The accompanying Table 1 shows the activities, times and sequences required for the project planning and monitoring. Based on the Table 1, using Critical Path Method (CPM) diagram, determine the ES, EF, LS & LF, identify the critical activities, critical path and the expected project completion time.arrow_forwardConsider a project that has been modeled as in the table below. Part a) Draw the PERT/CPM network for this project and determine the project’s expected completion time μP and its critical path. Part b) Suppose the standard deviations of the activity durations are σA = 2, σB = 1, σC = 0, σD = 2, σE = 3, and σF = 0. Then please estimate the standard deviation of the overall project’s standard deviation σP . Part c) Suppose for the standard Normal random variable Z, we know P[−1 ≤ Z ≤ +1] ' 68%, P[−2 ≤ Z ≤ +2] ' 95%, and P[−3 ≤ Z ≤ +3] ' 99.7%. Then, approximately what time T is one for which there is only a less than 2.5% chance for the completion time to beat (be shorter than)? *Please answer a-c and type your work and answers or write them neatly please* Thank youarrow_forward
- 4 01:34:47 The network diagram and task times for a project are shown below. A₁ A2 Late start time A3 Task A₁ A₂ A3 A₁ A5 What is the late start time for activity A3 ? Duration (days) 7 6644 A4 days A5arrow_forwardThe managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. Draw the project network, and compute the expected time and variance for each activity. Develop an activity schedule for this project, compute activity slack time and identify critical path.arrow_forwardBelow is a network diagram that represents a university revamp project. The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the networkarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.