Consider the cash flow of the two projects depicted in Table 3. If WiseGuy Inc. uses payback period rule to choose projects, which of the projects (Project A or Project B) will rank highest?
TABLE 3
Project A Project B
Time 0. -11,000. -10,000
Time 1. 3,000. 4,000
Time 2. 8,000. 3,000
Time 3. 3,000. 10,000
A) Project A
B) Project B
C) Project A and Project B have the same ranking.
D) It cannot calculate a payback period without a discount rate.
7 Consider the cash flow of the two projects depicted in Table 3. If WiseGuy Inc. uses
A) Project A
B) Project B
C) Project A and Project B have the same ranking.
D) It cannot calculate a payback period without a discount rate.
Trending nowThis is a popular solution!
Step by stepSolved in 4 steps with 2 images
- Masulis Inc. is considering a project that has the following cash flow and WACC data. What is the project's discounted payback? WACC: Year 0 Cash flows -$1,225 a. 3.37 years b. 3.63 years c. 1.12 years d. 2.63 years e. 2.37 years 8.75% 1 $575 2 $535 3 $495 4 $455arrow_forwardCase 1: Assume you are evaluating two mutually exclusive projects,the cash flows of which appear below, and that your company uses a cost of capital of 8 percent to evaluate projects such as these. Time Project A Cash Flow Project B Cash Flow 0 -$650 -$700 1 100 300 2 250 -200 3 250 550 4 200 200 5 100 80 a. Calculate the payback of Project A. b. Calculate the discounted payback of Project A. c. Calculate the IRR of Project A. d. Using the NPV method and assuming a cost of capital of 8 percent, which of these projects should be accepted?arrow_forwardplease be soecific w answer pls complete the boxarrow_forward
- The following are the cash flows of 2 projects Year 0, Project A $340, Project B $340 Year 1, Project A $170, Project B $240 Year 2, Project A $170, Project B $240 Year 3, Project A $170, Project B $240 Year 4, Project A $170, Project B Calculate the NPV for both projects if the discount rate is 10% Project A - NPV? Project B - NPV? Suppose that you have can choose only one of these projects. Which would you choose? Project A, B, or niether?arrow_forwardYou are choosing between two projects. The cash flows for the projects are given in the attached table ($miilion) . a. What are the IRRs of the two projects? (A &B) b. If your discount rate is 4.9%,what are theNPVs of the two projects? (A & B) c. Why do IRR and NPV rank the two projects differently?arrow_forwardThere is a project with the following cash flows : Year 0 1 2 1345 Cash Flow -$ 23,350 6,300 7,400 8,450 7,350 5,900 What is the payback period?arrow_forward
- Exercise 24-10 (Algo) Net present value, unequal cash flows, and profitability Index LO P3 Following is information on two alternative investment projects being conside return from its investments. (PV of $1, FV of $1. PVA of $1, and FVA of $1) Note: Use appropriate factor(s) from the tables provided. y Tiger Company. The company requires a 4% Initial investment Project X1 $ (130,000) Project X2 $ (220,000) Net cash flows in: Year 1 Year 2 Year 3 50,000 97,500 60,500 87,500 85,500 77,500 a. Compute each project's net present value. b. Compute each project's profitability index. c. If the company can choose only one project, which should it choose on the basis of profitability index? Answer is complete but not entirely correct. Complete this question by entering your answers in the tabs below. Required A Required B Required C Compute each project's net present value. Note: Round your final answers to the nearest dollar. Net Cash Flowe Present Value of 1 at 4% Present Value of Net Cash…arrow_forwardQUESTION 3 If the cash flows for Project M are CO= -2,000; C1 = +400; C2 = +1,400; and C3= +1,300, calculate the IRR for the project. Please input the percentage format for your answer. And there is no need to put the percentage sign (%).arrow_forwardMAKE SURE YOU ANSWER THIS QUESTION IN EXCEL FORMULA, NOT ALGEBRAICALLY!!!!!arrow_forward
- Consider the following projects: Cash Flows ($) Co -10,000 -20,000 Project D E Assume that the projects are mutually exclusive and that the opportunity cost of capital is 10%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project D E Profitability Index C1 20,000 35,000 b-1. Calculate the profitability-index using the incremental cash flows. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Profitability-indexarrow_forwardUse the table for the question(s) below. Consider the following two projects: Year 0 Project Cash Flow A - 100 40 50 B - 73 30 30 The payback period for project A is closest to: OA. 2.0 years O B. 2.4 years C. 2.2 years O D. 2.5 years Year 1 Cash Flow Year 2 Cash Flow Year 3 Cash Flow 60 30 Year 4 Cash Flow N/A 30 Discount Rate .15 .15arrow_forwardYou are given the following cash flow for a project, and told that PW(8%) = $8,300 for this project. What is the value of the unknown payment X for the second and third periods? n Cash Flow 0 -$36,000 1 $0 2 $X 3 $X O Cannot be determined. O $24,842.08 O $26,829.44 O $5,026.74arrow_forward
- Essentials Of InvestmentsFinanceISBN:9781260013924Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.Publisher:Mcgraw-hill Education,
- Foundations Of FinanceFinanceISBN:9780134897264Author:KEOWN, Arthur J., Martin, John D., PETTY, J. WilliamPublisher:Pearson,Fundamentals of Financial Management (MindTap Cou...FinanceISBN:9781337395250Author:Eugene F. Brigham, Joel F. HoustonPublisher:Cengage LearningCorporate Finance (The Mcgraw-hill/Irwin Series i...FinanceISBN:9780077861759Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan ProfessorPublisher:McGraw-Hill Education