Below is the first set of activities (Phase I) in constructing a new house, the respective time required to finish each activity, and the precedence relations. Activity A Description Clear site Predecessor Duration (in wks) 1 В Bring utilities to the site Excavate Pour Foundation Outside Plumbing Frame House 2 A 1 D 2 E В.С 6 F D 8 G Do electric wiring Lay Floor Lay Roof Inside Plumbing F 3 G 2 F E,H 5 (a) Construct the AON network. (b) Using AOA network, find the critical path/s and the project completion time. Summarize the results in a CPM Table. (c) What event is represented by node 2? Note: labeling starts at 0.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
Below is the first set of activities (Phase I) in constructing a new house, the respective
time required to finish each activity, and the precedence relations.
Activity
A
Description
Clear site
Predecessor Duration (in wks)
1
В
Bring utilities to the site
Excavate
Pour Foundation
Outside Plumbing
Frame House
2
A
1
D
2
E
В.С
6
F
D
8
G
Do electric wiring
Lay Floor
Lay Roof
Inside Plumbing
F
3
G
2
F
E,H
5
(a) Construct the AON network.
(b) Using AOA network, find the critical path/s and the project completion time.
Summarize the results in a CPM Table.
(c) What event is represented by node 2? Note: labeling starts at 0.
Transcribed Image Text:Below is the first set of activities (Phase I) in constructing a new house, the respective time required to finish each activity, and the precedence relations. Activity A Description Clear site Predecessor Duration (in wks) 1 В Bring utilities to the site Excavate Pour Foundation Outside Plumbing Frame House 2 A 1 D 2 E В.С 6 F D 8 G Do electric wiring Lay Floor Lay Roof Inside Plumbing F 3 G 2 F E,H 5 (a) Construct the AON network. (b) Using AOA network, find the critical path/s and the project completion time. Summarize the results in a CPM Table. (c) What event is represented by node 2? Note: labeling starts at 0.
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Site plan requirements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning