Structural Analysis
Structural Analysis
6th Edition
ISBN: 9781337630931
Author: KASSIMALI, Aslam.
Publisher: Cengage,
Bartleby Related Questions Icon

Related questions

bartleby

Concept explainers

Question
Considered the project below
Activity
A
B
C
D
E
F
G
H
I
J
Duration
6
2
9
4
7
5
10
8
3
2
IPA
-
A, B
B
D
D, E
C, F, G
C, G
H. I
Fifteen days after the start of the project. The following information was received:
Activity A: Completed two days later than planned.
Activity B: Completed on time.
Activity C: Started, 4 days left.
Activity D: Completed. It took 5 days to finish.
Activity E: Completed.
Activity F: Cancelled.
Activity G: Started three days late. Project manager hopes to cut one day of its duration.
Activity K: Added. Duration = 4 days. IPA = C.
Activity L: Added. Duration = 3 days. IPA = K, G.
Activity I: Adjusted: IPA = L.
Draw the original network and calculate the CPM values, then check the effect of these updates
and draw the updated network. Calculate the new project completion date. Check if there is any
change on the critical path. And explain what caused the changes, either in the CP or project
.duration
expand button
Transcribed Image Text:Considered the project below Activity A B C D E F G H I J Duration 6 2 9 4 7 5 10 8 3 2 IPA - A, B B D D, E C, F, G C, G H. I Fifteen days after the start of the project. The following information was received: Activity A: Completed two days later than planned. Activity B: Completed on time. Activity C: Started, 4 days left. Activity D: Completed. It took 5 days to finish. Activity E: Completed. Activity F: Cancelled. Activity G: Started three days late. Project manager hopes to cut one day of its duration. Activity K: Added. Duration = 4 days. IPA = C. Activity L: Added. Duration = 3 days. IPA = K, G. Activity I: Adjusted: IPA = L. Draw the original network and calculate the CPM values, then check the effect of these updates and draw the updated network. Calculate the new project completion date. Check if there is any change on the critical path. And explain what caused the changes, either in the CP or project .duration
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Text book image
Structural Analysis
Civil Engineering
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:Cengage,
Text book image
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Text book image
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Text book image
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning