b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's software firm is weeks. (Enter your response as a wholo numbor.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Activity Slack Time (weeks) A B What is the total slack for the non critical path(s) in the project?week(s) (Enter your response as a whole number.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

7

The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each
must precede:
Activity Duration (weeks)
A (start)
Precedes
B, C
6.
F (end)
This exercise contains only parts b, c, and d.
b) The activities on the critical path are
c) The total project completion time for Rafay Ishfaq's software firm is weeks. (Enter your responso as a wholo number.)
d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.)
Activity
Slack Time (weeks)
A
ar
VE
What is the total slack for the non critical path(s) in the project?
wook(s) (Enter your response as a whole number.)
ew
EFF
239w 2
Transcribed Image Text:The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) A (start) Precedes B, C 6. F (end) This exercise contains only parts b, c, and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's software firm is weeks. (Enter your responso as a wholo number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Activity Slack Time (weeks) A ar VE What is the total slack for the non critical path(s) in the project? wook(s) (Enter your response as a whole number.) ew EFF 239w 2
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.