а. Draw a project network. What are the critical activities? c. What activity has the most slack time? d. Will the project be completed by September 1?
Q: i. Discuss the concept of Critical Path in project scheduling? Outline how this is identified and if…
A: 1. Critical Path One of the most often used project planning strategies is the critical route…
Q: Which activity should be crashed to reduce the project completion time by one day? -Activity E…
A: In this given problem, first, calculate the project completion time. There are two possible paths.…
Q: 1. Why is the project schedule important?
A: Project management is the type of management in which finished products are produced using different…
Q: A company's information security blueprint is a project strategy, but how does this happen?
A: A security blueprint can be defined as a comprehensive plan that manages an organization's security…
Q: This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c)…
A: Forward pass: Earliest Start (ES) = Maximum of all predecessor activities (ES = 0 for Start…
Q: 44. What activities make up the critical path? In crashing this project, which activity is the first…
A: Project crashing is the process of reducing the activity duration using additional cost through…
Q: (d) What is the shortest possible time it will take to complete the project?
A: Below is the solution:-
Q: Project is usually a special one-time operation that must be completed over a liraited time period?…
A: Completing a project on schedule benefits the firm in a variety of ways. It assists the organization…
Q: Why are a forward pass and a backward pass needed toproduce a project schedule?
A: Project management is the process of putting processes, techniques, skills, information, and…
Q: Why is getting scope ‘sign-off’ so important in project management? Explain with an example?
A: A scope sign-off sheet refers to the document that is important for formally closing a project or…
Q: This exercise contains only parts b, c, and d. b) The critical activities for the leadership…
A: First we will draw the project network diagram. Initial activities are A, B, and C. After that we…
Q: 1- Calculate the total project time and floats 2- Identify activities on the critical path
A: In this question table data, we have activity information, for each activity, we have been given…
Q: Often circumstances dictate the need to accelerate a project schedule. Describe how crashing and…
A: Smashing and Fast Tracking are plan pressure methods. You apply them to abbreviate your timetable…
Q: Gantt and PERT charts are mostly implemented during project phases. They can be used in order to…
A: Project planning is described as a process or means of completing a project within a specified…
Q: 15F - Estimate how long (total time in months from start to finish, not how many months remain -…
A: THE ANSWER IS AS BELOW:
Q: Determine the critical path, and how many weeks will the project take to complete, suppose D could…
A: To find a critical path, one needs to first find all the possible paths to finish the project from…
Q: d. How much slack is in Activity C? What does this mean? e. How much slack is in Activity E?
A: The critical task is the task that performs the operations on the critical path of the project that…
Q: Task Duration (Weeks) Follows A 3 B 7 A C 9 A D 3 C E 11 B, D F 3 E G 2 F H 3 C F I 5…
A: We use the forward and backward methods to calculate the critical path.
Q: Who creates the project schedule?
A: Project scheduling refers to creating a schedule containing the activities, milestones, and…
Q: You work for a company that makes cell phones and have been made project manager for the design of a…
A: a) Activities Precedence Duration ES EF LS LF Slack P1 — 2 0 2 0 2 0 P2 P1 4 2 6 2 6 0 P3…
Q: What are some reasons project scheduling is not done well?
A: Project is an activity or the set of interrelated tasks that was generated in order to meet the…
Q: a) What is the expected time to complete the project?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: You work for a company that makes cell phones and have been made project manager for the design of a…
A: EST = Early start time LST = Late start time EFT = Early finish time LFT = Late finish time
Q: Explain SEVEN (7) steps for Project Time Management Processes. What is Work Breakdown…
A: 1.) Plan schedule management: - The first step is to remain on the schedule that was planned and…
Q: refers to how the project is expected to work and solve the stated problem in project or proposal…
A: OPTION D is correct - project activities
Q: n the project management plan's work that has to be done section?
A: Effective project management is crucial to the smooth operation of any business. Revenues and costs…
Q: Nhat is the overall duration of the project (in weeks)? 32 weeks Nhat is the earliest week you could…
A:
Q: cts to implement in project man
A: To be a good project manager, one must have a wide range of abilities. It requires a variety of…
Q: d. What is the expected project length? e. What is the slack time for individual activity? f.…
A: The AON diagram as per the given information is as follows:
Q: "-1" SV indicate the project is behind schedule. Select one: True False
A: Positive shows that the undertaking is running in front of endorsed plan. Negative implies that the…
Q: a.How would you explain Project? One time activity to solve a problem b. Describe what happens…
A: Note: - Since the exact question that has to be answered is not specified, we will answer only the…
Q: Why is the critical path important? Why would a task be on the critical path? 2) What is the role…
A: Hi, we are supposed to answer one question at a time. Since you have not mentioned which question to…
Q: b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's…
A: THE ANSWER IS AS BELOW:
Q: Define slack time and its effects on a project schedule.
A: Slack time is a term which is used to refer to the period of time to which a project might be…
Q: 2. Find the critical path. What is the earliest time that the project can be completed?
A: From the following table the critical path can be ascertained: ACTIVITY EXPECTED TIME…
Q: What is the probability of completion of the project before week 42
A:
Q: Calculate the start and finish times for each activity. (Leave no cells blank - be certain to enter…
A: Below is the solution:-
Q: Organizing a project, and developing a scope, budget and schedule are examples of technical skills…
A: A project manager is a person who works in the project management area. He or she is in charge of…
Q: A. If activity B were delayed by 2 days, how long can activity G be delayed without delaying the…
A: Given data is
Q: Define what a WBS is relative to project planning, and the importance of the WBS in a project plan.
A: Work breakdown structure (WBS) is a technique for finishing a complex, multi-step project. It's a…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 1 images
- 3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…Q3: What is Critical Path Analysis? Explain with the help of a suitable example.What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL CRASH TIME (DAYS) TIME (DAYS) 8 7 7 6 6 6 9 6 NORMAL COST 400 1,100 700 900 1,200 CRASH COST 550 1,300 800 1,250 1,950 IMMEDIATE PREDECESSOR(S) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $ whole number). A, B C (enter your response as a
- 1) Management at Kirkland Machine Tool Co. is considering the development of a new automated drill press called the Auto Drill. After conferring with the design engineers., the controller's staff assembled the following data about this project. Target selling price $ 7,500.00 Desired profit percentage 25% of total unit cost Projected unit demand 4500 units Activity-based cost rates Materials handling activity 5% of raw materials and purchased parts cost Engineering activity $300 per unit for Auto Drill Production and assembly activity $50 per machine hour Delivery activity $570 per unit for Auto Drill Marketing activity $400 per unit for Auto Drill Per unit data Raw Materials cost $ 1,620.00 Purchased parts cost $ 840.00 Manufacturing labor hours 6 hours Hourly rate $…1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?Q2(a) Choong Machinery specializes in developing grass cutting equipment. Mr Ahmad, who is an R&D engineer in the company, is contemplating the construction of a machine that would cut grass on narrow rivers and waterways. The activities that are necessary to build one of these experimental grass- cutting machines are listed in the following Table Q2.1. Activity times are in weeks. Table Q2.1: List of Activities Immediate Activity Time Predecessor (weeks) A 6 В 5 C A 3 D A 2 E В 4 F В 6. С, Е D, F G 10 H 7 Q2(a)(i) Construct a project network with earliest start, earliest finish, latest start and latest finish Q2(a)(ii) Determine the critical path(s) of this project network Q2(a)(iii) What happens to the project completion time, if activity D is delayed by 2 weeks and activity B is delayed by 1 week? Give your comments.
- Q4/ The table below shows the duration and direct costs for the activities of a construction project. It is required to caleculate the duration of the project that achieves the lowest possible total cost using the technique of crashing if the indirect costs are 20% from direct cost. Normal Time (NT) Normal Cost (NC) S Crash Time Crash Cost Activity (CT) weeks (CC) S weeks A 6. 1000 3. 7000 В 4 9000 5 10000 C 3 6000 1 10000 D 4 8000 2. 11000 E 6. 1000 4 13000 5 6. D A 3 End Start 6. B EQ1: Given the information below, draw the network (AOA) and find the probability of finishing the job in (40) weeks? Solve using PERT. Activity notation Weeks 1-2 2-3 2-4 2-5 3-6 4-7| 5-7 6-8 7-8 8-9 2,7,8 5,6,9 3,7,8 4,5,6 6,9,10 6,8,11 4,6,7 5,7,10 4,8,9 4,7,9 [50%]2.0 Give an example of Critical Path Analysis of one (1) Method.
- 2.1: For each of the following projects, determine the shape of its life cycle (S or J): SOLUTION (Answer just near the name of the project) • Building a nuclear station for electrical power generation– • Achieving an ILETS minimum score – • Organizing a wedding party – • Getting a masters degree in engineering management –2. Given the data, answer the questions below. Activity Normal Time Normal Cost Crashed Time Crashed Cost (weeks) (Pesos) (weeks) (Pesos) 1-2 12 30,000 7 50,000 2-3 8 20,000 35,000 2-4 4 40,000 3 70,000 3-4 4-5 4 5,000 1 11,000 4-6 12 500,000 9. 710,000 5-6 4 5,000 1 11,000 6-7 4 150,000 220,000 750,000 1,107,000 a. Suppose the project needs to be completed within 30 weeks, how much extra cost will be incurred to finish the project by this time? Which activity/ies must be crushed? b. If the project duration is reduced down to the minimum time possible, what is the total number of crashed weeks? How much extra cost will this require?Explain all parts Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity Description ImmediatePredecessor Time(weeks) A Survey building site 5 B Develop initial design 9 C Obtain board approval A, B 13 D Select architect C 3 E Establish budget C 5 F Finalize design D, E 14 G Obtain financing E 11 H Hire contractor F, G 9 A) Draw a project network. (Submit a file with a maximum size of 1 MB.) B) Identify the critical path. (Enter your answers as a comma-separated list.) C) Develop the activity schedule for the project. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F G…