a) The correct precedence relationship with one of the possible assignment of tasks to workstations is shown in Fig. 2 b) The operating efficiency of the assembly line with 5 workstations shown in the figure chosen above = % (enter your response as a percentage rounded to one decimal place).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 56 boats. Given the following information:

| Task | Performance Time (mins) | Predecessors |
|------|------------------------|--------------|
| A    | 1                      | -            |
| B    | 2                      | A            |
| C    | 2                      | A            |
| D    | 2                      | A, C         |
| E    | 1                      | C            |
| F    | 2                      | C            |
| G    | 1                      | D, E, F      |
| H    | 2                      | B, G         |
| I    | 2                      | G, H         |

**Questions:**

a) The correct precedence relationship with one of the possible assignment of tasks to workstations is shown in Fig. 2.

b) The operating efficiency of the assembly line with 5 workstations shown in the figure chosen above = ___% (enter your response as a percentage rounded to one decimal place).

**Diagrams:**

- **Figure 1, Figure 2, and Figure 3**: Each figure displays a different network of tasks with nodes connected by arrows indicating the order of operations. Nodes labeled with task letters correspond to tasks listed in the table. Arrows show which tasks need to precede others.

- **Figure 2 Explanation**: Tasks are arranged to reflect correct precedence relationships. Arrows indicate the flow from one task to the next based on the table's predecessor information.

The objective is to ensure that the tasks are correctly sequenced to optimize the assembly process and meet the daily demand.
Transcribed Image Text:The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 56 boats. Given the following information: | Task | Performance Time (mins) | Predecessors | |------|------------------------|--------------| | A | 1 | - | | B | 2 | A | | C | 2 | A | | D | 2 | A, C | | E | 1 | C | | F | 2 | C | | G | 1 | D, E, F | | H | 2 | B, G | | I | 2 | G, H | **Questions:** a) The correct precedence relationship with one of the possible assignment of tasks to workstations is shown in Fig. 2. b) The operating efficiency of the assembly line with 5 workstations shown in the figure chosen above = ___% (enter your response as a percentage rounded to one decimal place). **Diagrams:** - **Figure 1, Figure 2, and Figure 3**: Each figure displays a different network of tasks with nodes connected by arrows indicating the order of operations. Nodes labeled with task letters correspond to tasks listed in the table. Arrows show which tasks need to precede others. - **Figure 2 Explanation**: Tasks are arranged to reflect correct precedence relationships. Arrows indicate the flow from one task to the next based on the table's predecessor information. The objective is to ensure that the tasks are correctly sequenced to optimize the assembly process and meet the daily demand.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.