Q3: The activities involved in the construction of a certain project are given in the table below. One resource type will be used during the contract. Determine the minimum level of the resource required to complete the project. Dependency Duration Number of Activity Description (Days) Labours (Unit/Day) A 2 3 B A 4 3 C A 6 4 D A 9 4 B 5 3 B, C 7 2 D, E, F 3 4 E F G

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter13: Pricing Subcontractors' Work
Section: Chapter Questions
Problem 2RQ
icon
Related questions
Question
Q3: The activities involved in the construction of a certain
project are given in the table below. One resource type will be
used during the contract. Determine the minimum level of the
resource required to complete the project.
Activity
Dependency
Duration
Number of
Description
(Days)
Labours
(Unit/Day)
A
2
3
B
A
4
3
C
A
6
4
D
A
9
4
E
B
5
3
F
B, C
7
2
G
D, E, F
3
4
Transcribed Image Text:Q3: The activities involved in the construction of a certain project are given in the table below. One resource type will be used during the contract. Determine the minimum level of the resource required to complete the project. Activity Dependency Duration Number of Description (Days) Labours (Unit/Day) A 2 3 B A 4 3 C A 6 4 D A 9 4 E B 5 3 F B, C 7 2 G D, E, F 3 4
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Tax significance of depreciation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,