5. Suppose that Dara manufactures 4 products: A, B, C and D. output and cost da for period just ended are as follows: 3 Output units 10 10 100 100 Number of production runs in the period hour rate) 225 2. ABC 2 2 5 Direct labor cost per hours: $5 Overhead costs Short-run variable costs Set-up costs Expediting and scheduling costs Materials handling costs 14 Material cost per unit 20 80 20 80 Direct labor hours per unit 1 3 1 3 Machine hours per un S 3,080 10,920 9,100 7,700 30,800 Required Prepare unit costs for each product using: 1. Conventional absorption costing, (Assume that, in the traditional absorption costing system, overheads are a direct lab 1 3 1 3

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 5PB: Wrappers Tape makes two products: Simple and Removable. It estimates it will produce 369,991 units...
icon
Related questions
Question
5. Suppose that Dara manufactures 4 products: A, B, C and D. output and cost data
for period just ended are as follows:
A
B
с
D
Output units
10
10
100
100
Number of production
runs in the period
hour rate)
2
2
5
Direct labor cost per hours: $5
Overhead costs
Short-run variable costs
Set-up costs
Expediting and scheduling costs
Materials handling costs
2. ABC
5
14
Material cost
per unit
20
80
20
80
Direct labor
hours per unit
1
3
1
3
Machine
hours per unit
$
3,080
10,920
9,100
7,700
30,800
▪ Required
Prepare unit costs for each product using:
1. Conventional absorption costing,
(Assume that, in the traditional absorption costing system, overheads are a direct labor
1
3
1
3
Transcribed Image Text:5. Suppose that Dara manufactures 4 products: A, B, C and D. output and cost data for period just ended are as follows: A B с D Output units 10 10 100 100 Number of production runs in the period hour rate) 2 2 5 Direct labor cost per hours: $5 Overhead costs Short-run variable costs Set-up costs Expediting and scheduling costs Materials handling costs 2. ABC 5 14 Material cost per unit 20 80 20 80 Direct labor hours per unit 1 3 1 3 Machine hours per unit $ 3,080 10,920 9,100 7,700 30,800 ▪ Required Prepare unit costs for each product using: 1. Conventional absorption costing, (Assume that, in the traditional absorption costing system, overheads are a direct labor 1 3 1 3
Expert Solution
steps

Step by step

Solved in 4 steps with 8 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College