2. In the CPM network, the critical path has six activities. Their durations are tabulated next. Activity Optimistic Most Likely A C Q S N K 3 4 5 3 7 4 5 8 7 5 10 5 Pessimistic 6 13 8 7 15 8 Compute the following: a. The probability that the project will finish by the end of day 36 b. The probability that the project will finish by the end of day 39 c. The probability that the project will finish before day 38 d. The probability that the project will finish on the 35th day e. The completion date with at least a 95% confidence level.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
icon
Concept explainers
Question
This is an engineering project management question
2. In the CPM network, the critical path has six activities. Their durations are tabulated next.
Activity
Optimistic
Most Likely
A
C
Q
S
N
K
3
4
5
3
7
4
55555
10
Pessimistic
6
13
8
7
15
8
Compute the following:
a. The probability that the project will finish by the end of day 36
b. The probability that the project will finish by the end of day 39
c. The probability that the project will finish before day 38
d. The probability that the project will finish on the 35th day
e. The completion date with at least a 95% confidence level.
Transcribed Image Text:2. In the CPM network, the critical path has six activities. Their durations are tabulated next. Activity Optimistic Most Likely A C Q S N K 3 4 5 3 7 4 55555 10 Pessimistic 6 13 8 7 15 8 Compute the following: a. The probability that the project will finish by the end of day 36 b. The probability that the project will finish by the end of day 39 c. The probability that the project will finish before day 38 d. The probability that the project will finish on the 35th day e. The completion date with at least a 95% confidence level.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Knowledge Booster
Budget estimating
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning