Consider the following table:
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
to tml tp te
A --- 2 3 4
B --- 4 7 10
C A 1 2 3
D B 2 5 8
E B 4 6 8
F C , D 1 1 1
G E 3 4 5
H G , F 3 6 15
1. Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]
2. By using ES, EF, LF, LS, find the slack of each activity and the critical path. Show times on network!
3. Find the completion time ( ) and the standard deviation (σ) for the project— round off the standard deviation to the nearest hundredth: two decimal places.
4. What is the completion time at 68% and 99.7% confidence levels?
5. What is the likelihood of this project being completed in less than 23 days?
6. Between 23 and 26 days?

Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 1 images

- Ha Beyonce has started a new musical service automating the release of her key venture. Other pop stars are interested in how it works. Beyonce has asked you to analyze it from a project management angle, addressing the questions below. B(3) D(5) F(4) A(7) (G(5) C(4) (E(2) a. Find the critical path. O A-B-D-F-G O A-B-D-E-G O A-C-D-E-G O A-C-D-F-G BTS provided the following table with information you need to solve this problem. Note: times are shown in days ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST 6. ם00 ,$7 5,000 9,000 3,000 2,000 $ 8,000 7,000 10,200 4,500 4 D 4 E 3,000 F 2 4,000 5,000 7,000 8,000 4arrow_forwardExample 2.39 Table 2.119 provides normal and crash times as well as normal and crash costs for the activities of a project. Table 2.119 Project activity details Activity Normal Time (Weeks) Normal Cost (Lakhs) Crash Time (Weeks) 1-2 3 5 2-3 4 8 2-4 3 4 2-5 8 S 3-6 4 3 4-6 6 2 5-7 5 10 6-7 3 7 1 3 2 7 2 4 4 1 Crash Cost (Lakhs) 9 14 6 6 5 3 14 10 Project Network Analysis-1 | 141 (a) Draw the network and find the critical path. (b) Using the above information, crash or shorten the activities step by step until the shortest duration is reached. MMM, VI Sem, Mumbai Univ, 2006arrow_forwardRequired: Develop a schedule for hiring new employees. What is thetotal cost of this schedule?arrow_forward
- Give typed full explanation of botharrow_forwardI need help with part d. Bragg's Bakery is building a new automated bakery in downtown Sandusky. Here are the activities that need to be completed to get the new bakery built and the equipment installed. ACTIVITY PREDECESSOR NORMAL TIME (WEEKS) CRASH TIME (WEEKS) EXPEDITING COST per WEEK A — 9 6 $ 3,000 B A 8 5 3,500 C A 15 10 4,000 D B, C 5 3 2,000 E C 10 6 2,500 F D, E 2 1 5,000 b-1. Identify the critical path. A-C-E-F A-B-D-F A-C-D-F b-2. What is the normal project length? 36 weeks c. What is the project length if all activities are crashed to their minimum? 23 weeks d. Bragg's loses $3,500 in profit per week for every week the bakery is not completed. How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3,500 for each week crashed? I need help with this question. Thank you!arrow_forwardPlease don't provide handwriting solutionarrow_forward
- ed from online tutor od 1. Use the assignment method to determine the best way to assign workers to jobs, given the following cost information. Compute the total cost for your assignment plan. JOB A B C 5 8 6 2 Worker 6 9 7 3 5 S 4 PROB 1 Tarrow_forwardColonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilitíes. The following activities would have to be undertaken before construction can begin. Immediate Time Activity Description Predecessor (weeks) A Survey building site B Develop initial design 9. Obtain board approval А, В 14 D Select architect Establish budget 5 F Finalize design D, E 16 G Obtain financing E 12 Hire contractor F, G 6 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File) no file selected This answer has not been graded yet. (b) Identify the critical path. (Enter your answers as a comma-separated list.) (c) Develop the activity schedule for the project. Earliest Latest Finish Latest Earliest Activity Slack Start Start Finish A В D E F (d) Does it appear reasonable that construction of the athletic complex could…arrow_forwardK Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) ABCDEFG B A, D C E, F Time (days) 2 7 2 10 4 5 8 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G c) The project length for the leadership training program development project = days.arrow_forward
- M.arrow_forwardb) – Draw the Activity-on-Node (AON) diagram using the following representation for every node: Activity Description Expected Time ES EF LS LF Slack C.) Complete the following table, determine the expected time of completion assuming that the project starts at week 0 (zero) and identify the critical path for this project. Demonstrate all your calculations. On Critical Path? Activity Activity Description ES EF LS LF Slack Yes or No Locate new facilities 2 Order furniture Interview prospective staff Hire and train staff 3 4. Remodel facilities Receive and set up furniture Move in and start up 6 7 a) Complete the following table, calculate the project variance and project standard deviation. Demonstrate all your calculations.arrow_forwardRoss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels Time (weeks) Time (weeks) Immediate Predecessor(s) CE Activity A B C D E F a 4 1 9 5 1 6 m 9 9 14 6 2 9 b 10 24 18 10 4 21 Immediate Predecessor(s) A A A B C, E Activity a 3 2 G H 1 J K a) The expected (estimated) time for activity C is weeks. (Round your response to two decimal places) b) The variance for activity C is weeks. (Round your response to two decimal places) c) Based on the calculation of the estimated times, the critical path is 7 6 3 m 3 2 7 8 3 D 4 2 7 12 4 F F D. G. H 1.J d) The estimated time for the critical path is weeks. (Round your response to two decimal places) e) The activity variance along the critical path is weeks (Round your response to two decimal places) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 40 weeks or less is (Enter as a probability…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.