Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new
gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilitíes. The following activities
would have to be undertaken before construction can begin.
Immediate
Time
Activity
Description
Predecessor
(weeks)
A
Survey building site
B
Develop initial design
9.
Obtain board approval
А, В
14
D
Select architect
Establish budget
5
F
Finalize design
D, E
16
G
Obtain financing
E
12
Hire contractor
F, G
6
(a) Draw a project network. (Submit a file with a maximum size of 1 MB.)
Choose File)
no file selected
This answer has not been graded yet.
(b) Identify the critical path. (Enter your answers as a comma-separated list.)
(c) Develop the activity schedule for the project.
Earliest
Latest
Finish
Latest
Earliest
Activity
Slack
Start
Start
Finish
A
В
D
E
F
(d) Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project
with the site survey and initial design plans? What is the expected completion time for the project?
The expected completion time is
weeks, which is --Select-
than 1 year.
expand button
Transcribed Image Text:Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilitíes. The following activities would have to be undertaken before construction can begin. Immediate Time Activity Description Predecessor (weeks) A Survey building site B Develop initial design 9. Obtain board approval А, В 14 D Select architect Establish budget 5 F Finalize design D, E 16 G Obtain financing E 12 Hire contractor F, G 6 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File) no file selected This answer has not been graded yet. (b) Identify the critical path. (Enter your answers as a comma-separated list.) (c) Develop the activity schedule for the project. Earliest Latest Finish Latest Earliest Activity Slack Start Start Finish A В D E F (d) Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project? The expected completion time is weeks, which is --Select- than 1 year.
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.