preview

Assignment 2 Final

Better Essays

INSE 6230 — Fall 2014 Total Quality Project Management Assignment #21 – Submission Date: November 17October 20, 2014 Submitted by: Maria Azuelo – Student #: 70976809 Md Safwan Bin Alam – Student #: 7012128 Submitted to: Dr. Amin Hammad Assignment #21 Exercises: Chapter 6: Exercises4 1. Using Figure 6-2, enter the activities, their durations (in days), and their relationships in Project 2010. Use a project start date of August 3, 2009. View the network diagram. Does it look like Figure 6-4? Print the network diagram on one page. Return to the Gantt chart view. Click View on the menu bar, select Table: Entry, and then click Schedule to re- create Table 6-1. You may need to move the split bar to the right to reveal all of the …show more content…

Assume that Student 2 earns 70 percent on each of the exams, 80 percent on the homework, and 95 percent on the group project. Assume that Student 3 earns 90 percent on Exam 1, 80 percent on Exam 2, 75 percent on Exam 3, 80 percent on the homework, and 70 percent on the group project. You can use the weighted scoring model template, create your own spreadsheet, or make the matrix by hand. Exercises: Chapter 7: Exercises5 . Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. 
 PV = $23,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? d. Use the SPI to estimate how long it will take to finish this project. e. Sketch the earned value chart for this project, using Figure 7-5 as a guide. 3. Create the same WBS described in Exercise 2 using Microsoft Project 2010 and indenting categories appropriately. Use the outline numbering feature to display the outline numbers, or enter the numbers

Get Access