‘’Cost performance on project s often poor, what are the possible causes of this and how can it be improved?’’
Introduction
The cost planning is one of important phases for project management. It will goes through whole project’s life cycle. It is foundation of project and it will tell the project are measured, reported and controlled in every process. Estimating is the process of forecasting or approximating the time and cost of completing project deliverables.
A successful project management will include time control and cost planning. Accompany with these two important features, and then bring out the best quality project.
Causes of poor cost performance
According to many decades’ records, Morris et al. (1989) has researched more
…show more content…
In project management, contract almost related with every level of project, such as material buying, price negotiation, customer service and payments. Supplier is another important role in project management. If contractor could give a appropriate contact to supplier, it will helps on build stable relationship, with supplier, even more, it could bargain with price of materials. However, if contract not finish at each single phases of project, it will increase negotiation time, which means definitely time delay and cost overruns. With decent contract management of project, it will simply to avoid such fundamental problems. Another explanation for contract error is worker. Human resource is also important for basic project proceeding, and it has been included in contract management as well. Similarly, all potential possibilities need considered by manager. “careful consideration need to be finished when forming the initial contract, for about what might occur during its operation, this will guarantee that things are included in the contract documents that enable effective contract management”(OGC 2010)
Mega project management
Complexity could another reason for bad cost performance. The most of mega project, such as project Comanche, could be defined as complexity. When estimating mega project, it always will be affected by some errors, for instance inflation, exchange rates, change
592 Week 1 DQ 1 WBS Construction PROJ 592 Week 1 DQ 2 Project Cost Estimates and Assumptions PROJ 592 Week 2 DQ 1 Cost Components PROJ 592 Week 2 DQ 2 Estimating Processes PROJ 592 Week 3 DQ 1 Project Schedules PROJ 592 Week 3 DQ 2 Sensitivity Analysis PROJ 592 Week 4 DQ 1 Resource Allocation and Leveling PROJ 592 Week 4 DQ 2 Advanced Schedule Techniques PROJ 592 Week 5 DQ 1 Earned Value Calculation PROJ 592 Week 5 DQ 2 Project Monitoring and Control & EV PROJ 592 Week 6 DQ 1 Forecasting Project Completion Cost PROJ 592 Week 6 DQ 2 Project Control PROJ 592
The cost, team size and LOC are measured on the bases of COCOMO model. It is a constructive cost mode. Effort of the project is calculated by the help of algorithm models. One of these models which are widely used is COCOMO model. For the cost estimation of any project, COCOMO (constructive cost model) is used. This model was developed by Boehm in 1981. There are three versions of the COCOMO which are listed below:
After setting the entire project to 40% complete on Oct 1, 2008 we can see that the project is behind schedule. The schedule variance of the entire project is $ (736,599) and Schedule performance index is at 0.68, which indicates that for every $1.00 spent in the project we are only getting $0.68 worth of work done. Since we do not have actual cost data, the MS Project calculates the budget is under budget by a negligible $80.
Projected cash flows – always things will never take the direction that is planned. Evidently, the profit margins are very small, however when the expected cash flows drop by just a small percent the project will not make profits.
When considering factors that didn’t go well as far as schedule the project took a steep hit. While the initial item started on time, it ended two days later than was initially planned. This meant that “Set product Specs” was 2 days late starting. With this project each line item has a predecessor. This means that they cannot start until the previous item is finished. With this every portion of the project was late starting and threw the entire project off. With regards to the cost “Need Survey” was over budgeted by $6,400 and “Set product spec” was over budgeted by $11,520.
We used PV (planned Value), AC (actual cost), and EV (earned value) to calculate SPI (schedule performance index), SV (schedule variance), CPI (cost performance index), and CV (cost variance). Among these indicators, SPI and SV show whether a project is behind schedule or not, and CPI and CV indicate whether a project is under budget. Therefore, the statuses of the schedule and cost of technical infrastructure, software customization, and combined projects can be easily and clearly checked, respectively.
2) An organization's budget estimating process routinely misses the actual cost of a project by 25%. For the most recent project, the budget variance was a ridiculous 23%, but this must be considered common cause variance.
Essentially, with the current cost system, the managerial analysis is highly flawed due to a lack of crucial in-depth cost information, as indicated by:
Cost controlling means amending the cost of project by monitoring project status and controlling variation of the cost base line. From this case, I found that some methods were done for the cost change. The methods are list as following:
Essentially, with the current cost system, the managerial analysis is highly flawed due to a lack of crucial in-depth cost information, as indicated by:
ABI is using a top-down process in this project, meaning that determination of the final budget comes almost strictly from a compilation of experiences and judgments of the top and mid-level managers in the company. The higher-level managers break down costs into major categories, pass down their cost estimates to the next lowest level, lower-level managers break the major categories down into subcategories and so on until the estimation process reaches the lowest level of the company. By the end, each level knows the specific amount of money that it is allotted to complete the project tasks required at that level. Because the project is so extensive in price and risk, it would have been smarter for them use a bottom-up process which would have involved the employees who would actually be part of the work team so that management could get a more accurate estimate of the time and money that would be required to complete the project.
I was also, surprised when we created the first cost with no any supporting documents of the how we got to that figure. Based on my personal life experience and after working for a long time, I understand by experience that I can come up with a closer budget to any similar project that I had already executed in the past. It is also true that we use some techniques through which we can calculate the resources for the similar projects. Unfortunately, in our current environment, it is not the case. Do you remember when we are executing the job and repeating for several times? It is normal we come up to the point that we can manage the next similar project effortlessly.
In order to succeed in managing a project, the project manager needs to know how to make cost calculations, estimate resources required for the project, develop cost spreadsheets, use cost management templates etc. Project Cost management is a series of activities for estimating, allocating, and controlling the costs in a project. It allows a business to predict coming expenses in order to reduce the chances of it going over budget. Project cost management includes the processes required to ensure that the project is completed within an approved budget. Projected costs are calculated during the planning phase of a project and must be approved before work begins. As the project plan is executed, expenses are documented and tracked so things stay within the cost management plan. Once the project is completed, predicted costs vs. actual costs are compared, providing benchmarks
According to an accounting textbook, cost is defined as a resource sacrificed or foregone to achieve a specific objective. It is something given up in exchange. It is necessary for project managers to understand project cost management since project costs money and consumes resources.
In field of project management, there are a plethora of mechanisms under perpetual reevaluation. One specific segmentation of project management under such scrutiny pertains to cost duration, which is the time and monetary costs of completing individual tasks within the project’s critical path (IBM Knowledge Center, 2016). The process of monitoring and evaluating the time and financial impacts of each task is referred to as cost duration analysis (IBM Knowledge Center, 2016). A chief concern of cost duration analysis is identifying tasks within the project’s critical path which can reduce project duration (PMI, 2013). A common approach to reducing a project’s duration is task “crashing” (PMI, p.181). According to The Project Management Institute (2013) crashing refers to the process of methodical determining the financial value of increasing a critical path task’s resources in order to decrease project duration (p.181).