The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC’s president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.
The Project Priority Matrix for the Blue Zuma Project is:
Time Scope Cost
Constrain X
Enhance X
Accept X
Part 1
You are a member of a project team assigned to develop the new razor scooter code named “Blue Zuma.” Table A2.5 contains the information necessary to create a project schedule. For the purpose of this case …show more content…

Explain your choices as well as the reasons for not choosing other options.
2. How have these changes affected the sensitivity of the network?
Include a Gantt chart with a schedule table presenting the new schedule.
Note: You cannot go back and relevel resources. These new resources are only available for the stated specific tasks according to the schedule created at the end of Part 2.
Part 4
Robin Lane and top management have approved the schedule generated at the end of Part 3. Save the file containing this schedule as a baseline schedule.
Prepare a memo that addresses the following questions:
1. How much is the project estimated to cost?
2. What activity is estimated to cost the most to complete?
3. What resource commands the greatest total cost?
4. During which month of the project are the highest and lowest costs expected to occur? What are those costs?
5. What likely costs are not contained in this budget?
Include a table containing the estimated costs for each activity and a cash flow schedule for each month of the project.
Part 5
Today’s date is August 16, 2008. Table A2.8 summarizes the information regarding activities accomplished to date.
Robin Lane has requested a written status report for the Blue Zuma project.
1. Your status report should include a table containing the PV, EV, AC, BAC,
EAC, SV, CV, and CPI for each activity and the whole project. The report should also address the