You're managing a project using the earned value management for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual cost (AC) is $150,000. What is the cost variance (CV) for the project?

Survey Of Economics
10th Edition
ISBN:9781337111522
Author:Tucker, Irvin B.
Publisher:Tucker, Irvin B.
Chapter6: Proudction Costs
Section: Chapter Questions
Problem 8SQP
icon
Related questions
Question

You're managing a project using the earned value management for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual cost (AC) is $150,000. What is the cost variance (CV) for the project?

 


 

a.

-50,000

b.

100,000

c.

-100,000

d.
150,000
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Cost of Production
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Survey Of Economics
Survey Of Economics
Economics
ISBN:
9781337111522
Author:
Tucker, Irvin B.
Publisher:
Cengage,
Micro Economics For Today
Micro Economics For Today
Economics
ISBN:
9781337613064
Author:
Tucker, Irvin B.
Publisher:
Cengage,
EBK HEALTH ECONOMICS AND POLICY
EBK HEALTH ECONOMICS AND POLICY
Economics
ISBN:
9781337668279
Author:
Henderson
Publisher:
YUZU
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning