urrently the manufacturer has eight machines that operate on a two-shift (eight hours each) basis. Twenty days per year are available for cheduled maintenance of equipment. Assume there are 250 workdays in a year. Each manufactured good takes 20 minutes to produce. a. What is the effective capacity of the factory? Round your answer down to the nearest whole number and use this answer in subsequent computations. units/year b. Given the five-year forecast, how much extra capacity is needed each year? Round your answers to the nearest whole number. Year 1 2 3 Extra capacity needed (units) c. Does the firm need to buy more machines? If so, how many? When? If your answer is zero, enter "0". Round your answers up to the nearest whole number. Year Additional machines needed 1 2 3 4 5 5
Q: How can organizations ensure that their continuity plans remain up-to-date and effective in the face…
A: Ensuring that continuity plans remain up-to-date and effective in the face of evolving risks and…
Q: At Dominos pizza the time study restaurant yielded an average observed time of 4.0 minutes. The…
A: The standard time of the company shows the predefined amount of time that a company has to complete…
Q: 2-a. Using the least-squares regression method, estimate the variable etching cost per unit and the…
A: First, let me state the given data, WeekUnits or XTotal etching cost or…
Q: Professor Herman compares the “standard” frame of diversity, equity, and inclusion with the…
A: Professor Herman believes that the main components of the traditional frame of diversity, equality,…
Q: Consider the following information for a project to add a drive-thru window at Crestview Bank. a.…
A: a) d. option D is correct. It shows the network with correct predecessors for each activity Other…
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: Critical Path Method is a project management method that is used to plan, schedule, and manage…
Q: Use the following project status information to calculate each of the requested EVM numbers below…
A: Given,Task Budget Cost Budget Duration Status as of Week 13A $5,000 2…
Q: Explain how I
A: IoT refers to the interconnected network of physical devices, vehicles, and appliances, embedded…
Q: Company Z is just starting to make a brand new product it has never made before. It has completed…
A: Time taken by the First unit =29 hoursTime taken by the Second unit =22 hours
Q: Your small toy manufacturing facility has the following information: Fixed costs $39,000 Material…
A: Fixed costs$39,000Material cost per toy $0.888Electricity cost per toy $0.044Labor cost per toy…
Q: What is the importance of risk assessment in the development of continuity plans?
A: Risk assessment is a crucial stage in the development of any organization's continuity plan.…
Q: Waldo sells pre-packaged lunches to construction workers at a Peachtree Street construction site…
A: Order quantity refers to the number of goods that a company should order at a given point in time to…
Q: In Continuous manufacturing system, we need: O Highly skilled labours and special machine tools…
A: A continuous manufacturing system creates an environment, where we will see the continuous flow of…
Q: Once stock has been received, it must then be transported to the appropriate storage or operational…
A: The process of physically transporting products or inventory within a supply chain or facility setup…
Q: Question 3. Given the probabilities for each of the options happening, complete the Expected…
A: Here, there are a total of two alternatives, and the options are "Motel approved" and "Motel…
Q: How does the Wilson approach contribute to minimizing holding costs and ensuring optimal order…
A: The Wilson Approach is a well-established inventory management technique that minimizes holding…
Q: Explain the following project situations using just the following schedule and cost information:…
A: Project Performance Metrics:Project performance metrics are quantifiable measures used to assess…
Q: To ensure a balanced use of advertising media, radio advertisements must not exceed 50% of the total…
A: For this question, first, I will formulate the Linear programming model, Then, I will solve this LP…
Q: 1. A firm is considering the decision of investing in new plants. The following is the profit payoff…
A: State of economyAlternativeexpandcontractunchangedNo new plant$20 million- $3 million$4 million1 new…
Q: Auto pistons at Wemming Chung's plant in Shanghai are produced in a forging process, and the…
A: Find the given details below:
Q: Describe the key performance indicators (KPIs) and metrics used to measure the success of system…
A: For measuring the success of system management initiatives, we will consider Key Performance…
Q: Since the early 1980's business activities, personnel have been right size and/or down sized due to…
A: The business world has seen an impeccable growth and evolution when it comes to the technology that…
Q: Security clearances (none, confidential, secret, top secret)? Group of answer choices: Nominal…
A: Business information helps the organization in identifying as well as mitigating risks. The risk can…
Q: d. How many customers, on average, are waiting in line in front of each service desk? e. How much…
A:
Q: Year Season Sales 2018 Winter 40 2018 Spring 29 2018 Summer 31 2018 Fall 40 2019 Winter 102 2019…
A: Find the given details below:
Q: based on the attached article McKinsey’s analysis has found companies that invest in innovation…
A: Product development is the process that starts with making a final product available in the market…
Q: Which party is usually the receiver of the shipment as named on the official shipping documents?…
A: Shipping and logistics act as significant players in providing the efficient shipment of products…
Q: Analyze the factors organizations should consider when deciding whether to lease or purchase…
A: The decision to lease or buy hardware resources is crucial for organizations because it affects…
Q: How does containerization (e.g., Docker) impact system management, and what are its advantages and…
A: Containerization, exemplified by technologies like Docker, has revolutionized system management and…
Q: What are the primary objectives of a continuity plan?
A: A continuity strategy, also known as a business endurance blueprint (BEB) or an uninterrupted…
Q: A division of the Winston Furniture Company manufactures dining tables and chairs. Each table…
A: TablesChairs AvailableFeet of wood 40163,200Labor hour34520Profit $45$22
Q: Which of the following is a main characteristic of operation when applied to a queuing system? O…
A: (A) The population is the queuing system's prospective clientele. It has nothing to do with how the…
Q: Explain the key components of a business continuity plan (BCP
A: A Business Continuity strategy (BCP) is a documented strategy that outlines how a company expects to…
Q: Analyze the concept of BYOD (Bring Your Own Device) in the context of IT resource acquisition and…
A: With the help of the BYOD policy, employees can bring their personal devices for work purposes, such…
Q: conduct a critical evaluation and research to identify two operational risks that led to the…
A: Operational risk is a significant concern for financial institutions worldwide, and when not managed…
Q: A janitorial service, Mother’s Helpers, provide workers to clean office buildings during late…
A: Workers with 2 skill levels are available:Level 1 Level 2Level 1Level 2Wages…
Q: Analyze a specific product or service that utilizes persuasive technology. How does it leverage…
A: Persuasive technology refers to the application of digital technology or systems to change people's…
Q: Explain the concept of Customer Service Management (CSM) in CRM and its role in improving customer…
A: In order to provide outstanding customer support and service, customer relationship management (CRM)…
Q: Discuss the ethical considerations associated with continuity planning, such as prioritizing the…
A: Continuity planning is based on the practice of establishing and sustaining a strategy to make sure…
Q: The mean absolute deviation based on a 2-month moving average of March through December is
A: 2-month simple moving averageThe forecast for a period is based on the average of the actual data of…
Q: The Carbondale Hospital is considering the purchase of a new ambulance. The decision will rest party…
A: A 2-year-moving average is based on a forecasting tool that concludes the average demand of the…
Q: What are the key components of a business continuity plan (BCP) for a large multinational…
A: It is crucial to be able to continue running businesses through crises and unanticipated…
Q: EOQ, reorder point, and safety stock Alexis Company uses 937units of a product per year on a…
A: Find the given details below:
Q: Your
A: Environmental and resource efficiency policies and procedures are crucial documents that guide…
Q: What are the best practices for implementing service-level agreements (SLAs) in service-oriented…
A: Implementing Service-Level Agreements in service-oriented systems requires careful planning and…
Q: How does capacity planning contribute to effective system management, and what factors should be…
A: Effective system management relies on capacity planning because it provides the framework for…
Q: Consider the following information for a project to add a drive-thru window at Crestview Bank. a.…
A: Project completion time refers to the duration that is taken by a company to finish a specific…
Q: The time to deliver packaged containers by a logistics company is found from samples of size 4. The…
A: Solution :From the given data :n=4, μ = 140 hours , standard deviation = σ = 6 hours (a) Find the 2…
Q: GreenzTech Inc. is planning on installing a new computerised accounting system. For this project,…
A: The Critical Path Method (CPM) is a process that is operated to plan, schedule, and manage difficult…
Q: Marty's Barber Shop has one barber. Customers have an arrival rate of 2.2 customers per hour, and…
A: Find the given details below:
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
- A bicycle component manufacturer produces hubs for bike wheels. Two processes are possible for manufacturing, and the parameters of each process are as follows: Process 1 Production rate Daily production time Process 2 35 parts/hour 4 hours/day 20% 15 parts/hour 7 hours/day 9% Percent parts rejected Assume that the daily demand for hubs allows all defect-free hubs to be sold. Select the process that maximizes profit per day if each part is made from $4 worth of material and can be sold for $30. Both processes are fully automated, and variable overhead cost is charged at the rate of $40 per hour.Old Pueblo Engineering Contractors creates six-month “rolling” schedules, which are recomputed monthly. For competitive reasons (it would need to divulge proprietary design criteria, methods, and so on), Old Pueblo does not subcontract. Therefore, its only options to meet customer requirements are (1) work on regular time; (2) work on overtime, which is limited to 30 percent of regular time; (3) do customers’ work early, which would costan additional $5 per hour per month; and (4) perform customers’ work late, which would cost an additional $10 per hour per month penalty, as provided by their contract. Old Pueblo has 25 engineers on its staff at an hourly rate of $30. The overtime rate is $45. Customers’ hourly requirements for the six months from January to June are January 5000 February 4000 March 6000 April 6000 May 5000 June 4000 Develop an aggregate plan using a spreadsheet. Assume 20 working days in each month. 12. Alan Industries is expanding its product line to include three…Kilmer Company's customer demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units: Actual run tine this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 1-a. Utilization rate 1-b. Efficiency rate. 1-c. Quality rate 1-d. Overall equipment effectiveness 2-a. Utilization loss in units 12,800 minutes 16,000 minutes. 2-b. Efficiency loss in units 2-c. Quality loss in units 6.30 units per minute. 9 units per minute. Required: 1. and 2. With respect to the company's overall equipment effectiveness, calculate the following: Note: Do not round intermediate calculations. Round final answers to 2 decimal places and "Units" answers to the nearest whole number. 72,576 units 80,640 units
- Jefferson Company's demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units. 4,900 minutes 7,000 minutes 3.8 units per minute 4.0 units per minute 15,827 units 18,620 units Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) Required: 1. Compute the utilization rate. (Round your answer to 2 decimal places.) 2. Compute the efficiency rate. (Round your answer to 2 decimal places.) 3. Compute the quality rate. (Round your answer to 2 decimal places.) 4. Compute the overall equipment effectiveness (OEE). (Do not round intermediate calculations. Round your final answer to 3 decimal places.) Utilization rate Efficiency rate Quality rate Overall equipment effectivenessJefferson Company’s demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units. Actual run time this week 6,106 minutes Machine time available per week 8,600 minutes Actual run rate this week 4.32 units per minute Ideal run rate 6.00 units per minute Defect-free output this week 11,315 units Total output this week (including defects) 15,500 units 1. Compute the utilization rate.2. Compute the efficiency rate. 3. Compute the quality rate. 4. Compute the overall equipment effectiveness (OEE).Acme, Corp. produces and sells tennis rackets. Each tennis racket is sold for $150 and average total costs per racket are $125, $100 of which are variable. Acme's fixed costs total $10,000 per month. What is Acme's unit contribution margin? A. $50 B. Neither of these C. $25
- Prevost Chemicals manufactures an industrial solvent at its only processing plant. A liquid chemical and labor are the two primary inputs. All other resources are included in manufacturing overhead. The plant never has any work-in-process or finished goods inventories. Information from the previous four periods of production follows: Chemical input (gallons) Labor input (hours) Solvent sales (gallons) Average price of chemical per gallon Average wage rate per hour Average sales price per gallon Manufacturing overhead (total) Required A Required B Required C Required: a. Compute the partial productivity measures for chemical for the four periods. b. Compute the partial productivity measures for labor for the four periods. c. Compute the total factor productivity for the four periods. Complete this question by entering your answers in the tabs below. Period Period 1 125,000 12,500 110,000 Period 1 $ 2.00 28.00 10.26 236,000 Compute the partial productivity measures for chemical for the…XYZ Leather Company manufactures and sells two products, wallets and belts, in its two-department plant. Operating data pertaining to the two products are as follows: Wallets Belts Selling price per unit P30 P50 Cost per unit: Variable manufacturing costs P8 P15 Variable marketing costs P2 P3 Fixed manufacturing costs P5 P5 Fixed marketing costs P6 P1 Cutting Finishing…A company that makes shopping carts for supermarkets and other stores recently purchased somenew equipment that reduces the labor content of the jobs needed to produce the shopping carts.Prior to buying the new equipment, the company used five workers, who produced an average of80 carts per hour. Workers receive $10 per hour, and machine cost was $40 per hour. With the newequipment, it was possible to transfer one of the workers to another department, and equipment costincreased by $10 per hour while output increased by four carts per hour.a. Compute labor productivity under each system. Use carts per worker per hour as the measure oflabor productivity.
- A company that makes shopping carts for supermarkets and other stores recently purchased somenew equipment that reduces the labor content of the jobs needed to produce the shopping carts.Prior to buying the new equipment, the company used five workers, who produced an average of80 carts per hour. Workers receive $10 per hour, and machine cost was $40 per hour. With the newequipment, it was possible to transfer one of the workers to another department, and equipment costincreased by $10 per hour while output increased by four carts per hour.a. Compute labor productivity under each system. Use carts per worker per hour as the measure oflabor productivity.b. Compute the multifactor productivity under each system. Use carts per dollar cost (labor plusequipment) as the measure.c. Comment on the changes in productivity according to the two measures, and on which one youbelieve is the more pertinent for this situation.A process requires a 20 second setup for each batch. When producing, the process can produce one unit every 12 seconds. Demand for the product is 7 units per minute. With a batch size of 20 units, what is the process utilization? Note: Do not round your intermediate calculations. Round your answer to 2 decimal placesKilmer Company's customer demand for its only product exceeds its manufacturing capacity. The company provided the following information for the machine whose limited capacity is prohibiting the company from producing and selling additional units: Actual run time this week Machine time available per week Actual run rate this week Ideal run rate Defect-free output this week Total output this week (including defects) 1-a. Utilization rate 1-b. Efficiency rate. 1-c. Quality rate 1-d. Overall equipment effectiveness 2-a. Utilization loss in units 2-b. Efficiency loss in units 2-c. Quality loss in units 23,310 minutes 25,900 minutes 0.90 8.00 units per minute 10 units per minute Required: 1. and 2. With respect to the company's overall equipment effectiveness, calculate the following: Note: Do not round intermediate calculations. Round final answers to 2 decimal places and "Units" answers to the nearest whole number. 149,184 units 186,480 units