Consider the network below. Activity durations are given in nodes. What is latest finish date (LFD) of activitv H ? Select one: a. 23 b. 24 c. 25 d. 26
Q: Products or technologies that have not been tested against customer needs do not generate value. A.…
A: In today's competitive market landscape, every organization must understand customer needs, Knowing…
Q: Memorial College is considering building a new multipurpose athletic complex on campus. The…
A: A project with 8 activities is given below:ActivityPredecessorDuration in…
Q: How does supply chain integration help companies respond more effectively to changes in customer…
A: Supply chain integration is the process of creating an efficient system that prevents delays,…
Q: K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute…
A: A project has the following activities:ActivityPredecessor ActivitiesDuration…
Q: Discuss the relative merits of internal versus external recruitment. Give an example of a situation…
A: The objective of this question is to understand the advantages of internal and external recruitment…
Q: The FastMart convenience store is deciding on the optimal mix of the number of 2-liter bottles of…
A: Linear programming is a mathematical technique used for optimization of a linear objective function,…
Q: Discuss the role of knowledge management in organizational capacity building.
A: Knowledge management (KM) is instrumental in enhancing organizational capacity by facilitating the…
Q: Style Options → Higher Functionality 1 2 X Lower Functionality x Line 1 X X Line 2 3 1 2 3 X X X X X…
A: Line 2 offers products with Style Options 1 and 2 across all functionality levels.It does not offer…
Q: A firm with sales of $510,000 has average inventory of $380,000. The industry average for inventory…
A: Sales = $510,000Average inventory = $380,000Inventory turnover = 3 times a year
Q: Ralf Bohle GmbH, a German manufacturing company, produces bicycle and wheelchair tires under the…
A: The objective of the question is to calculate the process capability index, the probability of a…
Q: The following company sells two family of products. The company begins its roll-up forecast…
A: Find the given details below:
Q: A local bakery produces two popular items weekly: chocolate cakes and apple pies. The profit for a…
A: The objective of this question is to determine the optimal production plan for a bakery that…
Q: A large sporting goods store is placing an order for bicycles with its supplier. Four models can be…
A: The information regarding 4 types of bikes are given below:Adult Open TrailAdult City ScapeGirl's…
Q: Management Decision Systems (MDS) is a consulting company that specializes in the development of…
A: Find the given details below:
Q: The desired daily output for an assembly line is 300 units. This assembly line will operate 575…
A:
Q: Write your position regarding the importance of human capital management to achieve organizational…
A: “Since you have posted multiple questions, we will provide the solution only to the first question…
Q: An avant-garde clothing manufacturer runs a series of high-profile, risque ads on a billboard on…
A: A Pareto chart is a graphical representation of information that shows the recurrence of events in…
Q: Managers can serve customers, but you have to hire part-time servers to provide good customer…
A: manager can hire trained servers and managers so it's more productive for the organization and…
Q: a) As an Operation Manager, list down at least five possible things you should do inorder to…
A: The first part of the question is asking for ways to motivate employees beyond monetary incentives.…
Q: ANSWER THE B PART. ONLY THE SUMMISSION MEMO.Preparing your Event Communications: Communication…
A: The objective of this question is to develop a timeline and communication strategy to support the…
Q: how does the project life cycle contribute to effective resource management and budget control?
A: The project life cycle refers to the stages of a project that must be completed efficiently. It…
Q: Various financial data for the past two years follow: Output: Sales Input: Labor Raw Materials…
A: The objective of this question is to calculate the total productivity measure for a company for two…
Q: How does technology support value stream mapping activities, such as software tools and digital…
A: Value stream mapping, is the process of visualizing the data and important actions involved in…
Q: Describe the steps used to develop a forecasting sy
A: It is important to develop an effective and robust forecasting system. It is an iterative process…
Q: Phillip Witt, president of Witt Input Devices, wishes to create a portfolio of local suppliers for…
A: Given details:Shut down cost $ 4,00,000Probability of Super event0.5%Probability of a Unique…
Q: Discuss, How does procurement contribute to innovation and product development within organizations?
A: Supply chain management is the aspect of management that deals with all the movement or flow that…
Q: SE with moving average = 146.94 incorrect MSE with exponential smoothing with alpha = 0.2 = 10.86…
A: WeekTime series value119214317412518615
Q: How can companies use scheduling to improve resource utilization and minimize idle time?
A: In project management, scheduling is the process of listing out tasks, deliverables, and project…
Q: How does organisational culture play a role to stop concerns of "quiet quitting"?
A: A calm ending emerges when experts feel drawn out, confounded, or isolated from their work or the…
Q: The manager of the deli section of a grocery superstore has just learned that the department has 112…
A:
Q: Acme Manufacturing makes a variety of household appliances at a single manufacturing facility. The…
A: Linear programming helps us to find the optimal solution/best outcome, given the constraints. We…
Q: A manufacturer of kitchen appliances is preparing to set the price on a new blender. Demand is…
A: Total cost is the sum of a fixed cost and a variable cost that helps cover the goods and services…
Q: e,xplore the intricate significance of cross-functional alignment in the context of human resource…
A: Integration of Business Objectives: Cross-functional alignment guarantees that planning for human…
Q: On a sunny May morning, Marc Binton, CEO of Bay Area Automobile Gadgets (BAAG), enters the…
A: A decision tree is a flowchart-like structure in which each internal node represents a "test" on an…
Q: Consider the following linear program: Max 1A + 2B 1A <5 1B < 5 2A + 2B = 12 Show the…
A: Find the given details below:Objective Function:Constraints:Subject to
Q: Data collected on the yearly registrations for a Six Sigma seminar at the Quality College are shown…
A: Let me state the given data, YearRegistrations1525334651169778991310161117Here, I will apply a…
Q: A manager must decide how many machines of a certain type to purchase. Each machine can process 100…
A: The objective of the question is to determine the break-even point for each range of machines and to…
Q: 14 Community General Hospital finds itself treating many bicycle accident victims. Data from the…
A: To find: The exponentially smoothed forecast for day 4 and day 5 using the given data and alpha…
Q: Johnson is an estate agent and he has been asked by his client to sell for him three products A,B…
A:
Q: Question 1. Narrow the focus of each of the following broad topics so that they each signal the use…
A: The objective of the question is to narrow down the broad topics using the Analysis by Division…
Q: Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha…
A: Critical path method is project management tool (others e.g WBS, PERT). It uses flow chart of…
Q: explain the key components of operations planning in a manufacturing environment.
A: Operations planning is a critical aspect of manufacturing management, involving the strategic…
Q: .Explore the intricate significance of cross-functional alignment in the context of human resource…
A: Cross-cultural organization is the aspect of the organization that deals with a company that works…
Q: Centerville Bikes and Stuff (CBS) sells motorcycles and accessories. The number of helmets sold by…
A: Let me state the given data, WeekValue118211314410517612Here, I will use the three-week moving…
Q: Explain the major step involved in a supply chain management?.
A: A supply chain is an arrangement of interdependent systems, resources, capacities, and technologies…
Q: Sampling 4 pieces of precision-cut wire (to be used in computer assembly) every hour for the past 24…
A: 3-sigma control limits, also known as three standard deviation limits, are statistical boundaries…
Q: A. Choudhury's bowling ball factory in Illinois makes bowling balls of adult size and weight only.…
A: Statistical process control (SPC)is applying statistical techniques to determine whether a process…
Q: To generate value it is best to link IT strategy as closely as possible to business strategy. A.…
A: Every business should consider information technology and integrate the same in such a way, So, the…
Q: PERSON CENTERED PLANNING 8. The person you support makes a life choice that you do not think is…
A: The person-centered planning is a process that is choir to the person and their special needs,…
Q: In regards to the OPCF 43 limited waiver of depreciation endorsement, what is the insured NOT…
A: The Limited Waiver of Depreciation Endorsement is a type of add-on coverage that can be included in…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
- 2:30 PM ě 0.3KB/s 1ll 54 4G+ 00:15:12 Remaining Multiple Choice The primary difference between PERT and CPM is that CPM uses probabilities on the activity times and PERT does not. O. PERT considers activity costs and CPM does not. PERT can assign probabilities to activity times and CPM does not. CPM considers activity costs and PERT does not. 5 of 20 IINormal Time Problem 1 You are the manager of a project to improve a billing process at your firm. The following table contains the data you will need to conduct crashing of the project duration. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12. Activity Immediate Predecessor(s) Crash Time (weeks) Normal (Direct) Cost Crash Cost (weeks) ($) ($) A 4 1 5,000 8,000 B 5 2 8,000 11,000 C A 1 1 4,000 4,000 Ꭰ B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F Ꭰ 7 6 4,000 7,000 What is the optimum choice for project duration?7. The project information for the custom order project of the Air Control Compa presented here. Draw a project network for this project. Compute the early and activity times and the slack times. Identify the critical path. ID Description Predecessor Time Order review None Order standard parts Produce standard parts Design custom parts Software development A 3 A 10 A 13 A 18 Manufacture custom hardware C,D 15 Assemble Test B, F E, G 10 5 ABCD EFGH ||
- 1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,1. Using Microsoft Excel TM prepare a Gantt Chart for the following project. Activity Predecessor(s) Duration (Days) 1. Forming the problem statement 2. Identifying functional requirements 3. Identifying constraints and limitations 4. Defining a schedule 5. Defining the design parameters 6. Identifying alternatives 7. Evaluating and analyzing alternatives 8. Select a solution 9. Gather supplies 10. Construct prototype 11. Test performance 12. 1 1 1 1 1 2,3 1 2 1 2 7 1 8 4 10 1 Redesign 13. 11 2 Demonstrate solution to 12 1 class 5 CO
- Activity Predecessor Activities Normal Crashed Duration (Days) Cost ($) Duration Cost ($) KA - 5 2000 3 5600 LB - 7 3000 4 7800 MC A 10 4000 7 6100 ND AB 11 5000 8 8000 PE B 6 2400 4 3600 RF C 8 3000 6 5100 QG C,D,E 4 4200 1 3000 SH E,G 5 5500 3 2500 What is the ES for Activity G and and LS for activity F?Time Immediate Time Immediate Activity (weeks) Predecessor(s) Activity (weeks) Predecessor(s) A 7 4 7 B 3 11 C, E 1 7 D.F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF 7 B 10 7 E 11 G 22 20 Dave's latest start (LS) and latest finish (LF) are: Activity LS LF H 15 G 11 F 9 E 7 D 14 A The slack times are: Activity Slack A D E F G H The activities on the critical path are The total project completion time for Dave = weeks.Activity A B CDEFG 3. You have been appointed as the project leader of a project to be undertaken by your company. You have identified the following tasks and made the time estimates for each task as listed in the table below: с Preceding "from" activity A A A B,C C,D,E F Succeeding "to" activity B,C,D E E F F G Estimated duration work days) 3 5 3 10 8 14 7 a) Use the above table to construct a project network diagram. b) Determine the critical path for the project and its duration.
- 7. The project information for the custom order project of the Air Control Company is presented here. Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical path. ID Description Predecessor Time A Order review None 2. 3 Order standard parts Produce standard parts Design custom parts Software development A 10 D. 13 18 Manufacture custom hardware 15 Assemble В, F 10 H. Test E, G You houo nignod a contract to huild a garage for the Simpsons You will receive a D F AAACActivity (day) Predecessor(s) A 6 none B 5 none C 3 A D 2 A E 1 B F 7 C G 9 D E, H 11 F,G 1. Draw the network diagram 2. Determine the critical path 3. Find earlist and latest time of each event of the project in the network diagramb) Table Q1a shows the logic for a particular project. Time (days) Activity A Precedence 2 В A 3 C A 4 D A E B 3 F B,C H E 5 F 4 J H 3 G,H, I J,K K 4 L Table Q1a. Logic for project activities A through L. (i) Construct a Network Diagram showing the various logical activity relationships from this information. (ii) Perform a forward and backward pass completing the activity boxes. (ii) Highlight the critical path on your diagram and state the earliest project completion time. c) Provide an example of an ethical dilemma in engineering project management and explain how a code of ethics might be used to help the project manager in the decision making process.