Interpretation: The expected time and variance in task A is to be calculated.
Concept Introduction:
PERT diagram is a graphical project management tool used to organize and analyze project and it’s activity. It defines time duration for a project and also for each activity in a project.
Explanation of Solution
The estimated task time can be computed by adding optimistic time, mostly likely time multiplied by 4, and pessimistic time. Then, divide the attained value with 6. The optimistic time is 3 days, mostly likely time is 4 days, and pessimistic time is 10 days of task A.
Hence, the estimated time in task A is 4.8 days
Variance in task time:
The variance in task time computed by deducting optimistic time from pessimistic time and divided by six. Then, completely square the attained value. The optimistic time is 3 days, and pessimistic time is 10 days of task A.
Hence, the variance in task A time is 1.36 days.
The project management has two techniques that is critical path method and program Evaluation Review technique. In program evaluation review technique the project’s optimistic time, mostly likely time, and pessimistic time are combined together in to single expected value. This expected value signifies expected time of project’s task.
Want to see more full solutions like this?
Chapter 7 Solutions
Practical Operations Management
- An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 6. What is its expected activity time and variance? 3.67; 1 O 4.33; 1 O 3.33; 0.44 O 4; 0.44arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process a Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Activity Immediate Predecessor(s) ABCDEFG long dash- long dash- ABCDEFG A B C D, E E Normal Time Crash Time Normal Cost Crash Cost (weeks) (weeks) ($) ($) 1 14,000 2 3,000 1 40,000 3 22,000 1 8,000 4 13,000 2 16,000 3234 1 6 63 7,000 3,000 12,000 12,000 8,000 5,000 9,000 a. What is the shortest time duration for this project regardless of cost? (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? C. What is the total time of the minimum cost schedule? (enter your response as whole numbers). The total project's duration according to minimum cost schedule is? The minimum cost schedule…arrow_forwardThe Cove at UP is looking to open a new location. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. \ tasks predecessors task duration start 0 A start 7 B A 20 C A 34 D B 39 E C,D 6 F D 15 G E,F 33 end G 0 Guillermo has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: \ Metric Description ES Early start time for task EF Early finsh time for task LS Late start time for task LF Late finsh time for task TS Total slack for task FS Free slack for task IS Independent slack for task SS safety slack for task Please provide the CPM result for each of the following metrics: ES_{end} = LS_{D} = TS_{D} = EF_{G} = LF_{G} =arrow_forward
- After the first month of a project, the Actual Cost was $400 and the planned cost for the first month was $500. Currently, only 50% of the work have been completed. Based on this information, calculate the following: a.Earned Value b.Cost Variance c.Schedule Variancearrow_forwardA project consist of 5 activities A,B,C,D,E with ES, EF, LS and LF of A (0, 6, 9, 15); B (0, 7, 0, 7); C (6, 13, 15, 22); D (7, 13, 7, 13); E (13, 22, 13, 22). Normal Time (in month), Crash time (in month), Normal cost (in million Rp), Crash cost (in million Rp) from each activity are A (6, 4, 20, 24); B (7, 5, 30, 35); C (7, 6, 10, 13); D (6, 4, 20, 26); E (9, 8, 88, 90) a. What activities are in the critical path? How long is the project duration? b. If we want to crash the project for 2 months, what activities need to be crashed? How much additional cost required?arrow_forwardA project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 169, what is the probability that the project will be completed within 224 days? O 0.50 O 0.84 0.80 O 0.78arrow_forward
- Consider the following project activities with a normal unit: (The normal unit is Day) Activity Name Immediate Predecessor (list number/ name, separated by ‘,’) Normal Time A 6 B A 2 C A 4 D B, C 3 E D 1 F D 7 G E 4 H F, G 2 I F 6 J I 1 K H, J 5 Fill the following table: Activity Name Activity Time Earliest Expected Competition Time (TE) Latest Expected Competition Time (TL) Slack (TL-TE) A 6 B 2 C 4 D 3 E 1 F 7 G 4 H 2 I 6 J 1 K 5 Project Completion Time = Days The Critical Path is=arrow_forwardKelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: Time (days) Activity a 3 5 3 4 1 2 7 TH 3 10 10 ABCD E F G H I K 61 525DE5 13 m Activity A 3 7 11 15 9 This exercise contains only part a. a) Based on the activity time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places.) b 9 5 3 8 5 13 49127 13 Immediate Predecessor(s) Expected Time C B, D A, E A, E F G C H, I Variancearrow_forwardDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 44 33 $ 2 comma 100$2,100 $ 2 comma 700$2,700 long dash— B 22 11 $ 2 comma 200$2,200 $ 2 comma 900$2,900 long dash— C 33 33 $ 500$500 $ 500$500 long dash— D 88 44 $ 2 comma 500$2,500 $ 2 comma 820$2,820 A E 66 33 $ 1 comma 000$1,000 $ 1 comma 300$1,300 B F 33 22 $ 3 comma 400$3,400 $ 4 comma 800$4,800 C G 44 22 $ 1 comma 500$1,500 $ 2 comma 000$2,000 D, E Part 2 a) Based on the given information…arrow_forward
- Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table: Activity Normal Time (days) Crash Time (days) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 6 $6,000 $6,400 B $1,200 $3,000 C 11 $4,000 $6,000 a) Activity that should be crashed first to reduce the project duration by 1 day is b) Activity that should be crashed next to reduce the project duration by one additional day is c) Total cost of crashing the project by 2 days = $_____ (Enter your response as an integer.) 7 4 2 9 A B ---arrow_forwardSsus and the management at yankee ltd. Want an expected time and variance for pest control activity and for that optimistic time was 2 weeks , pessimistic time was 8 weeks and most likely time is 4 weeks ?arrow_forwardA large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. Description Survey Soils report C Traffic design D Lot layout E Approve design Illumination G Drainage H Landscape I Signage J Bid proposal ID A B The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity C is: Predecessor None A A A B, C, D E E E E F, G, H, I Time (days) 13 22 21 a 9 74 20 20 22 17 15 12 days. day(s).arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.