Concept explainers
a)
To determine: The time taken for the 5th liver transplant.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
b)
To determine: The time taken for first 5 transplants.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
c)
To determine: The time taken for the 18th liver transplant.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
d)
To determine: The time taken for all 18 transplants.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Want to see the full answer?
Check out a sample textbook solutionChapter E Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
- TOYS AND JOB DESIGN AT THE HOVEY AND BEARD COMPANY The following is a situation that occurred in the Hovey and Beard Company, as reported by J. V. Clark. This company manufactured a line of wooden toys. One part of the process involved spray painting partially assembled toys, after which the toys were hung on moving hooks that carried them through a drying oven. The operation, staffed entirely by women, was plagued with absenteeism, high turnover, and low morale. Each woman at her paint booth would take a toy from the tray beside her, position it in a fixture, and spray on the color according to the required pattern. She then would release the toy and hang it on the conveyor hook. The rate at which the hooks moved had been calculated so that each woman, once fully trained, would be able to hang a painted toy on each hook before it passed beyond her reach. The women who worked in the paint room were on a group incentive plan that tied their earnings to the…arrow_forwardGive at least 3 examples of jobs that requires Work Measurement and give a brief explaination.arrow_forwardInclude a synopsis of the prerequisites for training and certification, as well as some examples derived from real-life scenarios.arrow_forward
- Include a summary of the requirements for training and certification, as well as some examples taken from real-world events.arrow_forwardFor a time study of a health insurance claims-adjusting process, the analyst uses the continuous method of recording times. The job is divided into four work elements. Shown in Figure are the performance rating factors, RF, and the continuous method recorded times, r, for each work element.a. Calculate the normal time for this job. b. Calculate the standard time for this job, assuming that the allowance is 20 percent of the normal time. c. What is the appropriate sample size for estimating the time for element 2 within {10 percent of the true mean with 95 percent confidence?arrow_forwardA Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available. Observation: 1 2 3 4 5 Task time (seconds): 82 74 80 88 76 (a) What is the actual average time for this task? (b) What is the normal time for this task if the employee worked at a 10% faster pace than is typical for adequately trained workers? (c) What is standard time for this task if allowances sum to 12%? (d) If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not…arrow_forward
- Describe the idea behind the term "procedure." What makes a process different from a planned activity?arrow_forward1)We are undergoing a major refurbishment of our kitchen and we have new equipment being installed and other equipment being altered. What are the time requirements for hazard identification when changes are made to the workplace? There are three. 2)What records allow you to determine who has done what WHS training in kitchen safety? 3)You want to continually monitor your kitchen WHS processes and make recommendations for changes if required. Which reports will help you achieve this? List four. Questions from Implement & Monitor work health & safety practices1)We are undergoing a major refurbishment of our kitchen and we have new equipment being installed and other equipment being altered. What are the time requirements for hazard identification when changes are made to the workplace? There are three. 2)What records allow you to determine who has done what WHS training in kitchen safety? 3)You want to continually monitor your kitchen WHS processes and make recommendations…arrow_forwardInclude a summary of the training and certification requirements, as well as some real-world examples.arrow_forward
- Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 10 transplants under great scrutiny and at no cost to the patients with the hospital picking the expenses. The cost per hour of surgery is estimated to be $4,800. The very first transplant, just completed, required 27 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: a) the 10th transplant hours (round your response to two decimal places). b) The cost of 10th surgery to Beth Zion Hospital = $ c) the first 10 transplants d) The cost of all 10 surgeries to Beth Zion Hospital = $ whole number). Learning Curve Coefficients Unit Number (N) 10 Unit Time .385 hours (round your response to two decimal places). 75% Total Time 5.589 (round your response to the nearest whole number). Unit Time .477 (round…arrow_forwardA worker-machine operation was found to involve 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study. The worker's time-averaged 1.9 minutes per cycle, and the worker was given a rating of 120% (machine rating is 100%). Midway through the study, the worker took a 10-minute rest break. Assuming an allowance factor of 12% of work time, determine the standard time for this job. Hints: you should consider both machine time and machine time together. Also, Allowance only applies to the man, not a machine.arrow_forwardJob design determinations an employee’s work-related responsibilities. The point of departure when designing jobs for employees is to determine the level of specialisation. Write an explanation of not longer than one to one-and-a-half pages on job specialisation which include the following aspects (with suitable examples to support your answer): 1. What is job specialisation? 2. What is the purpose of job specialisation? 3. What are the limitations and benefits of job specialisation?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.