Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
12th Edition
ISBN: 9780134741062
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter D, Problem 14P
A
Summary Introduction
Interpretation:the objective function and constraints for maximize the contribution to profits
Concept Introduction:Objective functions are the linear functions and the equalities or inequalities are the constraints. It is the condition of an optimization of problem.
B
Summary Introduction
Interpretation:using the computer package, the interpretation is to be solved.
Concept Introduction:Objective functions are the linear functions and the equalities or inequalities are the constraints. It is the condition of an optimization of problem.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A manufacturing plant produces a product 'A' that requires one unit of 'B' and ½ unit of 'C'. Each unit of 'B' is comprised of one unit of 'D', two units of 'E', and one unit of 'F'. Each unit of 'C' requires ½ unit of 'G' and three units of 'H'. The manufacturing lead times for the components are as follows: 'A' - two weeks, 'B' - one week, 'C' - two weeks, 'D' - two weeks, 'E' - three weeks, 'F' - one week, 'G' - two weeks, 'H' - one week. There are 20 units in stock for each of these components. 100 units of 'A' are needed for delivery in seven weeks: a) Develop the product structure and indexed bill of materials for the product. b) Create a gross and net requirements plan for the manufacturer of the product.
A small shoe manufacturer makes two styles of shoes: oxfords and loafers. Two machines are used in the process: a cutting machine and a sewing machine. Each type of shoe requires 15 min per pair on the cutting machine. Oxfords require 10 min of sewing per pair, and loafers require 20 min of sewing per pair. Because the manufacturer can hire only one operator for each machine, each process is available for just 8 hours a day.
Set up a system of linear inequalities that describes the number of pairs of each style of shoes that the manufacturer can produce within required working hours.
bama pie company's assembly line operations (the assembly line operates for six hundred minutes per day) comprise of eleven tasks, with the longest task time being 2.4 minutes and the shortest task time being 0.4 minutes; the sum of the task times is eighteen minutes. the firm is working on balancing its assembly line operations. the firm needs to produce 200 pies per day; to achieve this, the firm calculates the required cycle time as ---- minutes?
Chapter D Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A machine used for cutting materials in a factory has the following outputs per hour at various speeds and required periodic tool regrinding at intervals cited. Speed Hour Output per Tool RegrindingA 200 pieces every 8 hours B 280 pieces every 5 hours A set of tools costs 560 and can be ground twenty times. Each regrinding costs 54.00 and the time needed to regrind and change tools is 1 hour. The machine operator is paid 35.00 per hour including the time the tool is changed. The tool grinder who also sets the tools to the machine is paid 40.00 per hour. The hourly rate chargeable against the machine is 38.00, regardless of machine speed. Which speed is more ecomical? A. Speed B, 0.096/pc B Speed B, 0.087/pc C. Speed A, .054/pc D. Speed A >037/pcarrow_forwardA machine tool company conducts a job-training programme at a ratio of one for everyten trainees. The training programme lasts for one month. From past experience it has been found thatout of 10 trainees hired, only seven complete the programme successfully. (The unsuccessful traineesare released). Trained machinists are also needed for machining. The company's requirement for thenext three months is as follows:January: 100 machinists, February: 150 machinists and March: 200 machinists.In addition, the company requires 250 trained machinists by April. There are 130 trained machinistsavailable at the beginning of the year. Pay roll cost per month is:Each trainee Rs. 400/- per month.Each trained machinist (machining or teaching): Rs. 700/- p.m.Each trained machinist who is idle: Rs.500/- p.m.(Labour union forbids ousting trained machinists). Build a l.p.p. for produce the minimum costhiring and training schedule and meet the company’s requirement.arrow_forwardConsider a two-step process that handles three types of customers. Each resourceis staffed by one employee. Type 1 customers spend 5 minutes at resource 1 and 2 minutesat resource 2. Type 2 customers also spend 5 minutes at resource 1, but spend 10 minutes atresource 2. Finally, type 3 customers spend no time at resource 1 and 8 minutes at resource2. Each hour, the demand is 10 customers of type 1, 4 customers of type 2, and 2 customers oftype 3. Where in the process is the bottleneck? What is the flow rate for each customer type?arrow_forward
- A company produces three products A,B, and C. The products are processed through three machines as follows Product Annual demand Standard Time on m/c 1 Standard Time on m/c 2 Standard Time on m/c 3 A 600 5 -- 8 B 350 8 2 -- C 1000 1 12 10 If there are 250 working days per year and the company plans to work one seven hours shift per day, then compute the number of machines required.arrow_forwardDuring an eight-hour shift, 750 non-defective parts are desired as a result of a manufacturing operation. The default operation time is 15 minutes. As the operators of machine are inexperienced, the actual time they take to perform the operation is 20 minutes, and, on average, a fifth of the parts that start to be manufactured are lost. Assuming that each one of the machines used in this operation will not be available for one hour in each shift, determine the number of machines needed.arrow_forwardA car wash offers two different types of wash services, deluxe wash and standard wash. The deluxe wash require(s) three steps: pre-wash, wash and dry. The standard wash only require(s) two steps: wash and dry. The pre-wash step has a capacity of 7 cars per hour. The wash step has a capacity of 11 cars per hour. The dry step has a capacity of 10 cars per hour. The demand for deluxe wash is 7 cars per hour and the demand for standard wash is 11 cars per hour. Instruction: Round to the nearest integer percentage. What is the implied utilization of the bottleneck resource?arrow_forward
- A car wash offers two different types of wash services, deluxe wash and standard wash. The deluxe wash require(s) three steps: pre- wash, wash and dry. The standard wash only require(s) two steps: wash and dry. The pre-wash step has a capacity of 5 cars per hour. The wash step has a capacity of 13 cars per hour. The dry step has a capacity of 10 cars per hour. The demand for deluxe wash is 9 cars per hour and the demand for standard wash is 13 cars per hour. Instruction: Round to the nearest integer percentage. What is the implied utilization of the bottleneck resource?arrow_forwardThe ABC Company is planning a new product line and a new plant to produce the parts for the line. The product line will include 8 different models. Annual production of each model is expected to be 900 units. Each product will be assembled of 180 components. All processing of parts will be accomplished in the new plant. On average, 6 processing operations are required to produce each component, and each operation takes an average of 1 min (including an allowance for setup time and part handling). All processing opera-tions are performed at workstations, each of which includes a production machine and a human worker. The plant operates one shift. Determine the number of (a) components, (b) processing operations, and (c) workers that will be needed to accomplish the processing operations if each worker works 2,000 hr/yr.arrow_forwardJoan has a small design and tailoring shop making custom outfits for women. She has two employees. Each employee only begins working on a dress when a customer order has been received and then she makes the dress from beginning to end. The average production time of a dress is 1.8 days, with a standard deviation of 2.1 days. Historically, Joan has been receiving orders with interarrival times of one day on average. The interarrival times of orders have a coefficient of variation of one. (Carry at least 4 decimal places in all intermediate calculations. Round your final answer to 2 decimal places.) What is the expected waiting time, in days, between when an order is received and when production begins on the dress? A. 9.12 days B. 6.50 days C. 1.23 days D.3.41 daysarrow_forward
- A serial process has 5 steps – A (4), B(5), C(2), D(6), and E(3) – that have to be performed in this order. The numbers in parentheses are the times (in minutes) needed to process a unit. For each unit produced by this process, the process has a total idle time of: Group of answer choices 1 min 10 mins 6 mins 3 minsarrow_forwardFormtech Inc. produces transformers. Each order is custom designed and manufactured for the customer. Each order goes through 3 phases: Transformer Design, which takes 4 weeks. Procurement, which has a lead time of 8 weeks. Assembly and Testing, which takes 4 weeks The design group can handle only 4 projects at any given time. The other groups are not capacity constrained. How much total work-in-process (number of projects started but not yet completed) does the company typically have? (Hint: Little's Law)arrow_forwardConsider a production line with four stations. Station 1 can produce a unit in 9 minutes. Station 2 can produce a unit in 8 minutes. Station three has two identical machines, each of which can process a unit in 12 minutes (each unit only needs to be processed on one of the two machines). Station 4 has two lines: one line has two continuous machines with a process time of 5 minutes/unit and 6 minutes/unit; the other line can produce a unit in 10 minutes. The bottleneck is station (just fill in a number in this question), the system process time is min/unit, the cycle time is mins. If one week has 5 working days and each day operates 8 hours, then the weekly capacity is unit/week.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,