Textbook Question
Book Icon
Chapter 9, Problem 21P

Multiple Products. Materials, and Processes
Mickley Corporation produces two products. Alpha’s and Zeta’s, which pass through two operations. Sintering and
Finishing. Each of the products uses two raw materials−X442 and Y661. The company uses a standard cost system, with the following standards for each product (on a per unit basis):
Chapter 9, Problem 21P, Multiple Products. Materials, and Processes Mickley Corporation produces two products. Alpha’s and , example  1
Information relating to materials purchased and materials used in production during May follows:

Chapter 9, Problem 21P, Multiple Products. Materials, and Processes Mickley Corporation produces two products. Alpha’s and , example  2
The following additional information is available:
a. The company recognizes price variances when materials are purchased.
b. The standard labor rate is $19.80 per hour in Sintering and $19.20 per hour in Finishing.
c. During May, 1,200 direct labor-hours were worked in Sintering at a total labor cost of $27,000, and 2,850 direct labor-hours were worked in Finishing at a total labor cost of $59.850.
d. Production during May was 1,500 Alpha6s and 2.000 Zeta7s.
Required:
1. Prepare a standard cost card for each product, showing the standard cost of direct materials and direct labor.
2. Compute the materials price and quantity variances for each material.
3. Compute the labor rate and efficiency variances for each operation.

.

1

Expert Solution
Check Mark
To determine
$

Standard cost card

A standard cost card contains all the information regarding standard quantities, rates, hours etc. It shows total cost of producing one unit.

To prepare: Standard cost card for both the given products, showing cost of direct materials and labor.

Answer to Problem 21P

Total standard cost of alpha6s is determined as $28.42 and of zeta7s is $41.01.

Explanation of Solution

Standard cost card of Alpha6s:

    ParticularsStandard Quantity or standard hoursStandard price or standard rateStandard cost (in $)
    Direct material (X442)1.8Kilos$3.5Per kilo6.3
    Direct material (Y661)2.0Liters$1.4Per liter2.8
    Direct labor (Sintering)0.2Hours$19.8Per hour3.96
    Direct labor (Finishing)0.8Hours$19.2Per hour15.36
    Total 28.42

Standard cost card of zeta7s:

    ParticularsStandard Quantity or standard hoursStandard price or standard rateStandard cost (in $)
    Direct material (X442)3.0Kilos$3.5Per kilo10.5
    Direct material (Y661)4.5Liters$1.4Per liter6.3
    Direct labor (Sintering)0.35Hours$19.8Per hour6.93
    Direct labor (Finishing)0.9Hours$19.2Per hour17.28
    Total 41.01

So, total standard cost of Alpha6s is $28.42 and of zeta7s is $41.01.

2

Expert Solution
Check Mark
To determine

Variances

A variance shows difference between actual amount of cost incurred and the budgeted cost. Variances can either be favorable or unfavorable.

To calculate: Amount of material price variance and quantity variance.

Answer to Problem 21P

Material price variance for material X442 is $1,450 unfavorable and for material Y661 is $775 favorable.

material quantity variance for material X442 is $700 favorable and for material Y661 is $1,400 unfavorable.

Explanation of Solution

Formula to calculate material price variance is:

  Material price variance = (Standard price - Actual price)×Actual quanity 

For material X442, actual price will be:

  Actual price = Purchases costPurchasesActual price = $52,20014,500Actual price= $3.6

Standard price is given as $3.5 per kilo and actual quantity purchased is 14,500. So, material price variance will be:

  Material price variance = (3.5 - 3.6)×14,500                                      = 1450 Unfavorable 

For material Y661, actual price will be:

  Actual price = Purchases costPurchasesActual price = $20,92515,500Actual price= $1.35

Standard price is given as $1.4 per liter and actual quantity purchased is 15,500. So, material price will be:

  Material price variance = (1.4 - 1.35)×15,500                                      = $775 Favorable 

Formula to calculate material quantity variance is:

  Material quantity variance = (Standard quantity - Actual quantity)×Standard price

For material X442, actual quantity is given as 8,500 kilos and standard price is $3.5 per kilo. Standard quantity will be calculated as:

  Standard quanitity = (Standard quanity of alpha6s × Produced units) + (standard units of zeta7s ×Produced units)                              = (1.8×1,500) + (3×2,000)                             = 2,700 + 6,000                              = 8,700 

So, Material quantity variance will be:

  Material quantity variance = (8,700 - 8,500)×3.5                                           = $700 Favorable

For material Y661, actual quantity is given as 13,000 liters and standard price is $1.4 per liter. Standard quantity will be calculated as:

  Standard quanitity = (Standard quanity of alpha6s × Produced units) + (standard units of zeta7s ×Produced units)                              = (2×1,500) + (4.5×2,000)                             = 3,000 + 9,000                              = 12,000

So, material quantity variance will be:

  Material quantity variance = (12,000 - 13,000)×1.4                                           = $1,400 Unfavorable

3

Expert Solution
Check Mark
To determine

Variances

Variances related to labor show difference among actual cost incurred on labor and the standard cost. Variances are considered favorable when standard cost is more than that of actual cost.

Amount of labor rate and efficiency variances.

Answer to Problem 21P

Labor rate variance for sintering is $3,240 unfavorable and for finishing is $5,130 unfavorable.

Labor efficiency variance for sintering is $3,960 unfavorable and for finishing is $2,880 favorable.

Explanation of Solution

Formula to calculate labor rate variance is:

  Labor rate variance = (Standard rate - Actual rate)×Actual hours worked

For sintering, standard rate is $19.80 per hour, actual hours worked are 1,200 and actual rate will be $22.5 per hour ($27,000/1,200). Labor rate variance will be:

  Labor rate variance = (Standard rate - Actual rate)×Actual hours worked                                = ($19.8 - 22.5)×1,200                                = $3,240 Unfavorable

For finishing, standard rate is $19.20 per hour, actual hours worked are 2,850 and actual rate will be $21 per hour ($59,850/2,850). So, labor rate variance will be:

  Labor rate variance = (Standard rate - Actual rate)×Actual hours worked                                = ($19.2 - 21)×2,850                                = $5,130 Unfavorable

Formula to calculate labor efficiency variance is:

  Labor efficiency variance = (Standard hours - Actual hours)×Standard rate

For sintering, actual hours are 1,200, standard rate is $19.8 and standard hours will be 1,000 ((0.2*1,500)+(0.35*2,000)). So, the labor efficiency variance will be:

  Labor efficiency variance = (Standard hours - Actual hours)×Standard rate                                         = ($1,000 - 1,200)×$19.8                                         = $3,960 Unfavorable

For finishing, actual hours are 2,850, standard rate is $19.2 and standard hours will be 3,000 ((0.8*1,500 + 0.9*2,000))

  Labor efficiency variance = (Standard hours - Actual hours)×Standard rate                                         = ($3,000 - 2,850)×$19.2                                         = $2,880 Favorable

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Trimake Limited makes three main products, using broadly the same production methods and equipment for each. A conventional product costing system is used at present, although an activity-based costing (ABC) system is being considered. Details of the three products for a typical period are: Product X Product Y Product Z Hours per Labour hours 1/2 1½ 1 Costs relating to set-ups Costs relating to machinery Costs relating to materials handling Costs relating to inspection Total production overhead Product X Product Y Product Z unit Total activities for the period: 75 115 480 670 Machine hours 1½ 1 3 Direct labour costs £6 per hour and production overheads are absorbed on a machine hour basis. The rate for the period is £28 per machine hour. Further analysis shows that the total of production overheads can be divided as follows: Number of Number of set-ups (%) 35 movements of materials 12 21 87 120 Materials per unit £ 20 15 30 100% 20 12 25 The following activity volumes are associated…
Apply the Concepts, Cost Reporting Medco Inc., a manufacturing firm, has four activities: purchasing materials, molding, inspecting molds, and grinding imperfect molds. Purchasing materials and molding are necessary activities; inspection and grinding are unnecessary. SQ provides the value-added quantity for each activity; AQ is the actual activity output. The following data pertain to the four activities for the year ending (actual price per unit of the activity driver is assumed to be equal to the standard price): Activity Activity Driver Purchasing Purchasing hours Molding Inspecting Inspection hours Molding hours Grinding. Number of units Required: SQ AQ SP 28,000 34,000 $20 42,000 47,600 121 0 8,400 15 0 6,000 6 1. Prepare a cost report for the year 1 ended that shows value-added costs, non-value-added costs, and total costs for each activity by completing the following table: Value-and Non-Value-Added Cost Report for the Year 1 Ended Activity Value-Added Costs Non-Value-Added…
Mickley Corporation produces two products, Alpha6s and Zeta7s, which pass through two operations, Sintering and Finishing. Each of the products uses two raw materials-X442 and Y661. The company uses a standard cost system, with the following standards for each product (on a per unit basis): Standard Labor Time Sintering Finishing 0.40 hours 0.80 hours 0.30 hours 0.90 hours Information relating to materials purchased and materials used in production during May follows: Material Standard Price $ 3.60 per kilo X442 Used in Production 8,600 kilos 13,100 liters Y661 $ 1.50 per liter Product Alpha6 Zeta7 Raw Material Y661 X442 1.5 kilos 3.5 kilos 4.4 liters 2.2 liters Purchases 14,100 kilos 15,100 liters Purchase Cost $ 53,580 $ 21,140 The following additional information is available: a. The company recognizes price variances when materials are purchased. b. The standard labor rate is $18.00 per hour in Sintering and $18.00 per hour in Finishing. c. During May, 1,250 direct labor-hours were…

Chapter 9 Solutions

INTRO.TO MGRL.ACCT.(LL)W/CONNECT>IP<

Ch. 9.A - Comprehensive Standard Cost Variances Flandro...Ch. 9.A - Selection of a Denominator: Overhead Analysis:...Ch. 9.B - Standard Cost Flows: Income Statement Preparation...Ch. 9.B - Standard Cost Flows: Income Statement Preparation...Ch. 9.B - Standard Cost Flows Bowen Company manufactures one...Ch. 9.B - Standard Cost Flows Hartwell Company manufactures...Ch. 9.B - Transaction Analysis; Income Statement Preparation...Ch. 9.B - Transaction Analysis; Income Statement Preparation...Ch. 9 - What is a static planning budget?Ch. 9 - What is a flexible budget and how does it differ...Ch. 9 - What are some of the possible reasons that actual...Ch. 9 - Why is it difficult to interpret a difference...Ch. 9 - What is a revenue variance and what does it mean?Ch. 9 - What is a spending variance and what does it mean?Ch. 9 - What does a flexible budget enable that a simple...Ch. 9 - How does a flexibe budget based on the cost...Ch. 9 - Prob. 9QCh. 9 - Why are separate price and quantity variances...Ch. 9 - Who is generally responsible for the materials...Ch. 9 - Prob. 12QCh. 9 - Prob. 13QCh. 9 - Our workers are all under labor contracts:...Ch. 9 - Prob. 15QCh. 9 - Prob. 16QCh. 9 - Prob. 17QCh. 9 - The Excel worksheet form that appears below is to...Ch. 9 - Prob. 2AECh. 9 - Preble Company manufactures one product. Its...Ch. 9 - Prob. 2F15Ch. 9 - Preble Company manufactures one product. Its...Ch. 9 - Prob. 4F15Ch. 9 - Prob. 5F15Ch. 9 - Prob. 6F15Ch. 9 - Preble Company manufactures one product. Its...Ch. 9 - Prob. 8F15Ch. 9 - Prob. 9F15Ch. 9 - Prob. 10F15Ch. 9 - Prob. 11F15Ch. 9 - Preble Company manufactures one product. Its...Ch. 9 - Prob. 13F15Ch. 9 - Preble Company manufactures one product. Its...Ch. 9 - Preble Company manufactures one product. Its...Ch. 9 - Prepare a Flexible Budget Puget Sound Divers is a...Ch. 9 - Prepare a Report Shong Revenue and Spending...Ch. 9 - Prepare a Flexible Budget with More Than One Cost...Ch. 9 - Direct Materials Variances Bandar Industries...Ch. 9 - Prob. 5ECh. 9 - Prob. 6ECh. 9 - Planning Budget Lavage Rapide is a Canadian...Ch. 9 - EXERCISE 98 Flexible Budget L091 Refer to the data...Ch. 9 - Prepare a Report Showing Revenue and Spending...Ch. 9 - Direct Labor and Variable Manufacturing Overhead...Ch. 9 - Prob. 11ECh. 9 - Working with More Than One Cost Driver The...Ch. 9 - Direct Materials and Direct Labor Variances Huron...Ch. 9 - Direct Materials Variances Refer to the data in...Ch. 9 - Prob. 15ECh. 9 - Prob. 16ECh. 9 - Prob. 17ECh. 9 - Comprehensive Variance Analysis Miller Toy Company...Ch. 9 - More than One Cost Driver Milano Pizza is a small...Ch. 9 - Basic Variance Analysis: the Impact of Vanances on...Ch. 9 - Multiple Products. Materials, and Processes...Ch. 9 - Variance Analysis In a Hospital John Fleming,...Ch. 9 - Flexible Budgets and Spending Variances You have...Ch. 9 - Comprehensive Variance Analysis Marvel Parts....Ch. 9 - Direct Materials and Direct Labor Variances:...Ch. 9 - Comprehensive Variance Analysis Highland Company...
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license