EBK PRINCIPLES OF OPERATIONS MANAGEMENT
EBK PRINCIPLES OF OPERATIONS MANAGEMENT
11th Edition
ISBN: 9780135175644
Author: Munson
Publisher: VST
Question
Book Icon
Chapter 9, Problem 20P

a)

Summary Introduction

To draw: The precedence diagram.

a)

Expert Solution
Check Mark

Answer to Problem 20P

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 20P , additional homework tip  1

Explanation of Solution

Given information:

Task Time (minutes) Immediate predecessors
A 3 -
B 6 -
C 7 A
D 5 A, B
E 2 B
F 4 C
G 5 F
H 7 D, E
I 1 H
J 6 E
K 4 G, I, J
Total 50  
  • Number of hours / day is 24
  • Output is 96 instruments / day.

Precedence diagram:

EBK PRINCIPLES OF OPERATIONS MANAGEMENT, Chapter 9, Problem 20P , additional homework tip  2

b)

Summary Introduction

To determine: The cycle time.

Introduction:

Cycle time:

Cycle time is the total time taken to complete an unit of work from the beginning of the process to the end of the process.

b)

Expert Solution
Check Mark

Answer to Problem 20P

The  cycle time is 15 minutes / unit.

Explanation of Solution

Formula to calculate cycle time:

Cycle time=Number of hours per dayDaily production× Number of minutes / hour

Calculation of cycle time:

Cycle time=2496×60=1,44096=15 minutes / unit

The  cycle time is 15 minutes / unit.

c)

Summary Introduction

To determine: The production rate.

c)

Expert Solution
Check Mark

Answer to Problem 20P

The  production rate is 144 units / day.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Formula to calculate production rate:

Cycle time=Number of hours per dayCycle time× Number of minutes / hour

Calculation of cycle time:

Cycle time=2410×60=1,44010=144 units / day

The  production rate is 144 units / day.

d)

Summary Introduction

To determine: The theoretical minimum number of workstations.

d)

Expert Solution
Check Mark

Answer to Problem 20P

The theoretical minimum number of workstations is 5 workstations.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Formula to calculate theoretical minimum number of workstations:

Workstations=Total task timeCycle time

Calculation of theoretical minimum number of workstations:

Workstations=5010=5 workstations

The theoretical minimum number of workstations is 5 workstations.

e)

Summary Introduction

To determine: The efficiency.

Introduction:

Efficiency:

Efficiency is the measure of  what is actually produced as opposed to what can be theoretically produced with the same amount of resources.

e)

Expert Solution
Check Mark

Answer to Problem 20P

The efficiency is 83.3%.

Explanation of Solution

Given information:

Cycle time = 10 minutes

Number of workstations = 6

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=506×10×100=50060=83.3%

The efficiency is 83.3%.

f)

Summary Introduction

To determine: The total idle time per cycle.

f)

Expert Solution
Check Mark

Answer to Problem 20P

The  idle time is 10 minutes / cycle.

Explanation of Solution

Given information:

Number of workstations = 6

Cycle time = 10

Calculation of total idle time per cycle:

Total idle time=(Number of workstations×Cycle time)-Total task time=(6×10)-50=60-50=10 minutes / cycle

The  total idle time is 10 minutes / cycle.

g)

Summary Introduction

To assign: The different tasks to different workstations and identify the efficiency.

g)

Expert Solution
Check Mark

Explanation of Solution

Assignment of different tasks to different workstations:

Workstation Elligible tasks Selected tasks Task time (minutes) Available cycle time (minutes)
1 10
A, B A 3 7
B B 6 1
1 (Idle time)
2 10
C, D, E C 7 3
3 (Idle time)
3 10
D, E, F D 5 5
E, F E 2 3
3 (Idle time)
4 10
F, G, H, I F 4 6
G, H, I G 5 1
1 (Idle time)
5 10
J, H, I, K H 7 3
H, I, K I 1 2
2 (Idle time)
6 10
K, J J 6 4
K K 4 0
Workstation Task assigned Idle time
1 A, B 1
2 C, D 3
3 D, E 3
4 F, G 1
5 H, I 2
6 J, K 0
Total 10

Efficiency:

Formula to calculate efficiency:

Efficiency=Total task timeNumber of workstations×Cycle time×100

Calculation of efficiency:

Efficiency=506×10×100=50060=83.3%

The efficiency is 83.3%.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
SITUATION: A company is about to begin production of a new product. The manager of the department that will produce one of the components for the product wants to know how often the machine used to produce the item will be available for other work. The machine will produce the item at a rate of 200 units a day. Eighty units will be used daily in assembling the final product. Assembly will take place five days a week, 50 weeks a year. The manager estimates that it will take almost a full day to get the machine ready for a production run, at the cost of $300. Inventory holding costs will be $10 a year. QUESTION: Suppose the manager decides to increase the run size of the new product. How many additional units would be needed just to accommodate the other job? How much will that increase the total annual cost?
A paced assembly line has been devised to manufacture​ calculators, as the following data​ show:                                                                                                                            LOADING... Station Work Element Assigned Work Element Time​ (min) S1 A 4.0 S2 ​D, E 0.9​, 1.5 S3 C 5.0 S4 ​B, F, G 1.1​, 1.0​, 1.3 S5 ​H, I, J 1.1​, 0.5​, 1.8 S6 K 4.0 a. What is the maximum hourly output rate from this​ line? ​(Hint​: The line can only go as fast as its slowest​ workstation.)   The maximum hourly output rate is nothing calculators per hour. ​(Enter your response as an​ integer.) B. What cycle time corresponds to this maximum output rate? C. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each? 10-hour shift? D. What is the line's efficiency?
Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly-line balancing. She has been told that the firm needs to complete 96 instruments per 24-hour day. The assembly-line activities are:                                                                                                               a) Draw the precedence diagram.b) Tf the daily (24-hour) production rate is 96 units, what is the highest allowable cycle time?c) If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate?d) With a 10-minute cycle time, what is the theoretical minimum number of stations with which the line can be balanced?e) With a I 0-minute cycle time and six workstations, what is the efficiency?f) What is the total idle time per cycle with a I 0-minute cycle time and six workstations?g) What is the best workstation assignment you can make without exceeding a I 0-minute cycle time, and what is its efficiency?
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.