Chapter 8, Problem 8.1P
To determine

Draw the flow net and calculate the seepage loss per meter length of the sheet pile.

Expert Solution & Answer
Check Mark

Answer to Problem 8.1P

The seepage loss per meter length of the sheet pile is 77.76×102m3/m/day_.

Explanation of Solution

Given information:

The hydraulic conductivity of the permeable soil layer k is 4×104cm/sec.

The height of the water level H1 is 6 m.

The height of the water level H2 is 1.5 m.

The depth of permeable layer up to the end of sheet pile D is 3 m.

The depth of permeable layer D1 is 6 m.

Calculation:

Draw the free body diagram of the flow net for the given values as in Figure (1).

Bundle: Principles Of Geotechnical Engineering, Loose-leaf Version, 9th + Mindtap Engineering, 2 Terms (12 Months) Printed Access Card, Chapter 8, Problem 8.1P

Refer Figure 1.

Determine the head difference between the upstream and downstream using the relation.

H=H1H2

Substitute 6 m for H1 and 1.5 m for H2.

H=61.5=4.5m

Determine the seepage loss per meter length of the sheet pile using the relation.

q=kHNfNd

Here, Nf is the number of flow lines and Nd is the number of potential drops.

Substitute 4×104cm/sec for k, 4.5 m for H, 4 for Nf, and 8 for Nd.

q=4×104cm/sec×1m100cm×86,400sec1day×4.5×48=77.76×102m3/m/day

Therefore, the seepage loss per meter length of the sheet pile is 77.76×102m3/m/day_.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Refer to Figure 8.23. Given:• H1 = 6m• H2 = 1.5 m• D = 3 m• D1 = 6 mDraw a flow net. Calculate the seepage loss per meter length of the sheet pile (at a right angle to the cross section shown).
Given h = 30 m, D= 40 m and the soil beneath the dam has a hydraulic conductivity of 3x10-3 cm/s. Compute 1) pore pressure at point b, and 2) the flow rate under the sheet pile. given = h = 30m NF No D=40m *units meters 0.8h h 30 640 0.7h Sheet pile D12-c 0.6h 0.5h 0.4h 0.2h
Determine the total flow rate through all channels per unit length of the respective Flownet of sheet pile. Given coefficient of permeability, k = 2.8 x10-5 cm/s (refer Figure above) h = 30 m h2= 10 m O 0.0021 cm2/s O 0.00125 cm2/s O 0.0056 cm2/s O 0.0028 cm2/s

Chapter 8 Solutions

Bundle: Principles Of Geotechnical Engineering, Loose-leaf Version, 9th + Mindtap Engineering, 2 Terms (12 Months) Printed Access Card

Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Fundamentals of Geotechnical Engineering (MindTap...
Civil Engineering
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Text book image
Principles of Geotechnical Engineering (MindTap C...
Civil Engineering
ISBN:9781305970939
Author:Braja M. Das, Khaled Sobhan
Publisher:Cengage Learning