Question
Chapter 8, Problem 7P
Summary Introduction
To determine: The location at which it should be locatedCalculate the weighted scores for the two locations Phila and NY as shown below
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Let us assume that a new medical facility, Health-care, is to be located in ABC city. The location factors, weights, and scores (1 = poor, 5 = excellent) for three potential sites are shown in the following table. What is the weighted score for these sites?
Which is the best location
Sr.
Location factor
Weight
Scores
Location 1
Location 2
Location 3
1
Facility utilization
25
3
5
6
2
Total patient per month
25
4
3
5
3
Average time per emergency trip
20
4
3
5
4
Land and construction costs
15
1
4
2
5
Employee preferences
25
5
3
5
The Giant Farmer Company processes food for sale in discount food stores. It has two plants: one in Chicago and one in Houston. The company also operates warehouses
in Miami, Florida; Denver, Colorado; Lincoln, Nebraska; and Jackson, Mississippi. Forecasts indicate that demand soon will exceed supply and that a new plant with a capacity
of 8,000 cases per week is needed. The question is where to locate the new plant. Three potential sites are Buffalo, Atlanta, and Memphis. The two tables below give data
on capacities, forecasted demand, and shipping costs that have been gathered.
Plant
Chicago
Houston
Capacity
(cases per week)
New plant
Warehouse
Plant
Chicago
Houston
Buffalo (alternative
1)
Atlanta (alternative
2)
Memphis
(alternative 3)
For each alternative new plant location, determine the total cost of the shipping pattern that will minimize total transportation costs. Where should the new plant be located?
If the new plant is located in Buffalo, the optimal cost is $
(Enter your…
Sap Manufacturing, a manufacturing company that manufactures football jerseys and located in Port Antonio, Jamaica, is preparing to build a new plant. J’s is considering three potential locations that are suitable for the construction of the plant. The fixed and variable costs for the three alternative locations are presented in the table below.
Identify the range over which each alternative (A, B and C) is best.
Chapter 8 Solutions
Mylab Operations Management With Pearson Etext -- Access Card -- For Operations Management: Sustainability And Supply Chain Management (13th Edition)
Ch. 8 - Prob. 1EDCh. 8 - Prob. 1DQCh. 8 - Prob. 2DQCh. 8 - Prob. 3DQCh. 8 - Prob. 4DQCh. 8 - Prob. 5DQCh. 8 - Prob. 6DQCh. 8 - Prob. 7DQCh. 8 - Prob. 8DQCh. 8 - Prob. 9DQ
Ch. 8 - Prob. 10DQCh. 8 - Prob. 11DQCh. 8 - Prob. 12DQCh. 8 - Prob. 13DQCh. 8 - Prob. 14DQCh. 8 - Prob. 15DQCh. 8 - Prob. 16DQCh. 8 - Prob. 17DQCh. 8 - Prob. 18DQCh. 8 - Prob. 1PCh. 8 - Prob. 2PCh. 8 - Prob. 3PCh. 8 - Prob. 4PCh. 8 - Prob. 5PCh. 8 - Prob. 6PCh. 8 - Prob. 7PCh. 8 - Prob. 8PCh. 8 - Prob. 9PCh. 8 - Prob. 10PCh. 8 - Prob. 11PCh. 8 - Prob. 12PCh. 8 - Prob. 13PCh. 8 - Prob. 14PCh. 8 - Prob. 15PCh. 8 - Prob. 16PCh. 8 - Prob. 17PCh. 8 - Prob. 18PCh. 8 - Prob. 19PCh. 8 - Prob. 20PCh. 8 - Prob. 21PCh. 8 - Prob. 22PCh. 8 - Prob. 23PCh. 8 - Prob. 24PCh. 8 - Prob. 26PCh. 8 - Prob. 27PCh. 8 - Prob. 28PCh. 8 - Prob. 29PCh. 8 - Prob. 31PCh. 8 - Prob. 32PCh. 8 - Prob. 1CSCh. 8 - Prob. 2CSCh. 8 - Prob. 3CSCh. 8 - Prob. 4CSCh. 8 - Prob. 1.1VCCh. 8 - Prob. 1.2VCCh. 8 - Prob. 1.3VCCh. 8 - Prob. 2.1VCCh. 8 - Prob. 2.2VCCh. 8 - Prob. 2.3VCCh. 8 - Prob. 2.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A manufacturing company preparing to build a new plant is considering three potential locations for it. The fixed and variable costs for the three alternative locations are presented in the table below. Table 1 Costs A B C Fixed 500,000 600,000 800,000 Variable 40 30 20 Indicate over what range, each of the alternatives A, B, C is the low-cost choice.arrow_forwardYou are trying to decide which of the following three cities in which to locate a new manufacturing facility, and you have gathered the following information about each: City Annual Fixed Cost Variable Cost (per unit) Singapore $30,000 $2 Hong Kong $20,000 $3 Niagara Falls $10,000 $6 If this facility will produce 2,000 units annually, where should you locate it? O A. Singapore O B. Niagara Falls O C. either Singapore or Niagara Falls O D. Hong Kong O E. either Hong Kong or Niagara Fallsarrow_forwardA firm that has recently experienced enormous growth is seeking to lease a small plant in Memphis, TN; Biloxi, MS; or Birmingham, AL. Prepare an economic analysis of the three locations given the following information: Annual costs for building, equipment, and administration would be $40,000 for Memphis, $60,000 for Biloxi, and $100,000 for Birmingham. Labor and materials are expected to be $8 per unit in Memphis, $4 per unit in Biloxi, and $5 per unit in Birmingham. The Memphis location would increase system transportation costs by $50,000 per year, the Biloxi location by $60,000 per year, and the Birmingham location by $25,000 per year. Expected annual volume is 10,000 units. 6.arrow_forward
- Wiebe Trucking, Inc., is planning a new warehouse to serve the western United States. Denver, Santa Fe, and Salt Lake City are under consideration. For each location, annual fixed costs (rent, equipment, and insurance) and average variable costs per shipment (labor, transportation, and utilities) are listed in the following table. Sales projections range from 550,000 to 600,000 shipments per year. Location Annual fixed cost Variable Costs per Shipment Denver $5,000,000 $4.65 Santa Fe $4,200,000 $6.25 Salt Lake City $3,500,000 $7.25 a. Plot the total cost curves for all the locations on a single graph. b. Which city provides the lowest overall costs? Thank you!!!arrow_forwardYou are trying to decide which of the following three cities in which to locate a new manufacturing facility, and you have gathered the following information about each: City Annual Fixed Cost Variable Cost (per unit) Singapore $30,000 $2 Hong Kong $20,000 $3 Niagara Falls $10,000 $6 If this facility will produce 15,000 units annually, where should you locate it? O A. Niagara Falls O B. Singapore C. either Hong Kong or Niagara Falls O D. Hong Kong O E. either Singapore or Niagara Fallsarrow_forwardNortheastern Insurance Company is considering opening an office in the U.S. The two cities under consideration are Philadelphia and New York. The factor ratings (higher scores are better) for the two cities are given in the following table. Factor Weight Philadelphia New York Customer convenience 0.25 70 80 Bank accessibility 0.20 40 90 Computer support 0.20 85 75 Rental costs 0.15 90 55 Labor costs 0.10 80 50 Таxes 0.10 90 50 Based on the given information, the best location for Northeastern Insurance Company to open the office is with a total weighted score of. (Enter your response as a whole number.)arrow_forward
- sniparrow_forwardTwo alternative locations are under consideration for a new plant: Jackson, Mississippi, and Dayton, Ohio. The Jackson location is superior in terms of costs. However, management believes that sales volume would decline if this location were chosen because it is farther from the market, and the firm’s customers prefer local suppliers. The selling price of the product is $250 per unit in either case. Use the following information to determine which location yields the higher total profit per year: Location AnnualFixed Cost Variable Costper Unit ForecastDemand per Year Jackson Dayton $1,500,000 $2,800,000 $50 $85 30,000 units 40,000 unitsarrow_forwardEagle Electronics must expand by building a second facility. The search has been narrowed down to locating the new facility in one of four cities: Atla nta (A),Baltimore (B), Chicago (C), or Dallas (D). The factors, scores,and weights follow: a) Using the factor-rating method, what is the recommended site for Eagle Electronics's new facility?b) For what range of values for the weight (currently w7 = I 0) does the site given as the answer to part (a) remain a recommended site?arrow_forward
- Balfour’s is considering building a plant in one of three possible locations. They have estimated the following parameters for each location: Location Fixed Cost Variable Cost Waco, Texas $300,000 $5.75 Tijuana, Mexico $800,000 $2.75 Fayetteville, Arkansas $100,000 $8.00 For what unit sales volume should they choose each location?arrow_forwardNortheastern Insurance Company is considering opening an office in the U.S. The two cities under consideration are Philadelphia and New York. The factor ratings (higher scores are better) for the two cities are given in the following table. Factor Weight Philadelphia New York Customer convenience 0.25 70 80 Bank accessibility 0.20 35 85 Computer support 0.20 90 75 Rental costs 0.15 95 55 Labor costs 0.10 85 45 Taxes 0.10 95 55 Based on the given information, the best location for Northeastern Insurance Company to open the office is with a total weighted score of (Enter your response rounded to two decimal places.) 3arrow_forwardQ2k Audi is considering three locations A, B and C for the production of its new model SUV XL500. The objective is to choose the location with the lowest costs. The costs are measured as annual fixed costs plus the variable costs of the product. The following data has been collected for the three locations.< Region Fixed costs per year A B C 10 000 000 20 000 000 25 000 000 Variable cost per unit 1. at what level of production will C be the best choice? 2. at what production rate will A be the best choice? 3. at what level of production will B be the best choice? 2500 2000< 1000< The company's projected annual production in the new plant is 0-60 000 units.< Askarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.