a)
To determine: The average cycle time for each operation.
Introduction: The amount of the dependency on human effort by an organization in terms of achieving its goals is given by the work design. It is directly linked to the productivity of an organization where good work design helps in achieving high productivity.
a)
Explanation of Solution
Given information:
Observation (minutes per cycle) | |||||||
Element | Performance rating | 1 | 2 | 3 | 4 | 5 | 6 |
1 | 90 | 0.44 | 0.5 | 0.43 | 0.45 | 0.48 | 0.46 |
2 | 85 | 1.5 | 1.54 | 1.47 | 1.51 | 1.49 | 1.52 |
3 | 110 | 0.84 | 0.89 | 0.77 | 0.83 | 0.85 | 0.8 |
4 | 100 | 1.1 | 1.14 | 1.08 | 1.2 | 1.16 | 1.26 |
Calculation of average time per cycle:
Observation (minutes per cycle) | |||||||
Performance rating | 1 | 2 | 3 | 4 | 5 | 6 | Average time per cycle |
90 | 0.44 | 0.5 | 0.43 | 0.45 | 0.48 | 0.46 | 0.46 |
85 | 1.5 | 1.54 | 1.47 | 1.51 | 1.49 | 1.52 | 1.505 |
110 | 0.84 | 0.89 | 0.77 | 0.83 | 0.85 | 0.8 | 0.83 |
100 | 1.1 | 1.14 | 1.08 | 1.2 | 1.16 | 1.26 | 1.156667 |
Excel worksheet:
Average time per cycle is calculated by taking average of all cycle in each element which is average of 0.44, 0.5, 0.43, 0.45, 0.48 and 0.46 which gives 0.46 as average time per cycle for element 1 and similar method follows for element 2, 3 and 4.
b)
To determine: The normal time for the operation.
b)
Explanation of Solution
Given information:
Observation (minutes per cycle) | |||||||
Element | Performance rating | 1 | 2 | 3 | 4 | 5 | 6 |
1 | 90 | 0.44 | 0.5 | 0.43 | 0.45 | 0.48 | 0.46 |
2 | 85 | 1.5 | 1.54 | 1.47 | 1.51 | 1.49 | 1.52 |
3 | 110 | 0.84 | 0.89 | 0.77 | 0.83 | 0.85 | 0.8 |
4 | 100 | 1.1 | 1.14 | 1.08 | 1.2 | 1.16 | 1.26 |
Formula:
Calculation of normal time:
Observation (minutes per cycle) | |||||||||
Element | Performance rating | 1 | 2 | 3 | 4 | 5 | 6 | Average time per cycle | NT |
1 | 0.9 | 0.44 | 0.5 | 0.43 | 0.45 | 0.48 | 0.46 | 0.46 | 0.414 |
2 | 0.85 | 1.5 | 1.54 | 1.47 | 1.51 | 1.49 | 1.52 | 1.505 | 1.27925 |
3 | 1.1 | 0.84 | 0.89 | 0.77 | 0.83 | 0.85 | 0.8 | 0.83 | 0.913 |
4 | 1 | 1.1 | 1.14 | 1.08 | 1.2 | 1.16 | 1.26 | 1.156666667 | 1.156667 |
Excel worksheet:
Normal time is calculated by multiplying observed timing, 0.46 and performance rating, 0.9 which yields 0.414 minutes for element 1, 2, 3 and 4.
c)
To determine: The standard time for the operation.
c)
Explanation of Solution
Given information:
Observation (minutes per cycle) | |||||||
Element | Performance rating | 1 | 2 | 3 | 4 | 5 | 6 |
1 | 90 | 0.44 | 0.5 | 0.43 | 0.45 | 0.48 | 0.46 |
2 | 85 | 1.5 | 1.54 | 1.47 | 1.51 | 1.49 | 1.52 |
3 | 110 | 0.84 | 0.89 | 0.77 | 0.83 | 0.85 | 0.8 |
4 | 100 | 1.1 | 1.14 | 1.08 | 1.2 | 1.16 | 1.26 |
Formula:
Calculation of standard time:
Allowance factor is calculated by dividing 1 with difference of 1 and 0.15 which yields 1.15.
Observation (minutes per cycle) | |||||||||||
Element | Performance rating | 1 | 2 | 3 | 4 | 5 | 6 | Average time per cycle | NT | Afjob | ST |
1 | 0.9 | 0.44 | 0.5 | 0.43 | 0.45 | 0.48 | 0.46 | 0.46 | 0.414 | 1.15 | 0.4761 |
2 | 0.85 | 1.5 | 1.54 | 1.47 | 1.51 | 1.49 | 1.52 | 1.505 | 1.27925 | 1.15 | 1.471138 |
3 | 1.1 | 0.84 | 0.89 | 0.77 | 0.83 | 0.85 | 0.8 | 0.83 | 0.913 | 1.15 | 1.04995 |
4 | 1 | 1.1 | 1.14 | 1.08 | 1.2 | 1.16 | 1.26 | 1.157 | 1.157 | 1.15 | 1.330167 |
Excel worksheet:
Standard time for the operation is calculated by multiplying normal time of 0.414 minutes with allowance factor of 1.15 which gives 0.4761 minutes for element 1 and same procedure goes with element 2, 3 and 4.
Want to see more full solutions like this?
Chapter 7 Solutions
Operations Management
- 5. The manager of Asombrado Bounty Office, Charles Badillo, estimates his employees are idle 25%of the time. With that problem, how many work samples are needed to consider within 3%accuracy and have 95.45% confidence level. 6. At ASP Micro Manufacturing, Inc. workers press semiconductor into predrilled slots on printed-circuit boards. Determine the normal time of the operation in seconds. The elemental motions for normal time used by the company are as follows:• Reach 6 inches for semiconductors 10.5 TMU• Grasp the semiconductors 8.0 TMU• Move semiconductor to printed-circuit board 9.5 TMU• Position semiconductor 20.1 TMU• Press semiconductor into slots 20.3 TMU• Move board aside 15.8 TMU 7. The semiconductor used in Costin Calculator has 5 components with the consistency of 90%, 95%,98%, 90%, and 99%, respectively. How reliable is one product of calculator?arrow_forwardB\ Put in Order: Below are the steps used in conducting a Job Safety Analysis. Place them in the correct order by putting the number 1 in front of the first step, the number 2 in front of the second step, and so forth. And why. a) Recommending procedures to meet those needs b) Observing the task c) Breaking the task down into activities or steps. d) Analyzing each step for safety or operational needs.arrow_forwardFor a time study of a health insurance claims-adjusting process, the analyst uses the continuous method of recording times. The job is divided into four work elements. Shown in Figure are the performance rating factors, RF, and the continuous method recorded times, r, for each work element.a. Calculate the normal time for this job. b. Calculate the standard time for this job, assuming that the allowance is 20 percent of the normal time. c. What is the appropriate sample size for estimating the time for element 2 within {10 percent of the true mean with 95 percent confidence?arrow_forward
- Compare stopwatch time study and work sampling.arrow_forwardWhat are the trade offs in choosing between time study and work sampling for work measurement.arrow_forwardA time study of an employee assembling peanut valves re-sulted in the following set of observations. What is the stan-dard time, given a performance rating of 95 percent and anallowance of 14 percent of the total normal time?arrow_forward
- Supervisor Kenneth Peterson wants to determinethe percent of time a machine in his area is idle. He decides touse work sampling, and his initial estimate is that the machine isidle 20% of the time. How many observations should Petersontake to be 98% confident that the results will be less than 5% fromthe true results?arrow_forward(a) What is a technique for estimating the percent of the time a worker spends on various tasks? A) stopwatch time study B) simultaneous motion study C) work sampling D) standard elemental (historical) times E) predetermined (published) time standards (b) A bank manager wants to determine the percent of the time the bank's tellers are working and idle. He decides to use work sampling, and his initial estimate is that the tellers are idle 22% of the time. Approximately how many observations should be taken to be 95% confident that the results will not be more than 5% away from the true result? A)6 B) 16 C) 203 D) 264 E) 246arrow_forwardThe final process of job analysis is the preparation of job description and job specification. Select one: O True O Falsearrow_forward
- Time study mainly addresses:a) Timing all workers’ performances for setting standardtimesb) Improving the working environment for setting standardtimesc) Timing a sample of worker’s performance for settingstandard timesd) Timely review of the workloads for setting standardtimese) All of the abovearrow_forwardTOYS AND JOB DESIGN AT THE HOVEY AND BEARD COMPANY The following is a situation that occurred in the Hovey and Beard Company, as reported by J. V. Clark. This company manufactured a line of wooden toys. One part of the process involved spray painting partially assembled toys, after which the toys were hung on moving hooks that carried them through a drying oven. The operation, staffed entirely by women, was plagued with absenteeism, high turnover, and low morale. Each woman at her paint booth would take a toy from the tray beside her, position it in a fixture, and spray on the color according to the required pattern. She then would release the toy and hang it on the conveyor hook. The rate at which the hooks moved had been calculated so that each woman, once fully trained, would be able to hang a painted toy on each hook before it passed beyond her reach. The women who worked in the paint room were on a group incentive plan that tied their earnings to the…arrow_forward1. Define ergonomics. Explain the role of ergonomics in job design. 2. What are the five core characteristics of a good job design? 3. Make an operations chart for putting paper into a printer.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.