Traffic and Highway Engineering - With Mindtap
Traffic and Highway Engineering - With Mindtap
5th Edition
ISBN: 9781305360990
Author: Garber
Publisher: CENGAGE L
bartleby

Concept explainers

Question
Book Icon
Chapter 6, Problem 20P
To determine

(a)

The maximum queue length that will be formed, total delay, number of vehicles that will be affected by the incident, the average individual delay for the expected demand flow of 70%of the capacity of the highway.

Expert Solution
Check Mark

Answer to Problem 20P

For 70 % expected demand flow:

Themaximum queue length that will be formed is qmax=400Veh.

The total delay is dr=445hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 0.0412hr.

Explanation of Solution

Given:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering - With Mindtap, Chapter 6, Problem 20P , additional homework tip  1

Calculation:

For the expected 70 % demand flow:

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 70 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 70%of6000)4000)2qmax=(( 6000× 70 100 )4000)2

  qmax=(( 60×70)4000)2qmax=(42004000)2qmax=400Veh.

The maximum queue length that will be formed is qmax=400Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=22( 70%of60004000)( 60004000)2( 600070%of6000)

  dr=4(42004000)(2000)2(60004200)

  dr=4( 100)( 2000)(1800)dr=40009

  dr=444.44=445hr.

The total delay is dr=445hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.=10800Veh.

The number of vehicles that will be affected by the incident is 10800Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =44510800.=0.0412hr.

The average individual delay is 0.0412hr.

Conclusion:

Therefore, for 70 % expected demand flow:

Themaximum queue length that will be formed is qmax=400Veh, the total delay is dr=445hr,

The number of vehicles that will be affected by the incident is 10800Veh and the average individual delay is 0.0412hr.

To determine

(b)

The maximum queue length that will be formed, total delay, number of vehicles that will be affected by the incident, the average individual delay for the expected demand flow of 75%of the capacity of the highway.

Expert Solution
Check Mark

Answer to Problem 20P

For 75 % expected demand flow:

Themaximum queue length that will be formed is qmax=1000Veh.

The total delay is dr=1334hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 0.1235hr.

Explanation of Solution

Given:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering - With Mindtap, Chapter 6, Problem 20P , additional homework tip  2

Calculation:

For the expected 75 % demand flow:

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 75 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 75%of6000)4000)2qmax=(( 6000× 75 100 )4000)2qmax=(( 60×75)4000)2qmax=(45004000)2qmax=1000Veh.

Themaximum queue length that will be formed is qmax=1000Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=22( 75%of60004000)( 60004000)2( 600075%of6000)dr=4( 45004000)( 2000)2( 60004500)dr=4( 500)( 2000)3000dr=8( 500)3dr=1333.33=1334hr.

The total delay is dr=1334hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.=10800Veh.

The number of vehicles that will be affected by the incident is 10800Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =133410800.=0.1235hr.

The average individual delay is 0.1235hr.

Conclusion:

For 75 % expected demand flow:

Themaximum queue length that will be formed is qmax=1000Veh, the total delay is dr=1334hr, the number of vehicles that will be affected by the incident is 10800Veh and the average individual delay is 0.1235hr.

To determine

(c)

The maximum queue length that will be formed, total delay, number of vehicles that will be affected by the incident, the average individual delay for the expected demand flow of 80% of the capacity of the highway.

Expert Solution
Check Mark

Answer to Problem 20P

For 80 % expected demand flow:

Themaximum queue length that will be formed is qmax=1600Veh.

The total delay is dr=2667hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 0.247hr.

Explanation of Solution

Given:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering - With Mindtap, Chapter 6, Problem 20P , additional homework tip  3

Calculation:

For the expected 80 % demand flow:

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 80 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 80%of6000)4000)2qmax=(( 6000× 80 100 )4000)2qmax=(( 60×80)4000)2qmax=(48004000)2qmax=1600Veh.

The maximum queue length that will be formed is qmax=1600Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=22( 48004000)( 60004000)2( 60004800)dr=4( 800)( 2000)2( 1200)dr=4( 800)( 20)24dr=2666.66hr.dr=2667hr.

The total delay is dr=2667hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.=10800Veh.

Therefore, the number of vehicles that will be affected by the incident is 10800Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =266710800.=0.247hr.

The average individual delay is 0.247hr.

Conclusion:

For 80 % expected demand flow:

Themaximum queue length that will be formed is qmax=1600Veh, the total delay is dr=2667hr, the number of vehicles that will be affected by the incident is 10800Veh and

the average individual delay is 0.247hr.

To determine

(d)

The maximum queue length that will be formed, total delay, number of vehicles that will be affected by the incident, the average individual delay for the expected demand flowof 85% of the capacity of the highway.

Expert Solution
Check Mark

Answer to Problem 20P

For 85 % expected demand flow:

Themaximum queue length that will be formed is qmax=2200Veh.

The total delay is dr=4889hr.

The number of vehicles that will be affected by the incident is 10800Veh.

The average individual delay is 0.453hr.

Explanation of Solution

Given:

We have been given the following information:

Total number of lanes = 3,

  V=90%of6000,

  tinc=2hr,

Mean free flow speed of the highway = 55 mi/h,

Jam density = 135 veh/mi/ln,

  Cr=4000.

Following is the lay out of the given highway section:

  Traffic and Highway Engineering - With Mindtap, Chapter 6, Problem 20P , additional homework tip  4

Calculation:

For the expected 85 % demand flow:

We have the following formula for the determination of maximum queue length that will be formed:

  qmax=(VCr)tinc

Where, qmax is the maximum queue length,

  V is the total volume,

  Cr is the reduced capacity,

  tinc is the duration of the incident.

Considering 85 percent of the flow and that the capacity of each lane is 2000 Veh/ h

Substituting the values in the following equation, we have

  qmax=(VCr)tincqmax=(( 85%of6000)4000)2qmax=(( 6000× 85 100 )4000)2qmax=(( 60×85)4000)2qmax=(51004000)2qmax=2200Veh.

Therefore, the maximum queue length that will be formed is qmax=2200Veh.

Now, the total delay, we have the following formula

  dr=tinc2(VCR)(CCR)2(CV)

Where, CR is the reduced capacity and can be found as follows:

  CR=Numberoflanesinuse×capacityofeachlane.CR=2000×(31).CR=2000×2=4000Veh/h.

And C is the total capacity and can be found as

  C=Totalnumberoflanesinuse×capacityofeachlane.C=2000×3.C=6000Veh/h.

Now, substituting the values in the required equation, we have

  dr=t inc2( V C R )( C C R )2( CV)dr=22( 85%of60004000)( 60004000)2( 60005100)dr=4( 51004000)( 2000)2( 900)dr=4( 1100)( 20)18dr=4888.88hr.dr=4889hr.

Therefore, the total delay is dr=4889hr.

The number of vehicles that will be affected by the incident.

To calculate the number of vehicles that will be affected by the incident can be found using the following formula:

Number of vehicles affected = V×tinc.

Substituting the values, we have

  =5400×2.00.=10800Veh.

The number of vehicles that will be affected by the incident is 10800Veh.

To calculate the average individual delay, we have the following formula:

Average individual delay =drNumber of vehicles affected 

Substituting the values, we have

  Averageindividual delay=drNumber of vehicles affected =488910800.=0.453hr.

the average individual delay is 0.453hr.

The graph of average individual delay versus the expected demand flow is as follows:

  Traffic and Highway Engineering - With Mindtap, Chapter 6, Problem 20P , additional homework tip  5

Conclusion:

For 85 % expected demand flow:

Themaximum queue length that will be formed is qmax=2200Veh, the total delay is dr=4889hr, the number of vehicles that will be affected by the incident is 10800Veh and

the average individual delay is 0.453hr.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The number of vehicles arriving at the upstream of a freeway bottleneck (free of queues) is shown in the table below. Based on the numbers given in the table, determine: (1) Bottleneck capacity in vehicles per hour (vph) (2) Downstream measured flow rate in the third time interval (3) The demand during the third time interval (4) Queue length at the end of the third and fourth intervals
Question 3 An accident on a freeway of constant flow (arrival rate) of 2430 vehicles per hour occurred at a point X closing the freeway to all morning traffic at 07h00. At 07h15 the freeway is partially opened with a capacity of 1900 vehicles per hour. Finally, the wreckage is removed and, the freeway is restored to a full capacity of 4200 vehicles per hour at 07h35. Assuming a deterministic queue model, (i) graphically illustrate the above traffic flow information (ii) determine the following: - time of queue dissipation ongest queue length - total delay average delay per vehicle - longest wait of any vehicle, assuming a first-in-first-out departure scenario. -
Use 2 decimal places in your final 4. Route 1 has a free flow travel time of 10 minutes and the average travel time on this route increases by 3 minutes for every vehicle increase and Route 2 has a free flow travel time of 15 minutes and its average travel time increases by 2 minutes for every vehicle increase. Compare the results for UE and SO conditions with a flow rate is 12 veh/hr, determine the ff: Travel times on each route Traffic volumes on each route Total system travel time ■
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning