Concept explainers
a)
To draw: A decision tree for the given problem.
Introduction:
Decision tree is one of the methods used in decision-making process. It would graphically represent the available alternatives and states of nature. It would also mention the payoffs and probabilities of the alternatives. It helps to choose the best alternative that would give the best result among the alternatives.
a)
Explanation of Solution
Given information:
Three decision alternatives:
- 1st construct small stamping plant
- 2nd construct medium stamping plant
- 3rd construct stamping plant
Each decision has demand:
- Low demand which have 20% probability
- Low demand which have 80% probability
- If firm build small facility and demand turn out to be low than
NPV is $42,000,000 - If firm build small facility and demand turn out to be high than either subcontract or expand greatly, if sub contract than NPV is $42,000,000 and if expand greatly than $48,000,000.
- If firm build medium facility and demand turn out to be low than NPV is $22,000,000.
- If firm build medium facility and demand turn out to be high than either it do nothing or expand, if sub contract than NPV is $46,000,000 and if expand greatly than $50,000,000.
- If firm build large facility and demand turn out to be low than NPV is -$20,000,000.
- If firm build large facility and demand turn out to be high than NPV is $72,000,000.
As per given information, construct the decision tree:
Now, calculate the value of payoff and monetary value in decision tree:
Analysis the decision from right to left:
- In the decision tree, there are two decisions making; first decision is between small, medium and large and second decision is between high demand of small and medium build facilities.
- If small facilities build with high demand then select expand greatly because the payoff of expand greatly is higher than subcontract. The payoff of expand greatly is $48,000,000 and place double slash (reject) on subcontract.
- If large facility build with high demand then select expand, because the payoff of expand greatly is higher than do nothing. The payoff of expand is $50,000,000 place double slash (reject) on do nothing.
Calculate the product of the chance probabilities and their respective payoffs for the remaining branches:
- If small facility build:
- If medium facility IS build:
- If large facility is build:
Calculation of the expected value in each alternative:
- If small facility build
- If medium facility build
- If large facility build
Here, it is obtained that large facility build have higher expected value, hence it should be selected. And small and medium facilities have to be rejected.
b)
To determine: Maximin alternatives
Introduction:
Maximin is the decision making method which is used to make decision under uncertainty. This method will find an alternative that maximizes the minimum outcome of every alternative or we can say that calculating the minimum outcome within the each alternative.
b)
Answer to Problem 9P
Explanation of Solution
Determine the worst possible alternatives from the given demand:
As definition stated above, Maximim is the selection from the best of the worst possible payoff for each alternatives.
Alternative | Next Year’s Demand | Worst Payoff | Decision | |
Low | High | |||
Small | $42,000,000.00 | $48,000,000.00 | $42,000,000.00 | Best of the Worst |
Medium | $22,000,000.00 | $50,000,000.00 | $22,000,000.00 | |
Large | -$20,000,000.00 | $72,000,000.00 | -$20,000,000.00 |
Hence, the best decision according to Maximin decision is to select a small medium facility.
c)
To determine: Expected value of perfect information (EVPI) and interpret it.
Expected value of perfect information: It is the rate that a person is willing to pay to gain access to perfect information. A common area which uses expected value of perfect information is the healthcare economy. This value tries to evaluate the expected cost of the uncertainty, which can be interpreted as the expected value of perfect information
The expected value of perfect information can be calculated by using below given formula:
c)
Answer to Problem 9P
Explanation of Solution
Calculate the expected value with perfection information or Expected payoff under certainty:
Calculate the expected value with perfect information:
Therefore, EVPI is $12,400,000.
d)
To determine: The sensitive analysis on P (high).
Introduction
Decision table is formats or visual representations were data is expressed arranged, determined and calculated to make a effective decision making. A decision table is a tabular representation that is used to analyze decision alternatives and states of nature.
d)
Explanation of Solution
Explanation
Here we draw each alternative to P (high), low demand should be on the left hand side and high demand value on the right hand side:
Next Year’s Demand | ||
Alternative | Low | High |
Small | $42,000,000.00 | $48,000,000.00 |
Medium | $22,000,000.00 | $50,000,000.00 |
Large | -$20,000,000.00 | $72,000,000.00 |
Graph plot:
From the above graph, we can determine the value of P (high) where each alternative are optimal.
From the graph, we can obtain that small build facility is best option, because of higher expected value. For low value of P(high) while for higher and intermediate value of P(high) large is the best option.
Calculate the range needed to determine upper part of line intersects:
For each line, b is the slope of the line and x = P(High). The slope of each line
Determination of equation:
Small build facility = 42+6P (because high demand $48 million which is subtracted with low demand value $42 million)
Large build facility =-20+92P (because high demand $72million which is subtracted with low demand value -$20million)
Determination of intersection between small and large
Hence, the intersection between small and large is 0.7209.
Therefore, optimal range can be derived as:
Small: P (High) = 0 to < .7209
Large: P (High) > .7209 to 1.00
Want to see more full solutions like this?
Chapter 5 Solutions
Operations Management
- If the values (Revenue - Cost) for the option for a retail store to move to a new location associated with the events strong growth and weak growth are $ 200000 and $100000 respectively, calculate the expected value for the option to move to a new location. The probability of strong growth = 55%.arrow_forward1. A builder has located a piece of property that she would like to buy and eventually build on. The land is currently zoned for four homes per acre, but she is planning to request new zoning. What she builds depends on approval of zoning requests and your analysis of this problem to advise her. With her input and your help, the decision process has been reduced to the following costs, alternatives, and probabilities: Cost of land: $2 million. Probability of rezoning: 0.60. If the land is rezoned, there will be additional costs for new roads, lighting, and so on of $1 million. If the land is rezoned, the contractor must decide whether to build a shopping center or 1,500 apartments that the tentative plan shows would be possible. If she builds a shopping center, there is a 70 percent chance that she can sell the shopping center to a large department store chain for $4 million over her construction cost, which excludes the land; and there is a 30 percent chance that she can sell it to an…arrow_forwardAdam has been offered to open up a Service station. However, the size of the establishment will be based on his decision. The annual return and investment required will be based on both size and market condition. To help out in the decision making, Adam has done the analysis and the expected profit/loss are shown in the table: What is the maximax,maximin and equally likely decision? Develop a decision treearrow_forward
- Build New plant option=arrow_forwardSee picture for question details.arrow_forwardII. + James Scott is considering the possibility of opening a small outfit shop on Sta. Maria District, a few blocks from St. Green Ville College. She has located on a mall that attracts students. To open a small shop, medium sized shop, or no shop at all are her options. The market can be good, average, or bad. The probabilities for these three possibilities are 30% for good market, 50% for an average market, and 20% for bad market. The profit or loss for the said market conditions are given in the table below; ALTERNATIVE Small Shop Medium Sized Shop No Shop GOOD 150,000 200,000 0 AVERAGE 50,000 70,000 0 a) Calculate the Expected Value of Perfect Information (EVPI) b) What do you recommend? BAD -80,000 -120,000 0arrow_forward
- The city of Winnipeg is considering whether to build a new public ice rink. This rink would have a capacity of 800 ice skaters per day, and the proposed admission fee is $6 per individual per day. The estimated cost of the ice rink, averaged over the life of the rink, is $4 per ice skater per day. The city of Winnipeg has hired you to assess this project. Fortunately, Ottawa already has an ice rink, and the city of Ottawa has randomly varied the price of that rink to find how price affects usage. The results from their study follow: Ice rink price Number of ice skaters per day $8 $10 $4 $6 $2 per day 500 200 1100 800 1400 a. If the ice rink is built as planned, what would be the net benefit per day from the ice rink? What is the consumer surplus for ice skaters? b. Given this information, is an 800-ice rink the optimally sized ice rink for Winnipeg to build? Explain.arrow_forwardThe owners of Sweet-Tooth Bakery have determined thatthey need to expand their facility in order to meet their increaseddemand for baked goods. Th e decision is whether to expand nowwith a large facility or expand small with the possibility of havingto expand again in fi ve years.Th e owners have estimated the following chances for demand:• Th e likelihood of demand being high is 0.70.• Th e likelihood of demand being low is 0.30.Profi ts for each alternative have been estimated as follows:• Large expansion has an estimated profi tability of either$80,000 or $50,000, depending on whether demand turnsout to be high or low.• Small expansion has a profi tability of $40,000, assumingdemand is low.• Small expansion with an occurrence of high demand wouldrequire considering whether to expand further. If the bakeryexpands at this point, the profi tability is to be $50,000.(a) Draw a decision tree showing the decisions, chanceevents, and their probabilities, as well as the profi tabilityof…arrow_forwardSuppose that an aircraft manufacturer desires to make a preliminary estimate of the cost of building a 600-MW fossil-fuel plant for the assembly of its new long-distance aircraft. It is known that a 200-MW plant cost $100 million 20 years ago when the approximate cost index was 400, and that cost index is now 1,200. The cost-capacity factor for a fossil-fuel power plant is 0.79.arrow_forward
- please answer in excel format showing formulasarrow_forwardABC Inc is considering the possibility of building an additional factory that would produce a new addition to its product line. The company is currently considering 2 options. The first is a small facility that could build be built at a cost of $6million. If demand for the new product is low, the company expects to receive $10million in discounted revenues(present value of future revenues) with the small building. On the other hand, if demand is high, it expects $12million in discounted revenues using the small building.The second option is to build a large facility at a cost of $9million. If the demand were to low, the company would expect $10million in discounted revenues with the large building. If demand is high, the company estimates that the discounted revenues would be $14million. In either case, the probability of demand being high is 0.40, and the probability of it being low is 0.60. Not constructing a new facility would result in no additional revenue being generated…arrow_forward1. Kirsten is trying to decide where to go for her well-earned vacation. She would like to camp, but if the weather is bad, she will have to go to a motel. Given the costs and probabilities of bad weather given below, which destination should she choose? Camping cost Motel cost Probability of bad weather Nevada $21.2 $80.9 0.2 Oregon $15.9 $84.6 0.4 California $30 $95 0.1 a. California, because its EMV = $33.14 b. Nevada, because its EMV = $33.14 c. California, because its EMV = $36.5 d. Any of the 3 choices. e. Oregon, because its EMV = $43.38 f. Nevada, because its EMV = $43.38 g. None of the 3 choices. h. Oregon, because its EMV is $36.50.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning