Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9781259666094
Author: Erik W. Larson, Clifford F. Gray
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 5.1A, Problem 1E
How many labor hours should the eighth satellite require?
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
How do scheduling activities differ for projects, mass pro-duction, and process industries?
Why managers are concerned with timing when scheduling production?
William, a project manager, has a workload of 25,000 hours that needs to be completed in 30 weeks. He has a team of 20 people who work five 8-hour days per week. He notices that in the 30-week period, there are three holidays and 6 members have each requested 8 days off. Given this information, William is _____ short of completing his workload.
Question options:
23,136 hours
1,864 hours
480 hours
1,480 hours
384 hours
Chapter 5 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 5.1A - How many labor hours should the eighth satellite...Ch. 5.1A - How many labor hours for the whole project of...Ch. 5.1A - What price would you ask for the project? Why?Ch. 5.1A - Midway through the project your design and...Ch. 5.1A - Near the end of the project, Deutsch Telefon AG...Ch. 5 - Why are accurate estimates critical to effective...Ch. 5 - Prob. 2RQCh. 5 - Prob. 3RQCh. 5 - What are the major types of costs? Which costs are...Ch. 5 - Why is it difficult to estimate mega project...
Ch. 5 - Define what a white elephant is in project...Ch. 5 - Calculate the direct cost of labor tor a project...Ch. 5 - Mrs. Tolstoy and her husband, Serge, are planning...Ch. 5 - Exercise Figure 5.1 is a project WBS with cost...Ch. 5 - Firewall Project XT. Using the complexity...Ch. 5 - At this point, what would you do if you were the...Ch. 5 - Prob. 5.1.2CCh. 5 - What estimating techniques should be used for a...Ch. 5 - Assume you are either Mike or Josh; how would you...Ch. 5 - Prob. 5.2.2CCh. 5 - After cost, what other factors should be...
Additional Business Textbook Solutions
Find more solutions based on key concepts
10-10 What challenges do managers face in managing global teams? How should those challenges be handled?
Fundamentals of Management (10th Edition)
Describe and evaluate what Pfizer is doing with its PfizerWorks.
Management, 13Th Edition
11-9. Identify a company with a product that interests you. Consider ways the company could use customer relati...
Business Essentials (11th Edition)
11-9. Identify a company with a product that interests you. Consider ways the company could use customer relati...
Business Essentials (12th Edition) (What's New in Intro to Business)
Much of risk management consists of reducing risky behavior. What kinds of risky behavior have you observed amo...
Understanding Business
Describe and evaluate what Pfizer is doing with its PfizerWorks.
Management (14th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- l TelkomSA 11:00 A ikamva.uwc.ac.za An IT project manager of ABC Company has developed an activity list for the purpose of tracking employees' daily activities on the project. The project's schedule is considered to be of high risk due to the possibility of sabotage by some of the employees. In addition, the IT project manager has gathered time information for each activity, as shown in the table below. Consider the following project's tasks and their identified best, likely, and worst case estimates of task duration. Assume the organization computes PERT weight average based on the standard formula. Activity Optimistic Most Pessimistic likely A 5 5 25 3 5 8 7 8. D 4 4 5 E 10 19 34 F 3 14 18 G 6. 16 20 H 32 44 65 12 17 25 J 2 8 18 The dependencies between the 10 activities listed in the table above are as follows: The project starts with two activities-A, and B-which can be done concurrently. • When activity A is finished, activity C can start • When activity B is finished, activities…arrow_forwardThe product development group at “Griffin” Company has already worked on new computer software products that has potential to know a large market share. Via an outside source, London Management has learned that a competitor is working to bring a similar product to market. As a result, London's top management increased its pressure on the product development group. Group leaders have turned to CPM / PERT as an aid to scheduling remaining activities before new products can be brought to market. The estimated time of activity in a day is as follows a.Create the the network if it is accelerated according to the schedule above b.Find the cost and the duration c.Determine the path and critical activitiesarrow_forwardThe product development group at “Griffin” Company has already worked on new computer software products that has potential to know a large market share. Via an outside source, London Management has learned that a competitor is working to bring a similar product to market. As a result, London's top management increased its pressure on the product development group. Group leaders have turned to CPM / PERT as an aid to scheduling remaining activities before new products can be brought to market. The estimated time of activity in a day is as follows Question: Create an initial network Find the cost and the duration Determine the path and critical activitiesarrow_forward
- A project consist of 5 activities A,B,C,D,E with ES, EF, LS and LF of A (0, 6, 9, 15); B (0, 7, 0, 7); C (6, 13, 15, 22); D (7, 13, 7, 13); E (13, 22, 13, 22). Normal Time (in month), Crash time (in month), Normal cost (in million Rp), Crash cost (in million Rp) from each activity are A (6, 4, 20, 24); B (7, 5, 30, 35); C (7, 6, 10, 13); D (6, 4, 20, 26); E (9, 8, 88, 90) a. What activities are in the critical path? How long is the project duration? b. If we want to crash the project for 2 months, what activities need to be crashed? How much additional cost required?arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $6,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Activity A B с D E F G Immediate Predecessor(s) AB Activity A B с D A C D, E E Normal Time Crash Time (weeks) (weeks) 3 1 2 2 1 3 4 1 6 3 Time according to schedule (weeks) 1 a. What is the shortest time duration for this project regardless of cost? The shortest project duration regardless of cost is 9 weeks. (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? The minimum total cost to complete the project in 12 weeks is $ 203500. (Enter your response as a whole number.) c. What is the total time of the minimum-cost schedule? (Enter your responses as whole numbers.) The total…arrow_forward4G+ 2:27 PM ě 4.3KB/s l 54 00:19:06 Remaining An activity in a PERT network is expected to require 54 days to complete. This estimate was calculated using the PERT formula based on an optimistic completion time of 48 days and a most likely completion time of 50 days. What estimate was used for the pessimistic completion time (t_P)? 54 days O 98 days O 76 days O 50 1/3 days 6 of 20arrow_forward
- Preceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!arrow_forwardFarihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forwardDescribe the Evaluation and Review Technique (PERT) for network planning and scheduling?arrow_forward
- Ed is planning to build a treehouse as a present for his son's upcoming 10th birthday. The details for each task are as follows: DE F G AD C,E F 12 Task A B Preceding Task Duration (day) | 12 A B 10 12 5 Cost (RM) 50 140 120 60 70 80 60 (a) Obtain the following: • The number of days it will take for Ed to finish building the treehouse. • Which tasks are cannot be delayed at all without delaying the whole project. • The total cost of building the treehouse. (b) Due to illness, Ed has to begin building the treehouse later than planned. He reckons that he must reduce the build duration by 3 days to complete the treehouse by his son's birthday. He has determined the crash cost and crash time for each task as follows: Task А В С DE F G Crash Time (day) | 12 8 9 8 10 5 6 Crash Cost (RM) | 50 170 180 70 95 80 60 Obtain the following: • All tasks that are crashed and by how much. • The new total cost for building the treehouse.arrow_forwardDesign a Gantt chart using the following data. TASK ASSIGN TO START END DURATION STATUS Ferry Maintenance Maria 01/01/2023 08/01/2023 7 Completed Crew Scheduling Maria 08/01/2023 15/01/2023 7 Completed Passenger & Cargo Handling Maria 15/01/2023 22/01/2023 7 Completed Route Planning Kerry Ann 22/01/2023 04/02/2023 13 Completed Safety & Emergency Planning Kerry Ann 02/02/2023 11/02/2023 9 Completed Ticketing & Payment Kerry Ann 11/02/2023 18/02/2023 7 Completed Marketing & Website Design Shenae 18/02/2023 25/02/2023 7 Completed Advertising Shenae 25/02/2023 04/03/2023 7 Completed Testing Jenerlee 04/03/2023 11/03/2023 7 Completed Implementation Jenerlee 11/03/2023 26/03/2023 15 Completedarrow_forwardStart date: April 8 (Friday) Working days:Monday-Saturday When will you start renting the sound equipment? When will you start printing the certificates and programme? When will you start disseminating the information?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY