Simplified Engineering for Architects and Builders, 12/E (HB-2016)
Simplified Engineering for Architects and Builders, 12/E (HB-2016)
12th Edition
ISBN: 9781118975046
Author: AMBROSE J
Publisher: Wiley,,Hoboken : Wiley, 2016
bartleby

Concept explainers

Question
Book Icon
Chapter 4.7, Problem 1P
To determine

Find the preliminary concrete moment frame system for the reinforced concrete frame with concrete masonry units’ infill shear walls on the exterior of office building.

Find the amount of concrete and steel saved when using concrete masonry units and also find the additional structural dead load added by the concrete masonry units.

Expert Solution & Answer
Check Mark

Answer to Problem 1P

The shape and the size of the column is square(14in.×14in.)_.

The dimension of the beam is 14in.×28in._.

The dimension of the joist is 12in.×18in._.

The slab thickness using in the project is 8in._.

The percentage saved in the concrete quantity is 48%_.

The percentage saved in the steel quantity is 22%_.

The structural dead load added by the CMU unit is 6,080kips_.

Explanation of Solution

Given information:

The floor plan is L in shape.

The number of stories in the building is 4 with a roof.

The floor-to-floor height between the first and second stories is 24 ft.

The floor-to-floor height for the upper floors is 15 ft.

The thickness of reinforced block used in this project is 8 in..

The percentage covered by the reinforced block in the building’s exterior walls between the beams and columns is 60 %.

Calculation:

The estimation of diaphragm of the office building has done by calculating the diaphragm of the two rectangles in the given floor plan. The dimension of the first rectangle is (100×210)ft and other dimension of second rectangle is (80×140)ft.

Determine the length to width ratio (lb)R1 of the first rectangle.

Substitute 100 ft for l and 210 ft for b.

(lb)R1=100210=1:2.1

Determine the length to width ratio (lb)R2 of the first rectangle.

Substitute 80 ft for l and 140 ft for b.

(lb)R2=80140=1:1.75

The value of length to width ratio of two rectangles is less than the maximum ratio required for an optimal diaphragm (1:3). Therefore, the diaphragm should work with the given condition.

Column–beam layout:

The floor plan has the irregularities resulting the column–beam layout will not produce equal structural bays. The aim of the design is to produce a floor plan with the fewest number of columns is suitable given that the floor-to-floor heights are sufficient to handle deeper beams.

The dimension of (100×130)ft segment can be divided into three bays of 33 ft 4in. by three bays of 43 ft 4 in..

The dimension of (100×80)ft segment can be divided into three bays of 33 ft 4in. by two bays of 40 ft.

The dimension of (40×80)ft segment can be divided into one bay of 40 ft by two bays of 40 ft. At last the three concrete joists per primary beam will be used to support the floor.

Column size:

Refer Table 4.3, “Determinates for column dimensions” in the textbook.

As per Table 4.3, the project has the four stories and column spacing of 24 ft for first and second floor and 15 ft for other floors defines that the project is moderate project.

The project is falls under the large project due to the column spacing 39 ft is greater than the 36 ft and 4 stories makes it a moderate project.

Refer Table 1.3, “Minimum floor live loads” in the textbook.

Take the uniformly distributed load as 50 psf for offices, 100 psf for lobbies and first-floor corridors, and 80 psf for corridors above first floor.

The offices have the floor live load of 50 psf, which would be a modest project. Lobbies and first floor corridors have the floor live load of 100 psf, and corridors above first floor have the 80 psf, which would be a moderate project.

For the moderate project, take the moderate column size of 14 in. with the square shape.

Therefore, the shape and the size of the column is square(14in.×14in.)_.

Beam, joist, and floor slab dimensions:

The width of beam is typically same as the width of the column. The beam width is taken as 14 in.

The depth of the concrete beam is approximately equal to 2 times the beam width. Hence, the depth of beam is 2×14=28in.. The dimension of the beam is 14in.×28in..

Therefore, the dimension of the beam is 14in.×28in._.

The joist widths are usually 2 in. less the width of the secondary beam. The joist width is taken as 142=12in.. The joist depth is approximately equal to 1.5 times its width. Hence, the joist depth is 1.5×12=18in..

Therefore, the dimension of the joist is 12in.×18in._.

The three concrete joists per primary beam will be supporting the floor.

Take the slab thickness of 8 in. due to the usage of beam and joist.

Therefore, the slab thickness using in the project is 8in._.

The first and second floor has the column height of 24 ft and upper floor has the column height of 15 ft.

Find the area of the column using the relation.

Ac=bc×dc

Here, bc is the width of the column and dc is the depth of the column.

Substitute 14 in. for bc and 14 in. for dc.

Ac=14×14=196in.2×(1ft12in.)2=1.36ft2

Find the area of the beam using the relation.

Ab=bb×db

Here, bb is the width of the beam and db is the depth of the beam.

Substitute 14 in. for bb and 28 in. for db.

Ab=14×28=392in.2×(1ft12in.)2=2.72ft2

Find the area of the joist using the relation.

Aj=bj×dj

Here, bj is the width of the joist and dj is the depth of the joist.

Substitute 12 in. for bj and 18 in. for dj.

Aj=12×18=216in.2×(1ft12in.)2=1.5ft2

Consider the height of the column in the ground floor and the above the roof.

Determine the total length of the column using the relation.

Totallength=(24×2+15×4)=108ft

The number of primary beams is 5.

Determine the total length of the beam using the relation.

Totallength=4×210+1×80=920ft

The number of joist is 10.

Determine the total length of the joist using the relation.

Totallength=10×100+4×40=1,160ft

Quantity of concrete and steel:

Show the estimation of concrete and steel quantities as in Table (1).

Element

Quantity of

Concrete (ft3)

Average % of steelQuantity of steel (ft3)
Columns{1.36ft2×108ft×27columns}=3,9662 %79 (17 tons)
Beams{2.72ft2×920ft×5floors}=12,5124 %501(112 tons)
Joists{1.5ft2×1,160ft×5floors}=8,7004 %348 (78 tons)
Slabs{0.67ft×24,200ft2×5floors}=81,0700.25 %202.7 (45 tons)
 106,248ft3 (7,240 tons) 1,130 (252 tons)
CMU Reinforced blocks{0.67ft×60100×24,200ft2×5floors}=48,6420.25 %122
Total quantity106,248ft348,642ft3=57,606ft3(3,926tons) 1,130122=1,008(225tons)

Refer Table 4.6, “Estimates of concrete and steel quantities for Example 3” in the textbook.

Refer Table 1.

Determine the percentage saved in the concrete quantity using the relation.

Pc=111,42057,606111,420×100=48%

Therefore, the percentage saved in the concrete quantity is 48%_.

Determine the percentage saved in the steel quantity using the relation.

Ps=1,2851,0081,285×100=22%

Therefore, the percentage saved in the steel quantity is 22%_.

Determine the structural dead load added by the CMU unit using the relation.

DL=48,642×125lb/ft3=6,080,250lb×1kip1,000lb=6,080kips

Therefore, the structural dead load added by the CMU unit is 6,080kips_.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
11:34
Students have asked these similar questions
Design Flow TABLE 3.1: Typical Distribution of Per-Capita Water Demand Average use Category (L/d) (gal/d) Percent of total Residential 380 100 56 Commercial 115 17 Industrial 85 22 12 Public 65 17 9 Loss 40 11 6 Total 685 180 100 Source: Solley (1998). TABLE 3.2: Typical Demand Factors Demand Minimum Maximum Typical Daily average in maximum month 1.10 1.50 1.20 Daily average in maximum week 1.20 1.60 1.40 Maximum daily 1.50 3.00 1.80 Maximum hourly 2.00 4.00 3.25 Minimum hourly 0.20 0.60 0.30 Design Flow Component TABLE 3.7: Typical Design Periods and Capacities in Water Supply Systems 1. Source of supply: River Wellfield Reservoir Design period (years) Design capacity Indefinite Maximum daily demand 10-25 25-50 Maximum daily demand Average annual demand 2. Conveyance Intake conduit 25-50 Maximum daily demand Conduit to treatment plant 25-50 Maximum daily demand 3. Pumps: Low-lift 10 Maximum daily demand, one reserve unit High-lift 10 Maximum hourly demand, one reserve unit 4.…
:
Solve this question in two ways: Aria and Section

Chapter 4 Solutions

Simplified Engineering for Architects and Builders, 12/E (HB-2016)

Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Structural Analysis
Civil Engineering
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:Cengage,
Text book image
Structural Analysis (10th Edition)
Civil Engineering
ISBN:9780134610672
Author:Russell C. Hibbeler
Publisher:PEARSON
Text book image
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Text book image
Fundamentals of Structural Analysis
Civil Engineering
ISBN:9780073398006
Author:Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:McGraw-Hill Education
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning