Construction Management
Construction Management
5th Edition
ISBN: 9781119256809
Author: Daniel W. Halpin, Bolivar A. Senior, Gunnar Lucko
Publisher: WILEY
bartleby

Concept explainers

Question
100%
Book Icon
Chapter 4, Problem 2RQE
To determine

Find the type of contract to perform excavation contract competitively with limited boring data, and explain the reason.

Blurred answer
Students have asked these similar questions
Which of the following is not a phase of construction project? Select one: a. Tendering b. Estimation c. Briefing d. Commissioning Question 29 Not yet answered Marked out of 1.00 P Flag question What would be the payback period of excavator generating annual return of $70000 and initial cost $350000 and service life 7 years? Select one: a. 2 YEARS b. 3 YEARS c. 4 YEARS
17.6 The following planned figures for a trenching job are available: Quantity                                            Resources(hours)                          Cost Excavation—second                       Machines1000                                  $100,000 Hauling                                              Labor 5000                                        $100,000 100,000 cubic yard                          Trucks 2000                                      $ 62,500 At a particular time during the construction, the site manager realizes that the actual excavation will be in the range of 110,000 cubic yards. Based on the new quantity, he figures that he will have 30,000 cubic yards left. From the main office, the following job information is available: Resources                                                    Cost Machines                   895 hours                  85000 Labor                          6011 work hours       79000 Trucks                        1684 hours…
The total estimated duration of the mass excavation activities in an office building project is 40 days. After 18 days, the project manager receives the following information: Activity Earth Clay Rock Total Volume to be excavated (cubic yard) What is the forecasted cost Select the correct response: 13,129.03 -16,633.06 20,000 8,000 11,000 -13,129.03 16,633.06 Unit Price 2.50 5.50 7.50 riance of rock excavation? Actual volume excavated (cubic yard) 8,400 3,100 6,200 Actual cost 19,750 20,850 53,900
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,