Question
Chapter 3, Problem 9RQE
To determine
List the reasons of changed conditions in a building contract, and also mention the clauses of the typical contract related to the changed conditions in a building contract.
Suppose separate contracts are given for building foundation and all remaining work, and the second contractor finds that the foundation is incorrectly calculated, find whether he will be able to assert a changed condition.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
C. Discuss the consideration provided under construction contracts by
a. Client
b. Contractor
True or false? A builder’s risk “all-risk” policy of construction insurance covers all perils without additional endorsement.
What type of work is conducted under the earthwork section of a construction contract?
Chapter 3 Solutions
Construction Management
Knowledge Booster
Similar questions
- Calculate the cost per cubic yard to place concrete using each of the alternatives described. The work in both cases consists of placing 140 cubic yards of concrete in footings. a. Using a crane and bucket at a price of $225 per hour, including an operator, with a crew consisting of 6 laborers, a cement finisher, and a foreman. The concrete will be placed in 7 hours using this setup, and transportation of the crane costs $390. b. Using a concrete pump at a price of $295 per hour, including an operator and a crew consisting of 5 laborers, a cement finisher, and a foreman. With this setup, concrete is placed in 6 hours and transportation of the pump costs $290.arrow_forwardwhat type of contract is this: (1) The supply by a wholesaler of 10,000 bricks to the site following a telephone request from the site agentarrow_forward6. Describe and provide and example of the most appropriate situation for the following: a) but-for or collapsed as-built analysis, b) line-of-balance and c) impacted baseline techniques. 7. Many contracts require that the contractor prepare and present the construction schedule and receive the owner's approval before any contract payments are made. Explain in detail what are the three elements of the contractor's schedule that the owner will typically be interested in?arrow_forward
- In a circumstances in a private construction where there are any indications that the work done is not in accordance with theDrawings and Specification, what are the rights of the owner and the responsibility or obligations of the contractor?arrow_forwardHow does the Total foundation settlement results?arrow_forwardAre the liquidated damages the common practice throughout the construction?arrow_forward
- Is the ownership of materials to be used in the work and stored at the site vested in the contractor?arrow_forward. Describe the three types of authorities exercised in a construction contract?arrow_forward1. Four legal components are required for construction contracts to be valid include 3. 2. The following were common forms of construction contracts: 1... 4. 5. 1. 6. 7. **** the owner will pay the builder an agreed-upon amount of money for the completion of a project that complies with a clearly defined scope of work. the owner will pay to the constructor an agreed-upon of amount of money for the owner will reimburse the constructor for all costs specified each unit of work completed in a project. to construct the project. the current value of money is higher than its future value commonly represented as a percentage of the amount owedarrow_forward
- What are the obligations of the contractor?arrow_forwardQ1. Q2. Q3. Q4. Q5 Which of the following area in construction industry deals with tendering process A. Risk Management B. Financial Management C. Safety Management D. Procurement Which contract system has the highest risk for the client A. Traditional contract B. Cost plus fixed fee C. Design and Build D. Built Operate Transfer The contract system where the contractors must use their own source of fund to finance the project without getting the interim progress payment is known as A. Traditional contract B. Cost plus fixed fee C. Design and Build D. Built Operate Transfer At what phase of project life cycle where the client makes highest cost commitment for the project A. Design B. Procurement C. Construction D. Operation What is the main root factor that contribute to the fragmented work process in construction industry? A. The involvement of so many stakeholders in the construction project B. The practice of division of labour concept inherits from scientific management theory C.…arrow_forwardSelect a type of construction contract and make a brief discussion of its advantages and disadvantages to both the contractor and the owner.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,Construction Materials, Methods and Techniques (M...Civil EngineeringISBN:9781305086272Author:William P. Spence, Eva KultermannPublisher:Cengage Learning
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,
Construction Materials, Methods and Techniques (M...
Civil Engineering
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:Cengage Learning