The Hard Rock Mining Company is developing cost formulas for management planning and decision-making purposes. The company’s cost analyst has concluded that utilities cost is a mixed cost, and he is attempting to find a base with which the cost might be closely correlated. The controller has suggested that tons mined might be a good base to use in developing a cost formula. The production superintendent disagrees; she thinks that direct labor-hours would be a better base. The cost analyst has decided to try both bases and has assembled the following information:

Chapter 2A, Problem 2A.3P, Least-Squares Regression; Scattergraph; Comparison of Activity Bases [LO 2-4, LO 2-8] The Hard Rock

Required:

  1. Using tons mined as the independent variable: prepare a scattergraph that plots tons mined on the horizontal axis and utilities cost on the vertical axis. Determine a cost formula for utilities cost using least-squares regression- Express this cost formula in the form Y = a + b X .
  2. Using direct labor-hours as the independent variable: prepare a scattergraph that plots direct labor-hours on the horizontal axis and utilities cost on the vertical axis- Determine a cost formula for utilities cost using least-squares regression. Express this cost formula in the form Y = a + b X .
  3. Would you recommend that the company use tons mined or direct labor-hours as a base for planning utilities cost?

1.

Expert Solution
Check Mark
To determine

Concept Introduction:

Scatter-graph:Scatter-graph implies the visual presentation of data on the graph in which costs are shown on the y-axis and activity level is presented in the x-axis.

Least-square regression: Least square regression method use all the available data to derive the best fitting line which would minimize the sum of squared errors between the data points and the regression line.

To prepare:The scatter diagram using tons mixed and utilities cost and determine cost formula

Explanation of Solution

  Managerial Accounting for Managers, Chapter 2A, Problem 2A.3P , additional homework tip  1

The cost formula is Y=28352+2.58X where, Y is the utilities cost and X is the tons mixed.

Thus, the scatter diagram has been prepared, and least square regression has been performed and cost equation has been determined.

2.

Expert Solution
Check Mark
To determine

Concept Introduction:

Scatter-graph:Scatter-graph implies the visual presentation of data on the graph in which costs are shown on the y-axis and activity level is presented in the x-axis.

Least-square regression: Least square regression method use all the available data to derive the best fitting line which would minimize the sum of squared errors between the data points and the regression line

To prepare:The scatter diagram using tons mixed and utilities cost and determine cost formula

Explanation of Solution

  Managerial Accounting for Managers, Chapter 2A, Problem 2A.3P , additional homework tip  2

The cost formula is Y=17000+9X where, Y is the utilities cost and X is the direct labor hours Thus, the scatter diagram has been prepared, and least square regression has been performed and cost equation has been determined.

3.

Expert Solution
Check Mark
To determine

Concept Introduction:

Scatter-graph:Scatter-graph implies the visual presentation of data on the graph in which costs are shown on the y-axis and activity level is presented in the x-axis.

Least-square regression: Least square regression method use all the available data to derive the best fitting line which would minimize the sum of squared errors between the data points and the regression line

The activities to be selected as as a base for planning utilities cost

Answer to Problem 2A.3P

Direct labor hours should be taken as a base for planning utilities costs.

Explanation of Solution

The regression coefficient is 0.9346 when direct labor is taken as base whereas it is 0.4668 when tons mined is taken as base. Regression coefficient determines the accuracy with which the costs can be determined. Thus taking direct labor as base, the costs can be determined with 93.46% accuracy whereas the accuracy percentage is only 46.68% when tons mined are taken as base. Thus, the activity to be taken as a base for planning utilities cost has been determined.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Can you provide samples/examples of tasks for developing the costing and profitability model for a new product? Should include the following: o   A table showing the list of the parameters used in your model o   A breakdown of the expected production costs and profitability o   Calculation of the NPV of expected sales/ profitability o   A sensitivity analysis that accounts for changes in any three (3) parameters of your model. o   At least two trade-off rules you developed for your product development
Steele Industries manufactures a number of products at its highly automated factory. The products are very popular, with demand far exceeding the factory's capacity. To maximize profit, management should rank products based on their: gross margin O contribution margin O selling price O contribution margin per unit of the constrained resource
The managerial accountant at Fast and Mean Manufacturing reported that the organization contains an automated production line to manufacture and produce its products for consumers to enjoy in the marketplace. The managerial accountant reported that the company uses the high-low method to estimate the costs in the new budget. The managerial accountant reported the following information: Compute the slope of the mixed cost, or the variable cost per unit of activity. Compute the vertical intercept, or the fixed cost component of the mixed cost. What is the mixed cost equation? Month Total machine hours total cost January 250,000 $5,500,000 February 248,000 $5,260,000 March 249,000 $5,400,000 April 248,000 $5,220,000 May 238,000 $5,180,000 June 230,000 $5,130,000

Chapter 2A Solutions

Managerial Accounting for Managers

Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license