What is the minimum size service for a one-family dwelling? ____________________
Find the minimum rating of service size for a one-family dwelling.
Answer to Problem 1R
The minimum rating of service size for a one-family dwelling is
Explanation of Solution
Discussion:
The National Electrical Code committee develops NEC – the standard electrical code, and the main objective for the origin of the code is to protect and safeguard people and elements from electrical hazards. The codes that explain the rating of service disconnecting means are defined in an article NEC 230.79.
According to an article NEC 230.79 (C), for a one-family dwelling, the rating of the service disconnecting means should not be less than
Conclusion:
Thus, the minimum rating of service size for a one-family dwelling is
Want to see more full solutions like this?
Chapter 28 Solutions
Electrical Wiring Residential
Additional Engineering Textbook Solutions
Principles Of Electric Circuits
Microelectronics: Circuit Analysis and Design
Electronics Fundamentals: Circuits, Devices & Applications
Programmable Logic Controllers
Electric machinery fundamentals
Engineering Electromagnetics
- Explain with the aid of your investigations why a minimum separation between the individual wind turbines is necessary in large wind farms in order to avoid power losses. *********arrow_forwardExplain each option & Choose the correct option. 4) The _ calculated load is rarely placed on an electrical system.A. optionalB. standardC. total 5) What's the primary disadvantage of using copper conductors?A. CostB. AvailabilityC. Weight 6) You're evaluating the components of a multioccupancy building that won't have an on-site employee. To be compliant with the NEC, each occupant will need to have access to their ownA. service-disconnecting means.B. service conductor.C. cable attachment point.D. emergency fire water pump disconnect ..arrow_forward13. If an equipment bonding jumper is run external to a raceway, it must be less than _______ feet.A. 6B. 2C. 4D. 5arrow_forward
- 6. According to the NEC, allowance for the future expansion of installations isA. an exception.B. in everyone's best interest.C. defined.D. a requirement.arrow_forward___________ is an Area on a device characteristic where the ratio between applied voltage and resulting current is constant.arrow_forward1.1 PV modules can be wired together in an array using ______ connections to increase voltage. a. Terminating b. Series c. Parallel d. AC 1.2 A PV module, also called a solar panel, is comprised of individual photovoltaic _______ wired and mounted together as an integrated unit. a. Capsules b. Compartments c. Chips d. Cells 1.3 A __________ system uses a storage system that stores the generated electricity so it can provide during times when the system’s panels are not receiving solar energy. a. Direct coupled b. Self regulating c. Charge controlled d. Indirectly connected 1. 4 __________ energy may have the potential to supply all of the world's energy needs, but at this time, it provides a very small percentage. a. Coal b. Natural Gas c. Diesel d. Solararrow_forward
- A device used in kitchen serving hotels dining rooms club houses and restaurants is__________. a.) Grease basin b.) Yard basin c.) Garage basin d.) Oil catch basinarrow_forwardIf an electrical system operates at a potential higher than 600 volts, the nonmetallic conduit must be encased in at least_of concrete. A. 1 inch B. 2 inches C. 4 inches D. 6 inchesarrow_forward______________1. It checks the ability or range of operations of the electronic components that be run in the system. ______________2. It assesses the ability of the electronic components to exchange information or can access data without any restriction. ______________3. It evaluates the ability of the part to meet the functional, mechanical, and electrical performance requirements.arrow_forward
- If the total computed load of a residence is 45,840 volt-amperes, the computed amperage of the residence is __________ ampsarrow_forwardWhat color are the faceplates in the bathrooms? Refer to the specifications. ________________arrow_forwardPart 2: Analysis and selection of the Wind Turbine. The team decides at install a 30 MW wind farm. The turbine that has been selected by the local contractor is an Enercon wind turbine. The specifications of all the available Enercon wind turbine is shown in the attached datasheet. 1. Decide on the required number of wind turbines needed. 2. In your own words, explain what the Betz limit for wind turbines means.arrow_forward
- EBK ELECTRICAL WIRING RESIDENTIALElectrical EngineeringISBN:9781337516549Author:SimmonsPublisher:CENGAGE LEARNING - CONSIGNMENT