Chapter 23, Problem 23.4E
Explanation of Solution
Reducing risk in Cost estimation:
The possible techniques to reduce risk in cost estimation are as follows:
- Develop a prototype for those system parts that are hard to estimate in order to find out what problems are likely to arise.
- Software requirements are partitioned into critical, desirable, and gold plating. If necessary, gold plating is eliminated.
- Reuse software to reduce the amount of required estimation and the overall costs...
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The board of directors of a company determines that senior management
should be rewarded in order to achieve the company's objectives. The board of
directors determines whether to award bonuses based on growth in share value
at the conclusion of each fiscal year. Bonuses will be given in stock, which the
managers may keep or sell on the open market. What are the ramifications of
instituting a rewards scheme like this?
Use Critical Path Method to estimate in how many weeks the project below will be submitted and find the critical path.
(Choose 2 answers weeks and critical path)
Activity
A: Prepare initial design
B: Identify new potential clients
C: Develop prospectus for tenants A
D: Prepare final design
E: Obtain planning permission
F: Obtain finance from bank
G: Select contractor
H: Construction
I: Finalize tenant contracts
dependent
time
8
D
3
D
4
6, F
В, С, Е
I, H
17
13
J: Tenants move in
Critical path : A-D-E-F-H-J
O Critical path: A-C-E-F H-J
35 weeks
29 Weeks
Critical path : A-G-E-F-H-J
34 Weeks
The Spiral Model may be useful for planning and managing even the smallest of projects.
Chapter 23 Solutions
Software Engineering (10th Edition)
Ch. 23 - Prob. 23.1ECh. 23 - Explain why the process of project planning is...Ch. 23 - Prob. 23.3ECh. 23 - Prob. 23.4ECh. 23 - Prob. 23.5ECh. 23 - Prob. 23.6ECh. 23 - The planning game is based on the notion of...Ch. 23 - Prob. 23.8ECh. 23 - Prob. 23.9ECh. 23 - Is it ethical for a company to quote a low price...
Knowledge Booster
Similar questions
- Activity Predecessor Normal Time Activity Crash Normal Cost ($) Crash Cost ($) (days) Time (days) or Activities A 5 4 2000 2200 В 7 6. 1500 2000 C 5 4 2200 2400 D 10 8 2500 2800 E B 6. 5 1950 2350 F А, С 7 5 800 1450 G В 4 3650 4150 H E, D, G 6 5 1200 1550 a) What is the critical path for this project in Table 1, using the normal times (you are required to submit your CPM Arrow on Node Diagram)?arrow_forwardDetermine the output and input variables for cost estimates using the bottom-up and top-down approaches.arrow_forwardWhen conducting engineering economic analyses, it will be assumed at first, for simplicity, that benefits, costs, and physical quantities will be known with a high degree of confidence. This degree of confidence is sometimes called assumed certainty. In virtually all situations, however, there is some doubt as to the ultimate values of various quantities. Both risk and uncertainty in decision-making activities are caused by a lack of precise knowledge regarding future conditions, technological developments, synergies among funded projects, etc. Explain the difference between decisions taken under risk and the decision taken under uncertainty.arrow_forward
- What precisely does it imply when people talk about "algorithmic cost models," and how does one go about applying these models? Which disadvantages does it have in comparison to the many other methods that may be used in order to arrive at an estimate of costs?arrow_forwardThe board of directors of a corporation has decided that it is time to provide bonuses to the company's senior executives. Each year, the board of directors decides on incentive payments depending on the performance of the stock market. Managers will get bonuses in the form of stock that they may either retain or sell. The implications of such a bonus plan are unclear.arrow_forwardThe board of directors of a firm believes that top management should be rewarded for their efforts in furthering the company's goals. At the conclusion of each year, the board of directors determines whether or not to award bonuses based on share price increases. Bonuses will be paid out in the form of stock, which managers will be able to keep or sell. What are the repercussions of implementing such a bonus program?arrow_forward
- Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000 EV = $20,000 AC = $25,000 BAC = $120,000 What is the cost variance, schedule variance, cost performance index (CPI), and scheduleperformance index (SPI) for the project? How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Use the schedule performance index (SPI) to estimate how long it will take to finish this project. Sketch the earned value chart based for this project, using Figure 7-5 as a guide.arrow_forwardThe board of directors of a company decides that senior management has to be rewarded in order to achieve the company's objectives. The board of directors selects whether or not to award bonuses based on growth in share value at the end of each fiscal year. Bonuses will be given in shares, which the managers can keep or sell on the open market. What are the ramifications of implementing a bonus system like this?arrow_forwardInnis Investments manages funds for a number of companies and wealthy clients. The investment strategy is tailored to each client’s needs. For a new client, Innis has been authorized to invest up to $1.2 million in two investment funds: a stock fund and a money market fund. Each unit of the stock fund costs $50 and provides an annual rate of return of 10%; each unit of the money market fund costs $100 and provides an annual rate of return of 4%. The client wants to minimize risk subject to the requirement that the annual income from the investment be at least $60,000. According to Innis’ risk measurement system, each unit invested in the stock fund has a risk index of 8, and each unit invested in the money market fund has a risk index of 3; the higher risk index associated with the stock fund simply indicates that it is the riskier investment. Innis’s client also specified that at least $300,000 be invested in the money market fund. Let S = units purchased in the stock fund…arrow_forward
- A Cost Benefit Analysis, sometimes referred to as a CBA, is a technique for conducting an economic review that entails the computation of all of the positive and negative monetary implications that a certain programme may have. This approach is also frequently referred to as a Cost Benefit Analysis. Explain.arrow_forwardGiven the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000 EV = $20,000 AC = $25,000 BAC = $120,000 Use the schedule performance index (SPI) to estimate how long it will take to finish this project.arrow_forwardThe independent project estimates below have been developed by the engineering and finance managers. The corporate MARR is 8% per year, and the capital investment limit is PhP 4 million. Project Project Cost, PhP M Life, years NCF, PhP per year 1 -1.5 8 360,000 2 -3.0 10 600,000 3 -1.8 5 520,000 4 -2.0 4 820,000 Use Linear programming and a spreadsheet-based solution technique to select from the independent unequal-life projects. COMPLETE THE FOLLOWING: Objective Function: Maximize Z = Blank 1X1 + Blank 2X2 + Blank 3X3 +Blank 4x4 Constraint: Blank 5X1 + Blank 6X2 +Blank 7X3 +Blank 8X4 <= Blank 9 What is the Maximum Z ? ANSWER: Blank 10 How much is the total investment? ANSWER: Blank 11 Which project/s will be included in the investment? Blank 12 & Blank 13 (put zero on the other blank if only 1 project will be selected) NOTE: Do not use COMMAS and DECIMALS. UPLOAD YOUR SOLUTION BELOW.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning