Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN: 9781305970663
Author: Don R. Hansen, Maryanne M. Mowen
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 20, Problem 5CE
See Cornerstone Exercise 20.4. Fisher Company has three sequential processes: cutting, welding, and assembly. Assume that the optimal mix is Component A = 0 units per week; and Component B = 30 units per week. Demand is uniformly spread out over the five-day work week. Fisher requires a 2.5-day buffer.
Required:
- 1. Identify the drummer, the rate of production, the time buffer, and the rope.
- 2. Illustrate the DBR structure of Fisher Company.
- 3. What if the Welding Department was allowed or encouraged to produce at capacity? What effect will this have on work-in-process inventories?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
During the most recent month at Schwab Corporation, queue time was 10.6 days, inspection time was 1.7 day, process time was 2.7
days, wait time was 12.5 days, and move time was 3.5 day.
Required:
a. Compute the throughput time.
b. Compute the manufacturing cycle efficiency (MCE).
c. What percentage of the production time is spent in non-value-added activities?
d. Compute the delivery cycle time.
a. Throughput time
b. MCE
c. Percentage of non-value-added activities
d. Delivery cycle time
days
%
%
days
Calculate Lead Time
Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 64 units. The process time for each step is as follows:
Process Step 1
Process Step 2
Process Step 3
Process Step 4
7 minutes
5 minutes
4 minutes
9 minutes.
The time required to move each batch between steps is 12 minutes. In addition, the time to move raw materials to Process Step 1 is also 12 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 12
minutes.
The new lean layout will allow the company to reduce the batch sizes from 64 units to 4 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay
the same.
Value-added time
Non-value-added time
Total lead time
Value-added ratio (as a percent)
Determine the value-added, non-value-added, and total lead…
Mabbut Company has the following departmental manufacturing layout for one of its plants:
Required:1. Calculate the total time it takes to produce a batch of 10 units using the traditionaldepartmental manufacturing layout.2. Using cellular manufacturing, how much time is saved producing the same batch of10 units? Assuming the cell operates continuously, what is the production rate? Whichprocess controls this production rate?3. Assume the processing time of Welding is reduced to 6 minutes, while the times ofthe other processes stay the same. What is the production rate now, and how longwill it take to produce a batch of 10 units if the cell is in a continuous productionmode?
Chapter 20 Solutions
Cornerstones of Cost Management (Cornerstones Series)
Ch. 20 - What are ordering costs? What are setup costs?...Ch. 20 - Explain why, in the traditional view of inventory,...Ch. 20 - Discuss the traditional reasons for carrying...Ch. 20 - Prob. 4DQCh. 20 - Explain how safety stock is used to deal with...Ch. 20 - Prob. 6DQCh. 20 - What approach does JIT take to minimize total...Ch. 20 - One reason for inventory is to prevent shutdowns....Ch. 20 - Prob. 9DQCh. 20 - Explain how long-term contractual relationships...
Ch. 20 - What is a constraint? An internal constraint? An...Ch. 20 - Prob. 12DQCh. 20 - Prob. 13DQCh. 20 - Explain how lowering inventory produces better...Ch. 20 - Prob. 15DQCh. 20 - Thomas Corporation produces heating units. The...Ch. 20 - Sterling Corporation has an EOQ of 5,000 units....Ch. 20 - Patz Company produces two types of machine parts:...Ch. 20 - Prob. 4CECh. 20 - See Cornerstone Exercise 20.4. Fisher Company has...Ch. 20 - Ottis, Inc., uses 640,000 plastic housing units...Ch. 20 - Ottis, Inc., uses 640,000 plastic housing units...Ch. 20 - Melchar Company uses 78,125 pounds of oats each...Ch. 20 - Prob. 9ECh. 20 - Morrison Manufacturing produces casings for sewing...Ch. 20 - Morrison Manufacturing produces casings for sewing...Ch. 20 - Refer to Exercise 20.10. Assume the economic lot...Ch. 20 - Eyring Manufacturing produces a component used in...Ch. 20 - Hales Company produces a product that requires two...Ch. 20 - Many companies have viewed JIT as a panaceaa...Ch. 20 - Prob. 16ECh. 20 - Prob. 17ECh. 20 - Which of the following describes the economic...Ch. 20 - The economic order quantity (EOQ) for Part X15 is...Ch. 20 - A JIT inventory management system maintains which...Ch. 20 - For the theory of constraints, which of the...Ch. 20 - A dedicated pharmaceutical plant uses the theory...Ch. 20 - Prob. 23PCh. 20 - Burnett Company produces two types of gears: Model...Ch. 20 - Taylor Company produces two industrial cleansers...Ch. 20 - Prob. 26PCh. 20 - Calen Company manufactures and sells three...Ch. 20 - Confer Company produces two different metal...Ch. 20 - Pratt Company produces two replacement parts for a...Ch. 20 - Bountiful Manufacturing produces two types of bike...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Gumbrecht Company has the following departmental manufacturing layout for one of its plants: A consulting firm has recommended a value stream with the following manufacturing cell: Required: 1. Calculate the total time it takes to produce a batch of 20 units using the traditional departmental manufacturing layout. 2. Using cellular manufacturing, how much time is saved producing the same batch of 20 units? Assuming the cell operates continuously, what is the production rate? Which process controls this production rate? 3. Assume the processing time of Casting is reduced to 9 minutes, while the times of the other processes stay the same. What is the production rate now, and how long will it take to produce a batch of 20 units if the cell is in a continuous production mode?arrow_forwardHernandez Corp. wants to compute its throughput for August. The following production data are available: Good units produced and sold 2,923,200 Total units produced 4,844,000 Total processing (in hours) 201,600 Value-added time (in hours) 50,300 a. Determine the manufacturing cycle efficiency. ______% b. Determine the process productivity. ______ units per hour c. Determine the process quality yield. ______% d. Determine the throughput using only good units and total time. ______ units per hourarrow_forward(Chapter 4: Process Improvement) Consider a process consisting of three resources. Assume the demand rate is 8 units/hour. The process activities are always performed in the following sequence. Resource 1 has a processing time of 5 minutes per unit. Resource 2 has a processing time of 4 minutes per unit. Resource 3 has a processing time of 6 minutes per unit. Resource 1 is staffed by worker A and A's wage rate is $13 per hour. Resource 2 is staffed by worker B and B's wage rate is $13 per hour. Resource 3 is staffed by worker C and C's wage rate is $20 per hour. If one additional worker could be hired, to which resource should this worker be assigned? Calculate the new process capacity in units/hr. O Assign the new worker to Resource 3. The process capacity is 12 units per hour. O Assign the new worker to Resource 3. The process capacity is 10 units per hour. O Assign the new worker to Resource 1. The process capacity is 20 units per hour. O Assign the new worker to Resource 2. The…arrow_forward
- Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Step Time (in minutes) Process Step 1 5 Process Step 2 8 Process Step 3 4 Process Step 4 3 The time required to move each batch between steps is 4 minutes. In addition, the time to move raw materials to Process Step 1 is also 4 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 6 minutes. The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the: present and proposed production…arrow_forwardWilliams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 5 minutes Process Step 2 8 minutes Process Step 3 4 minutes Process Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step 1 is also 5 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 5 minutes. The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the present and proposed production approaches. If required,…arrow_forwardIsaacson Dental Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 50 units. The process time for each step is as follows: Process Step 1 Process Step 2 Process Step 3 Process Step 4 6 minutes 12 minutes 9 minutes 3 minutes The time required to move each batch between steps is 6 minutes. In addition, the time to move raw materials to Process Step 1 is also 6 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 6 minutes. The new lean layout will allow the company to reduce the batch sizes from 50 units to 2 units. The time required to move each batch between steps and the inventory locations will be reduced to 1 minute. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the (a) present and (b) proposed production approaches. If required, round…arrow_forward
- Williams Optical Inc. is considering a new lean product cell. The present manufacturing approachproduces a product in four separate steps. The production batch sizes are 45 units. The processtime for each step is as follows: Process Step 1 5 minutesProcess Step 2 8 minutesProcess Step 3 4 minutesProcess Step 4 3 minutes The time required to move each batch between steps is 5 minutes. In addition, the time tomove raw materials to Process Step 1 is also 5 minutes, and the time to move completed unitsfrom Process Step 4 to finished goods inventory is 5 minutes.The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units.The time required to move each batch between steps and the inventory locations will be reducedto 2 minutes. The processing time in each step will stay the same.Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the (a) present and (b) proposed production approaches. Round percentages to one…arrow_forwardWilliams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows:Step Time (in minutes)Process Step 1 5Process Step 2 8Process Step 3 4Process Step 4 3The time required to move each batch between steps is 4 minutes. In addition, the time to move raw materials to Process Step 1 is also 4 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 6 minutes. The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the:a. present and b. proposed production approaches. (Round percentages to one decimal…arrow_forwardCompute Lead Time Williams Optical Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 45 units. The process time for each step is as follows: Process Step 1 Process Step 2 Process Step 3 Process Step 4 5 minutes 8 minutes 4 minutes The time required to move each batch between steps is 5 minutes. In addition, the time to move raw materials to Process Step 1 is also 5 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 5 minutes. Value-added time 3 minutes The new lean layout will allow the company to reduce the batch sizes from 45 units to 3 units. The time required to move each batch between steps and the inventory locations will be reduced to 2 minutes. The processing time in each step will stay the same. Non-value-added time Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the present and…arrow_forward
- Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 5 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 6 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Traditional Philosophy Lean Manufacturing Philosophy Value-added time ? min ? min Non-value-added time ? min ? min Total lead time ? min ? min Value-added ratio…arrow_forwardBienestar Inc., has the following departmental structure for producing a well-known multivitamin: A consultant designed the following cellular manufacturing structure for the same product: The times above the processes represent the time required to process one unit of product. Required: 1. Calculate the time required to produce a batch of 15 bottles using a batch-processing departmental structure. 2. Calculate the time to process 15 units using cellular manufacturing. 3. How much manufacturing time will the cellular manufacturing structure save for a batch of 15 units?arrow_forwardAnderson Company has the following departmental manufacturing structure for one of its products: After some study, the production manager of Anderson recommended the following revised cellular manufacturing approach: Required: 1. Calculate the total time it takes to produce a batch of 20 units using Andersons traditional departmental structure. 2. Using cellular manufacturing, how much time is saved producing the same batch of 20 units? Assuming the cell operates continuously, what is the production rate? Which process controls this production rate? 3. What if the processing times of molding, welding, and assembly are all reduced to six minutes each? What is the production rate now, and how long will it take to produce a batch of 20 units?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Cost Accounting - Definition, Purpose, Types, How it Works?; Author: WallStreetMojo;https://www.youtube.com/watch?v=AwrwUf8vYEY;License: Standard YouTube License, CC-BY