OM6     ONLINE-LMS INTEGRATED ACCESS
OM6 ONLINE-LMS INTEGRATED ACCESS
6th Edition
ISBN: 9781337118323
Author: Collier
Publisher: CENGAGE L
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 18, Problem 14PA

(a)

Summary Introduction

Interpretation: The probability that the project is completed within 33weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(a)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 33weeks deadline.

  z=33321.69=11.3=0.769

Refer probability distribution table.

For z0.769 .

  P(z0.769)=0.77935 .

Hence, the probability that the project is completed within 33weeks is 0.77935 .

(b)

Summary Introduction

Interpretation: The probability that the project is completed within 30weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(b)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 30weeks deadline.

  z=30321.69=21.3=1.539

Refer probability distribution table.

For z1.539 .

  P(z1.539)=0.06178 .

Hence, the probability that the project is completed within 30weeks is 0.06178 .

(c)

Summary Introduction

Interpretation: The probability that the project is completed within 35weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(c)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 35weeks deadline.

  z=35321.69=31.3=2.308

Refer probability distribution table.

For z2.308 .

  P(z2.308)=0.99134 .

Hence, the probability that the project is completed within 35weeks is 0.99134 .

(d)

Summary Introduction

Interpretation: The probability that the project is completed within 32weeks is to be determined.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

(d)

Expert Solution
Check Mark

Explanation of Solution

The activity with optimistic, most probable and pessimistic time is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic Time
    A456
    B2.533.5
    C678
    D55.59
    E678
    F135
    G81012

Table (1)

The expression for the estimated time is given by,

  te=t0+4tm+tp6

Here, te is the estimated time of an activity, t0 is the optimistic time, tm is the most probable time and tp is the pessimistic time.

The expression for variance is given by,

  Variance=(tpt0)236

The variance and estimated time of each activity is tabulated below.

    ActivityOptimistic timeMost Probable TimePessimistic TimeEstimated TimeVariance
    A45650.111
    B2.533.530.028
    C67870.111
    D55.5960.444
    E67870.111
    F13530.444
    G81012100.444

Table (2)

Calculate z value to find the probability of meeting a 32weeks deadline.

  z=32321.69=01.3=0

Refer probability distribution table.

There is no value for z=0 .

Hence, the probability that the project is completed within 32weeks cannot be determined.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
8 EARNED VALUE ANALYSIS The following project is reported to be at the end of its 8 week. Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Find the condition of the project at the this reporting period. PV AC Budget ($) Duration Actual Cost % D-8 Activity Predecessor (s) (week) ($) Complete 300 400 A 3 100 A3 В 4 200 180 100 B:4 C 7 250 300 90 A 8 600 400 50 400 200 В 40 150 180 F В 4 100 G C 4 100 200 40 500 H D, E 2 300 F, G 3 J H, I 1 100 ㅇ CO 프 (-)
Project B is the development of a facility in a remote area, of about GHS 5 million in value, of approximately 18 months’ planned duration. It is 30 per cent completed. Earned Value analysis shows that the project is not achieving its planned cost or progress targets. The project is also not achieving quality requirements. Some of the specialized components used for this project are only obtainable from overseas suppliers and are difficult to transport over the rough terrain near the project site. There has been a delay on ordering these components. The transportation of these components, which must be booked several months ahead, has not been arranged, and there is also difficulty with obtaining tradespeople with the requisite set of skills to install them. There are also several other risks associated with this project, including a quite basic business case, rudimentary project charter, poor definition of expected project outcomes, exchange rate risks and the potential for…
The following project has a critical path of ACD with an expected duration of 10 weeks and a standard deviation of 2 weeks. Given the cost data below. What is the P95 estimate of the cost of the project, Мean Stdh. Dev. Activity Predecessors Cost ($K) Cost ($K) none A 4 1.5 A 7. 2.75 B,C 2 0.5 O 19.6 O 8.4 22.8 O 24.2 O 14.6
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY