Intermediate Accounting: Reporting and Analysis
2nd Edition
ISBN: 9781285453828
Author: James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 17, Problem 9MC
To determine
Compute the amount contract costs incurred during the year ended December 31, 2018.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
In 20x1, ABC Co. enters into a contract to construct a building
for a customer. ABC identifies its performance obligation to be
satisfied over time. ABC measures its progress on the
contract based on costs incurred. The contract price is
P20,000,000. ABC has an unconditional right to all billings
made in accordance with the billing schedule stated in the
contract. Information on the construction is as follows:
20x1
20x2
20x3
Contract costs incurred
per year
Billings per year
Collections on billings
per year
Estimated costs to
8,160,000 7,320,000
1,920,000
10,000,000 7,000,000 3,000,000
9,500,000 6,650,000 3,850,000
complete (at each
year-end)
8,840,000 1,720,000
How much profit is recognized on the contract in 20x3?
In 20x1, ABC Co. enters into a contract to construct a building
for a customer. ABC identifies its performance obligation to be
satisfied over time. ABC measures its progress on the
contract based on costs incurred. The contract price is
P20,000,000. ABC has an unconditional right to all billings
made in accordance with the billing schedule stated in the
contract. Information on the construction is as follows:
20x1
20x2
20x3
Contract costs incurred
per year
Billings per year
Collections on billings
per year
1,920,000
3,000,000
5,650,000 3,850,000
8,160,000 7,320,000
10,000,000
500,000 6600,000
Estimated costs to
complete (at each
year-end) from the Student Ha8,840,000 1,720,000
ons, quizzes
rection
with any academic work, abetting of the same: 1st violation
How much profit is recognized on the contract in 20x3?
In 20x1, ABC Co. enters into a contract to construct a building
for a customer. ABC identifies its performance obligation to be
satisfied over time. ABC measures its progress on the
contract based on costs incurred. The contract price is
P20,000,000. ABC has an unconditional right to all billings
made in accordance with the billing schedule stated in the
contract. Information on the construction is as follows:
20x1
20x2
Contract costs incurred
per year
Billings per year
Collections on billings
20x3
8,160,000 7,320,000
1,920,000
10,000,000 7,000,000 3,000,000
9,500,000 6,650,000 3,850,000
per year
Estimated costs to
1911
complete (at each
year-end)er from the Student Ha8,840,000 of 1,720,000
"Cheating during examinations, quizzes or plagiarism in connection
with any academic work, abetting of the same: 1st violation-
How much profit is recognized on the contract in 20x3?
suspension with invalidation of grade; 3rd violation- suspension
Chapter 17 Solutions
Intermediate Accounting: Reporting and Analysis
Ch. 17 - Prob. 1GICh. 17 - Prob. 2GICh. 17 - When a company recognizes revenue during a period,...Ch. 17 - Prob. 4GICh. 17 - Prob. 5GICh. 17 - What is the proper accounting for a wholly...Ch. 17 - If a seller enters into more than one contract...Ch. 17 - Prob. 8GICh. 17 - Prob. 9GICh. 17 - Prob. 10GI
Ch. 17 - Prob. 11GICh. 17 - Prob. 12GICh. 17 - Prob. 13GICh. 17 - Prob. 14GICh. 17 - Prob. 15GICh. 17 - Prob. 16GICh. 17 - If the standalone selling price of a good or...Ch. 17 - Prob. 18GICh. 17 - Prob. 19GICh. 17 - If the sellers performance creates on asset (e.g.,...Ch. 17 - Describe input and output methods used to measure...Ch. 17 - Prob. 22GICh. 17 - Prob. 23GICh. 17 - Prob. 24GICh. 17 - Prob. 25GICh. 17 - A company should recognize revenue when a. the...Ch. 17 - A contract between one or more parties creates: a....Ch. 17 - Morgan Company and its customer agree to modify...Ch. 17 - Chlorine Corp. has a contract to deliver pool...Ch. 17 - Prob. 5MCCh. 17 - Prob. 6MCCh. 17 - In accounting for a long-term construction...Ch. 17 - Prob. 8MCCh. 17 - Prob. 9MCCh. 17 - Prob. 10MCCh. 17 - CustomTee Inc. contracts with various customers to...Ch. 17 - Yankee Corp. agrees to provide Albany Company 24...Ch. 17 - Prob. 3RECh. 17 - Prob. 4RECh. 17 - Prob. 5RECh. 17 - Prob. 6RECh. 17 - VolleyElite runs a volleyball program consisting...Ch. 17 - Enterprise Solutions Inc. licenses its...Ch. 17 - Prob. 9RECh. 17 - Magical Memories sells Florida theme park vacation...Ch. 17 - Prob. 11RECh. 17 - Robotics Inc. contracts with a customer to build a...Ch. 17 - CoolShoes sells its elite tennis shoes to sports...Ch. 17 - Using the information in RE17-13, what journal...Ch. 17 - GameDay sells recreational vehicles along with...Ch. 17 - Prob. 16RECh. 17 - Using the information provided in RE17-16, prepare...Ch. 17 - Prob. 18RECh. 17 - Prob. 19RECh. 17 - Prob. 1ECh. 17 - Prob. 2ECh. 17 - Prob. 3ECh. 17 - Prob. 4ECh. 17 - Prob. 5ECh. 17 - Assume the same facts as in E17-5. On July 1,...Ch. 17 - Prob. 7ECh. 17 - Prob. 8ECh. 17 - Prob. 9ECh. 17 - Prob. 10ECh. 17 - Prob. 11ECh. 17 - Jonas Consulting enters into a contract to provide...Ch. 17 - Prob. 13ECh. 17 - Prob. 14ECh. 17 - Prob. 15ECh. 17 - Prob. 16ECh. 17 - Prob. 17ECh. 17 - Prob. 18ECh. 17 - Prob. 19ECh. 17 - Prob. 20ECh. 17 - Crazy Computer Store sells a back-to-school bundle...Ch. 17 - Each of the following is an independent situation...Ch. 17 - Prob. 23ECh. 17 - Prob. 24ECh. 17 - Prob. 25ECh. 17 - Prob. 26ECh. 17 - Prob. 1PCh. 17 - Prob. 2PCh. 17 - Prob. 3PCh. 17 - Prob. 4PCh. 17 - Prob. 5PCh. 17 - Prob. 6PCh. 17 - Prob. 7PCh. 17 - SoccerHawk Merchandise Inc. enters into a 6-month...Ch. 17 - Prob. 9PCh. 17 - Prob. 10PCh. 17 - Prob. 11PCh. 17 - Prior to ASU 2014-09 changing the principles...Ch. 17 - The first step in the revenue recognition process...Ch. 17 - Prob. 3CCh. 17 - One of the more difficult issues that companies...Ch. 17 - Prob. 5CCh. 17 - Prob. 6CCh. 17 - Prob. 7CCh. 17 - Prob. 8CCh. 17 - Revenue for a company is recognized for accounting...Ch. 17 - Prob. 10C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Celestial Holdings Co. began constructing a condominium in January 1, 2017 for a contract price of P1,250,000. The entity has assured collection of its contract and the costs can be reliably estimated. For the year ended December 31, 2018, Celestial billed its client an additional 60% of the contract price. Data relating to the construction are as follows: 2017 2018 2019 Construction in progress 300,000 ? ? Estimated cost to complete ? ? - Cost incurred 250,00 600,000 112,500 Excess of CIP over PB 25,000 (125,000) How much is the Gross Profit/Loss Realized in 2018? Show your good accounting form. Thank you!arrow_forwardGeorge Co. enters into a contract to build an apartment for Jungle Co. For a fixed fee of P20,000,000. At contract inception, George Co. assesses its performance obligations in the contract and concludes that it has a single performance obligation that is satisfied over time. George Co. determines that the measure of progress that best depicts its performance in the contract is input method based on costs incurred. George estimates that the total contract costs would amount to P16,000.000 over the construction period. George incurs contract costs of P2,000,000 during the year. How much revenue is recognized for the year?arrow_forwardOn July 1, 2017, Dinar obtained a contract to construct a building. The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion on October 2019. The contract contains a penalty clause to the effect that the other party was to deduct P35,000 from the contract price for each week of delay. On the other hand, if the contractor was able to finish the building earlier than agreed, it will be rewarded an amount equal to P50,000 for every month of early completion. Furthermore, cost escalation clause was included in the contract. In 2018, the estimated costs of particular construction material amounting to P520,000 were bought for P780,000. The increase in the contract price related to this cost escalation was approved by the client. Completion was delayed for 4 weeks. The records show: 2017 2018 2019 Costs incurred P1,750,000 6,440,000 1,085,000 Estimated cost to complete 7,000,000 1,810,000 -- Progress billings…arrow_forward
- On January 1, 2020, Gordon Co. enters into a contract to sell a customer a wiring base and shelving unit that sits on the base in exchange for $3,000. The contract requires delivery of the base first but states that payment for the base will not be made until the shelving unit is delivered. Gordon identifies two performance obligations and allocates $1,200 of the transaction price to the wiring base and the remainder to the shelving unit. The cost of the wiring base is $700; the shelves have a cost of $320. Instructions a. Prepare the journal entry on January 1, 2020, for Gordon. b. Prepare the journal entry on February 5, 2020, for Gordon when the wiring base is delivered to the customer. c. Prepare the journal entry on February 25, 2020, for Gordon when the shelving unit is delivered to the customer and Gordon receives full payment.arrow_forwardOn July 1, 20x1, Zevrek Co. enters into contract with a customer for the construction of a building. The contract price is P6M. However, Zevrek Co. is entitled to a bonus of P500,000 if the building is completed within 3 years. Zevrek Co. uses the cost-to-cost method in measuring its progress on the contract. At contract inception, Zevrek Co. estimates total contract costs of P4M. In 20x1, Zevrek Co. incurs total costs of P1,350,000. Due to bad weather conditions, Zevrek Co. does not expect that it can finish the building on time for it to be entitled to the bonus. The estimated costs to complete as of the end of 20x1 are P2.4M. In 20x2, Zevrek Co. incurs total costs of P2,260,000. Due to improvements in weather conditions, Zevrek Co. now believes that it is highly probable that the building will be finished on time and the bonus will be received. The estimated costs to complete as of the end of 20x2 are P190,000. Requirement: Compute for the revenues, costs of construction and…arrow_forwardABC Co. began constructing a condominium on January 1, 2017 for a contract price of P1,250,000. The entity has assured collection of its contract and the costs can be reliably estimated. For the year ended December 31, 2018, ABC Co billed its client an additional 60% of the contract price. Data relating to the construction are as follows: 2017 2018 2019 Construction Progress 300,000 ? ? Estimated Cost to Complete ? ? - Costs Incurred 250,000 600,000 112,500 Excess of CIP over PB 25,000 (125,000) HOW MUCH IS THE GROSS PROFIT/LOSS REALIZED IN 2018? Kindly show your solution in a good accounting form. Thank you!arrow_forward
- J Contractors entered into a contract on October 2017 to build a warehouse for Francis Corporation. The total contract price amounting to P10,000,000 was received by Il upon completion on June 30, 2018. Materials purchased during construction valued at P4,000,000 were paid on June 1, 2018 while a construction equipment worth P3,000,000 (net of VAT) was purchased on January 1, 2018 with the following terms; down payment - 500,000, balance payable every January 1 until fully paid starting 2019. The equipment was estimated to last for 6 years. How much is the VAT payable of JJ for June 30, 2018? P360,000 P690,000 P684,000 P0arrow_forwardCurtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,to construct a four-story office building. At that time, Curtiss estimated that it would take between two and threeyears to complete the project. The total contract price for construction of the building is $4,000,000. Curtissconcludes that the contract does not qualify for revenue recognition over time. The building was completed onDecember 31, 2020. Estimated percentage of completion, accumulated contract costs incurred, estimated costs tocomplete the contract, and accumulated billings to Axelrod under the contract were as follows:At 12-31-2018 At 12-31-2019 At 12-31-2020Percentage of completion 10% 60% 100%Costs incurred to date $ 350,000 $2,500,000 $4,250,000Estimated costs to complete 3,150,000 1,700,000 –0–Billings to Axelrod, to date 720,000 2,170,000 3,600,000Required:1. For each of the three years, prepare a schedule to compute total gross profit or loss to be…arrow_forwardJJ Contractors entered into a contract on October 2017 to build a warehouse for Francis Corporation. The total contract price amounting to P10,000,000 was received by JJ upon completion on June 30, 2018. Materials purchased during construction valued at P4,000,000 were paid on June 1, 2018 while a construction equipment worth P3,000,000 (net of VAT) was purchased on January 1, 2018 with the following terms; down payment - 500,000, balance payable every January 1 until fully paid starting 2019. The equipment was estimated to last for 6 years.How much is the VAT payable of JJ for June 30, 2018?a. P360,000b. P690,000c. P684,000d. P0arrow_forward
- Zentric Garage Inc. enters into a contract to provide services totaling $78,000. The contract includes a potential performance bonus based on when Zentric Garage completes the services. Zentric Garage estimates the following scenarios for completion. (Click the icon to view the scenarios.) Determine the bonus using the most-likely-amount approach. Determine the bonus using the most-likely-amount approach under scenario 1. The bonus for this contract using the most-likely-amount approach under scenario 1 is $ Determine the bonus using the most-likely-amount approach under scenario 2. The bonus for this contract using the most-likely-amount approach under scenario 2 is $ Determine the bonus using the most-likely-amount approach under scenario 3. The bonus for this contract using the most-likely-amount approach under scenario 3 is $ Ente Scenarios Complete within 3 days 5 days 8 days Probability Bonus Scenario 1 Scenario 2 80% 47% 15% 38% 5% 15% $ 13,000 $ 8,000 $ 3,500 Print Done…arrow_forwardIn 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000. The road was completed in 2018. Information related to the contract is as follows: 1. Calculate the amount of gross profit to be recognized in each of the three years under percentage-of-completion method of accounting for long-term construction contracts. 2. Calculate the amount of gross profit to be recognized in each of the three years under completed contract method of accounting for long-term construction contracts.arrow_forwardOn July 1, 2020, Oriole Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Oriole estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020, 2021, and 2022. At12/31/20 At12/31/21 At12/31/22 Contract costs incurred to date $288,800 $1,227,600 $2,078,500 Estimated costs to complete the contract 1,231,200 752,400 –0– Billings to Gumbel 290,000 1,090,000 1,820,000 (a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2020, 2021, and 2022. (Ignore income taxes.) (If answer is 0, please enter 0. Do not leave any field blank.…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning