Question
Chapter 17, Problem 9E
a)
To determine
To describe: The various departments’ desires to use different discount rates.
b)
To determine
To calculate: The projects by using the rate
c)
To determine
To describe: The more appropriate discount rate
d)
To determine
To describe: The best choice between the projects and the tax-refund alternative
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
The state of Glottamora has $300 million remaining in its budget for the current year. One alternative is to give Glottamorans a one-time tax rebate. Alternatively, two proposals have been made for state expenditures of these funds. The first proposed project is to invest in a new power plant, costing $300 million and having an expected useful life of 20 years. Projected benefits of the new power plant are as follows:
Years
Benefits per Year
($ Millions)
1 - 5
0
6 - 20
60
The second alternative is to undertake a job retraining program, also costing $100 million and generating the following benefits:
Years
Benefits per Year
($ Millions)
1 - 5
60
6 - 10
42
11 - 20
12
The state Power Department argues that a 5 percent discount factor should be used in evaluating the projects because that is the government’s borrowing rate. The Human Resources Department suggests using a 12 percent rate because that more nearly equals society’s true…
Sacramento is considering building a temporary bridge to cut travel time during the three years it will take to build the new permanent “I” Street bridge to West Sacramento. The temporary bridge would be constructed over two years at a cost of $300,000 each year. At the beginning of the fourth year following three years of useful life it would be removed at a cost of $80,000. City cost-benefit analysts predict that the benefits in real dollars would be $200,000 during the first year, $300,000 during the second year, and $400,000 during the third year. Set up the NPV equation for the CBA.
Juba city council is considering to construct a sewage management system, the construction of this system will take 3 years before commissioning. the initial capital outlay is estimated to be $10m after commissioning, the juba city council will incur an annual operation and maintenance cost in the amount of $500,000. the sewage management system will generate an annual benefit of $ 2.5m.
the sewage management system will have useful life of 27 years. the city council use 5% discount rate to appraise public project.
Required.
1- compute the present value of the cost and benefits?
2-perform cost benefit analysis to determine whether the project should be undertaken by the City council?
3-Assume you are consulted on this project, advice the city council on how to governed the project.
4- In addition to monetary conditions, what are the other factors to be considered in deciding whether or not the project would be taken?
Chapter 17 Solutions
Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
Knowledge Booster
Similar questions
- The city of Oakmont is interested in developing some lake front property into a sports park (picnic facilities, boat docks, swimming area, etc.). A consultant has estimated that the city would need to invest $3 million in this project. In return, the developed property would return $500,000 per year to the city through increased tax revenues and recreational benefits to the public. What would the life of this project need to be in order to be cost-beneficial to the city? The interest rate on municipal bonds is 4% per year. E Click the icon to view the interest and annuity table for discrete compounding when i= 4% per year. The life of the project needs to be at least years in order to be cost-beneficial to the city. (Round up to the nearest whole number.)arrow_forwardThe government is considering undertaking one of the four projects A1, A2, A3, and A4. These projects are mutually exclusive, and the estimated present values of their costs and of their benefits are shown in millions of dollars as follows: All of the projects have the same duration. Assuming that there is no donothing alternative, which alternative would you select? Justify your choice by using a benefit-cost ratio on incremental investment (BC(i)).arrow_forwardThe government is considering undertaking four projects. These projects are mutually exclusive, and the estimated present worth of their costs and the present worth of their benefits are shown in millions of dollars in the table below. All of the projects have the same duration. Assuming no do-nothing alternative, which alternative would you select? Justify your choice by using a benefit-cost (BC()) analysis on incremental investment. Click the icon to view the data for the four projects. Which project(s) should be excluded from subsequent consideration? Select all that apply. A. None of the projects B. Project A2 C. Project A1 D. Project A3 E. Project A4 Fill in the table below. (Round to two decimal places.) Project A1 A2 A3 A4 www Incremental Investment A4 - A3 A2 - A4 BC(1) 47 1.36 2.8 1.64 BC(1) K-jarrow_forward
- Consider the following cash flow and calculate the NPV of the project with a discount rate of 10%. $1,00,000 a) -$17,200.85 b) -$12,500.20 c) -$21,985.70 d) -$14,428.00 $20,000 1 $20,000 2 $20,000 $20,000 3 $20,000 5arrow_forwardThe city of Calgary has a new subdivision, Paradise Mountain, at its outskirts. The city wants to encourage the growth of Paradise Mountain by improving transportation between Paradise Mountain and the centre of Calgary. Two alternatives are being considered: (1) new buses on the route between Paradise Mountain and Calgary and (2) improvement of the road between Paradise Mountain and Calgary. Both projects will have as their main benefit improved transportation between Paradise Mountain and Calgary. Rather than measuring the value of this benefit directly to the city, engineers have estimated the benefit in terms of an increase in the value of land in Paradise Mountain. That is, potential residents are expected to show their evaluations of the present worth of improved access to the town centre by their willingness to pay more for homes in Paradise Mountain. The road improvement will entail construction cost and increased operating and maintenance costs. In addition, the improved road…arrow_forwardThe city of Oakmont is interested in developing some lake front property into a sports park (picnic facilities, boat docks, swimming area, etc.). A consultant has estimated that the city would need to invest $3 million in this project. In return, the developed property would return $500,000 per year to the city through increased tax revenues and recreational benefits to the public. Whatwould the life of this project need to be in order to be cost-beneficial to the city? The interest rate on municipal bonds is 6% per year.arrow_forward
- You have been asked to evaluate whether a project to preserve an area of forest should go ahead or whether the land should be converted to agriculture. The net benefits of ecosystem goods and services have been valued over the next four years at R6000, R10 000, R14 000 and R22 000 respectively. The immediate cost of preserving the forest is R23 500. Assume that MWTP = 90 - 3Q and MC = 10 + 2Q. The discount rate is 7%.arrow_forwardThe construction of a bypass road needs a capital investment of $200,000 and $10,000 would be required each year for maintenance. The annual benefits to the project have been estimated to be $60,000. The study period(estimated life) of the project is 10 years. The MARR is set at 12%. a. What is the discounted payback period(in years)? b. Detemine whether this is a good investment using Modified Benefit-Cost Ratio method with Present Worth(PW). c. Using Conventional Benefit-Cost Ratio method with PW but the MARR is set at 12%, is this project acceptable?arrow_forwardTower City aims to construct a new bypass between two main routes that will reduce commuter travel time. The route will cost $15 million and will save 17,500 people $100 per year in petrol costs. The path will be paved. Every year, at a cost of $7,500, the surface must be refinished. The road will be in use for the next 20 years. Determine if Tower City should construct the road. Money has an interest rate of 8%(ɛ = interest rate) . Note: Show final answer in two decimal places and show complete solution with cash flow a. The Net Present Worth of this project = $ Blank 1 b. The IRR of this project = Blank 2% c. The ERR of this project = Blank 3% %3D d. Should the city build the bypass road? (type only Yes or No) = Blank 4 %3Darrow_forward
- Kipling Equipment Inc. must decide to produce either a face mask or a face shield to alleviate the spread of a quickly evolving coronavirus. The face mask is disposable and developing it could potentially lead to a profit of $230,000 if competition is high or a profit of $515,000 if competition is low. The face shield, on the other hand, is reusable and has the potential of generating a fixed profit of $438,000 irrespective of high or low competition. The probability of high competition is 43% while that of low competition is 57%. Part A a) What is the expected monetary value of the optimal decision? $ b) Based on expected monetary value, what should the Kipling do? Select an answer c) What is the upper bound on the amount Kipling should pay for additional information? $arrow_forwardThe government of a subtropical country is evaluating the costs and benefits of protecting a rainforest versus cutting it down for timber. The estimated value of the wood is $270$270 million. If the same forest is used as a national park, it may attract 0.030.03 million additional tourists per year. Statistically, each tourist spends $1,600$1,600 inside the country during their stay.How long will it take tourism to exceed the estimated value of the wood in the rainforest? Enter your answer in the box below and round to two decimal places if necessary.arrow_forwardA bridge is to be constructed now as part of a new road. Engineers have determined that current traffic volume on the new road will justify a two-lane road and a bridge at the present time. Because of the uncertainty regarding future traffic, the time at which the additional two lanes will be required is currently being studied. Two alternatives are being considered. Alternative 1 - One-stage construction: Build a four lane bridge right now for $360,000. Alternative 2 - Two-stage construction: Start with a two-lane bridge now for $170,000 and widen to four lanes later when traffic justifies. The future cost of widening the bridge to four-lanes at that time will be $170,000 plus an extra $23,000 for every year that widening is delayed. For example, if future widening is done at the end of year 7, the cost of widening at that time will be equal to $170,000 + 7x($23,000) = $331,000. The following estimates have been made of when widening to a four-lane bridge will be required: Pessimistic…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Economics: Applications, Strategies an...EconomicsISBN:9781305506381Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. HarrisPublisher:Cengage Learning
Managerial Economics: Applications, Strategies an...
Economics
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:Cengage Learning