Question
Chapter 17, Problem 1CQ
Summary Introduction
To determine: Every flow units are served, when capacity exceeds demand. Whether the statement is true or false?
Expert Solution & Answer
Answer to Problem 1CQ
B. False
Explanation of Solution
It is not true that every flow units are served when capacity exceeds demand. In some circumstances, few demands may be lost when capacity is more than the demand.
Want to see more full solutions like this?
Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
11. Leo manages a receiving station for rice. Farmers deliver their loads of rice from 7 am to 7 pm. Leo can process them at a rate of 4.5 tons an hour, and on a heavy day, a total of 96 tons can be expected. The station has room to hold only 15 tons of rice in inventory prior to processing. Once this space is filled, the farmers’ trucks must wait to dump their contents. What is the throughput (flow) rate after 7 pm (in tons/hr)?
[Queuing Theory - Operation Research]
RBMC Industry manufactures a special printing according to customer specifications with respect to the number of sheets the machine can produce per hour. With this, there is a $50 increase in the production rate x. A shop owner is considering buying one of these machines. From his past experiences, the owner estimates that the arrival rate is three per hour and each order averages 500 sheets. Contracts signed by the owner, and the customer says that there will be a penalty of 10$ per late order per hour. It is assumed that the actual production time is exponential.
(a) Formulate the cost model as a function of the production rate x.
(b) Determine the optimal production rate the owner should specify in his purchase of the machine from RBMC. Hint: Get the derivative of the cost function.
Why does a (M/M/2):(GD/5/infinity) queuing system have a steady state regardless of the values of A > 0 and u >
0?
O No further calling unit can enter the system when there are 5 in it.
O A and u are both positive
O The queue is not a Poisson queue.
none of the above
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- 1. Which of the following statements will hold good in the case of a system with uncertainty in demand for service and in service times? a) When the utilization of resources fall it is an indication of greater efficiency of the service b) It is a good practice to plan for resource utilization levels more than 85% c) Cost of waiting to get serviced is directly proportional to the cost of providing the service d) None of the abovearrow_forwardPlease do not give solution in image format thanku A takeaway café has an average rate of customer arrival of 6 per hour. The café uses two service counters and both counters take 6 minutes to serve each customer. Assuming Poisson arrivals and exponential service, what is the average number of customers waiting in a queue? a. 1.000 b. 0.059 c. 0.600 d. 0.333 e. None of the other answers is correct Feedbackarrow_forwardA graphics reproduction i rm has four units of equipment that are automatic but occasionallybecome inoperative because of the need for supplies, maintenance, or repair. Eachunit requires service roughly twice each hour, or, more precisely, each unit of equipmentruns an average of 30 minutes before needing service. Service times vary widely, rangingfrom a simple service (such as pressing a restart switch or repositioning paper) to moreinvolved equipment disassembly. The average service time, however, is i ve minutes.Equipment downtime results in a loss of $20 per hour. The one equipment attendant ispaid $6 per hour.Using i nite queuing analysis, answer the following questions:a. What is the average number of units in line?b. What is the average number of units still in operation?c. What is the average number of units being serviced?d. The i rm is considering adding another attendant at the same $6 rate. Should the i rmdo it?arrow_forward
- 2. A repair and inspection facility consists of two stations: a repair station with two technicians, and an inspector station with 1 inspector. Each repair technician works at the rate of 3 items per hour; the inspector can inspect 8 items per hour. Approximately 10% of all items fail inspection and are sent back to the repair station. (This percentage holds even for items that have been repaired two or more times.) If items arrive at the rate of 5 per hour, what is the long-run expected delay that items experience at each of the two stations, assuming a Poisson arrival process and exponentially distributed service times? What is the maximum arrival rate that the system can handle without adding personnel?arrow_forwardA heat tempering machine tempers a surgical instrument in exactly 2 minutes. Surgical instruments arrive at the rate of 20 units per hour. The machine has a capacity to temper only 1 instrument at a time and there is not setup required between two tempering processes. Find the average number of surgical waiting to be tempered including the one that is going under treatment process. (A)0.33 (B) 1.33 (C) 2.33 (D) 3.33arrow_forward* 08 HI FL R %S4 LLI %#3 50 For the first two hours of the day, the arrival rate at the donut shop is 10 customers per hour. The donut shop is capable of serving 8 customers per hour. Assume that the system is empty at the start and that no customer who arrives leaves without being served. (Round your answer to 2 decimal places.) What is the average wait time for customers during this time period (in hours)? unoy nces Mc Graw Wellington Paranormal Stars and Pahkitew Island RESTAURANT Restaurant: Scissor Seven My 600-lb Life The Afterparty Pam & Tommy As We See It 8,425 MAR étv A 644 DD F7 F12 F8 F10 F3 F 4 F5 93 %23 5 delet 9 7. 2. } P. 1 B. W N alt 38 command MOSISO commandarrow_forward
- c) i. If an M/M/1 queue has utilization of 90%, what do you think will be the average queue length and the average response time? If the arrival rate is 100 jobs per secondii. If an M/D/1 queue has utilization of 80% do you expect its mean queue length and response time to be less, same, or greater than that of an M/M/1? Explain your answer.arrow_forwardA Printed Circuit Board (PCB) machine installs integrated circuits onto a board. Before starting to produce a board, the PCB machine requires a 16-minute setup. Once in production, the PCB machine requires only 0.19 minute per board. a. Currently, the PCB machine produces 525 boards between setups. Given this operating process, what is the capacity of the PCB machine (in boards per min)? b. Currently, the PCB machine produces 525 boards between setups. Given this operating process, what is the utilization of the PCB machine? c. Say the PCB machine produces 400 boards s between setups and demand is 2 boards per minute. Given the operating process, what is the avergae inventory of boards anf the PCB machine? d. Demand for boards occurs at the rate of 2 boards per minute. What is the smallest batch size such that the PCB machine does not constrain the flow rate through the process?arrow_forwardPrince Shop. owns and operates a chain of popular coffee stands that serve over 30 different coffee-based beverages. The constraint at the coffee stands is the amount of time required to fill an order, which can be considerable for the more complex beverages. Sales are often lost because customers leave after seeing a long waiting line to place an order. Careful analysis of the company's existing products has revealed that the opportunity cost of order- filling time is P34.00 per minute. The company is considering introducing a cappuccino, to be made with almond extract and double-fine sugar. The variable cost of the' standard size amaretto cappuccino would he P4 60 and new product, amarettoarrow_forward
- A fast food restaurant receives a large volume of drive-through orders. A Lean Six Sigma team wants to understand the resources required to maintain a maximum target cycle time of 4 minutes. When demand fluctuates, personnel can be reassigned temporarily to increase the rate of processing. If the normal processing rate is 40 seconds per order, what should the maximum customers in process (queue) be before reassigning resources?arrow_forward1)Which of the following statements will hold good in the case of a system with uncertainty in demand for service and in service times? A)When the utilization of resources fall it is an indication of greater efficiency of the serviceB)It is a good practice to plan for resource utilization levels more than 85%C)Cost of waiting to get serviced is directly proportional to the cost of providing the serviceD)None of the above PS: Option B is wrong!!!arrow_forward10. Customers arrive an average of 8 per hour and an average of 12 customers can be served in an hour. Assume this is an M/M/1 model. (Noteshaper Quick Start #18 - #20) what is the system utilization? what is the average length of the line? what is the average number of customers in the system? what is the average amount of time spent waiting in the line? what is the average amount of time a customer spends in the system? what is the probability of no customers in the system? 11. Customers arrive at a ferry ticket office at the rate of 18 per hour on Monday mornings. This can be described as a M/M/1 model. Selling the tickets and providing general information takes an average of 2 minutes per customer. One ticket agent is on duty on Mondays. (Noteshaper Scenario #34) a. What is the average length of the line on Monday mornings? b. On average, how long does a customer wait to buy a ticket on Monday mornings (in minutes)? c. How long does it take to successfully buy a ticket on Monday…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.