Summary Introduction
To draw: To calculate the number of kanbans that must be circulated betwixt the sandy’s process and previous process.
Introduction
Lean production is a system for the management in which it focuses on reducing waste, checking the quality, and all the efforts are put to fulfill the market needs. All the activities starting from manufacturing to distribution are managed efficiently through the lean system.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
snip
An assembly station is asked to process 100 circuit boards per hour. It takes 20 minutes to receive the necessary components from the previous work station. Completed circuit boards ae placed in a rack that will hold 10 boards. The rack must be full before it is sent on to the next work station. If the factory uses a safety factor of 10%, how many kanbans are needed for the circuit board assembly process?
A JIT system uses kanban cards to authorize movement of incoming parts. In one portion of thesystem, a work center uses an average of 100 parts per hour while running. The manager hasassigned an inefficiency factor of .20 to the center. Standard containers are designed to hold sixdozen parts each. The cycle time for parts containers is about 105 minutes. How many containersare needed?
Chapter 16 Solutions
Operations and Supply Chain Management 9th edition
Ch. 16 - Prob. 1QCh. 16 - Prob. 2QCh. 16 - Prob. 3QCh. 16 - Prob. 4QCh. 16 - Prob. 5QCh. 16 - Prob. 6QCh. 16 - Prob. 7QCh. 16 - Prob. 8QCh. 16 - Prob. 9QCh. 16 - Prob. 10Q
Ch. 16 - Prob. 11QCh. 16 - Prob. 13QCh. 16 - Prob. 14QCh. 16 - Prob. 15QCh. 16 - Prob. 16QCh. 16 - Prob. 17QCh. 16 - Prob. 18QCh. 16 - Prob. 19QCh. 16 - Prob. 20QCh. 16 - Prob. 21QCh. 16 - Prob. 22QCh. 16 - Prob. 23QCh. 16 - Prob. 25QCh. 16 - Prob. 26QCh. 16 - Prob. 27QCh. 16 - Prob. 28QCh. 16 - Prob. 30QCh. 16 - Prob. 31QCh. 16 - Prob. 1PCh. 16 - As local developers prepare for an increase in...Ch. 16 - Prob. 3PCh. 16 - Prob. 4PCh. 16 - Prob. 5PCh. 16 - Prob. 6PCh. 16 - Prob. 7PCh. 16 - Prob. 8PCh. 16 - Prob. 9PCh. 16 - In a large microelectronics plant, the assembly...Ch. 16 - Prob. 11PCh. 16 - Prob. 12PCh. 16 - Prob. 13PCh. 16 - Prob. 2.1CPCh. 16 - Prob. 2.2CPCh. 16 - Prob. 2.3CPCh. 16 - Prob. 2.4CPCh. 16 - Prob. 3.1CPCh. 16 - Prob. 3.2CPCh. 16 - Prob. 3.3CPCh. 16 - Prob. 3.4CP
Knowledge Booster
Similar questions
- sniparrow_forwardDescribe how the following kanbans work: a. Production and withdrawal of b.Kanbans square c. Kanbans signal d. Kanban material Material e. Kanbans supplierarrow_forwardA JIT system uses kanban cards to authorize movement of incoming parts. In one portion of the system, a work center uses an average of 98 parts per hour while running. The manager has assigned an inefficiency factor of .28 to the center. Standard containers are designed to hold 6 dozen parts each. The cycle time for parts containers is about 105 minutes.arrow_forward
- A production system uses kanban cards to control production and movement of parts and uses 30 pieces of a certain part. Standard containers hold 15 parts. The waiting time for parts containers is about 42 minutes. Management has assigned a safety factor of .20 to this work centre. How many containers should be used to support this operation?arrow_forwardThe welding department supplies parts to the final assembly line. Management decides to implement a kanban system and has collected the following data: The daily demand is 2000 units. The production lead time is 4 days (this includes processing time, transport time, and waiting time). Management has decided to have 1 day of safety stock. One container fits 400 units. How many kanban containers will be needed to support this system?arrow_forwardWorkers have an ability to pull the Andon cord during the production process to prevent overproduction in an unbalanced process. True or False?arrow_forward
- sniparrow_forwardAn assembly station is asked to process 100 circuit boards per hour. It takes 20 minutes to receive the necessary com- ponents from the previous workstation. Completed circuit boards are placed in a rack that will hold 10 boards. The rack must be full before it is sent on to the next worksta- tion. If the factory uses a safety factor of 10%, how many kanbans are needed for the circuit board assembly process?arrow_forwardThe text presents multiple techniques that service firms can use to make their processes leaner. Which technique is demonstrated by a restaurant that offers special discounts mid-week to attract more demand during a traditionally slow period? Vary income level Reduce inventory levels Level the facility load Eliminate unnecessary activities Reduce labor equipmentarrow_forward
- Tej Dhakar’s company wants to establish kanbansto feed a newly established work cell. The following data havebeen provided. How many kanbans are needed?arrow_forwardTransmissions are delivered to the fabrication line four at a time. It takes one hour for transmissions to be delivered. Approximately four vehicles are produced each hour, and management has decided that 50 percent of expected demand should be maintained as safety stock. How many kanban card sets are needed?arrow_forwardFlores Manufacturing, Inc., is moving to kanbans to support its electronic-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed. Setup cost $16 Annual holding cost subassembly $250 per subassembly 600 subassemblies Daily production Annual usage 62,500 (-50 weeks x5 days each x daily usage of 250 subassemblies) Lead time Safety stock The kanban size is (round your response to the nearest whole number). 2 days 1 day's production of subassembliesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.