Concept explainers
Whether the given culvert will operate under inlet or outlet control for the given conditions.
Answer to Problem 20P
The given culvert is acceptable and inlet control governs.
Explanation of Solution
Given:
The diameter of concrete circular box is
The angle of inclination of flared walls is
The
The design headwater elevation is
Elevation of stream bed at face of invert is
Tail water depth is
Approximate length of culvert is
Slope of stream is
The value of
The value of
Formula used:
The flow rate per width is given by,
Here,
The required headwater is given by,
Here,
The design headwater depth is given by,
Here,
The formula for fall is given by,
The culvert invert elevation is given by,
The depth from outlet invert to hydraulic line is given by,
Here,
The outlet water elevation is given by,
Here,
The required outlet headwater elevation is given by,
Here,
Calculation:
The flow rate per width is calculated as,
Substitute
Consider Figure 16.17, "Headwater Depth for Concrete Pipe Culverts with Inlet Control" from the book "Traffic and Highway Engineering", for a depth of
The required headwater is calculated as,
Substitute
The design headwater depth is calculated as,
Substitute
The fall is calculated as,
Substitute
The culvert invert elevation is calculated as,
Substitute
The depth from outlet invert to hydraulic line is calculated as,
Substitute
The tail water is not greater so take
The outlet water elevation is calculated as,
Substitute
For circular culvert with
The required outlet headwater elevation is calculated as,
Substitute
The required outlet headwater elevation is less than the design headwater design so the given culvert is acceptable and inlet control governs.
Conclusion:
Therefore, the given culvert is acceptable and the inlet control governs.
Want to see more full solutions like this?
Chapter 16 Solutions
Traffic and Highway Engineering
- Compute the hydraulic radius and hydraulic depthj for a 36 inch diameter culvert with a depth of flow of 20 inchesarrow_forwardDesign a pipe culvert depending on the following data: Q=2 m³/sec; length of culvert (L)= 40 m; k₁= 0.25; k2= 0.5; n= 0.015; H₁= 0.1 m; and upstream water depth=1.5 m.arrow_forwardCompute the normal depth of flow in a 36-in diameter culvert with a slope of 0.0016 and a Manning's n of 0.015 for a discharge of 20 cfsarrow_forward
- Hydraulic Please both answer required otherwise please don't attemptarrow_forwardPls answer with complete solution. Tyarrow_forwardI. Design a box culvert with the following particulars: Inside dimensions: 3.5 m x 3.5 m Live load: IRC Class A Density of soil: 18 kN/m Angle of repose 30° Materials: M25 concrete, Fe 415 grade steel.arrow_forward
- Kindly answer correctly. Please show the necessary stepsarrow_forwardA pipe culvert 45 ft long extends between two reservoirs as shown below. The difference in the water surface elevation (Ah) between the two reservoirs is 21.7 ft. The pipe is 5.0 ft in diameter and has a friction factor of 0.04. Calculate the discharge in the pipe if the entrance loss coefficient is 0.5 and the exit loss coefficient is 1.0. L Aharrow_forwardQuestion What is the hydraulic radius of a stable canal carrying a discharge of 27 m³/s using Lacey's method ? (Assume silt factor is 1.0)arrow_forward
- Q2/what is the appropriate diameter of twin pipes culverts a used to pass discharge 6.5 Cumecs, if you know the natural bed slope = 1.8%, elevation at Culvert face = 22.60m, the shoulder elevation = 25, 90m, the freeboard = 0.60m, tailwater depth = o. Yom, the length the length of culvert - 80m, ke=01², n=0.012.arrow_forwardA circular finished concrete culvert is to carry a discharge of 50 cfs on a slope of 0.0010. It is to flow not more than half full. The culvert pipes are available from the manufacturer with diameters that are multiples of 1 ft. Determine the smallest suitable culvert diameter. [Answer in units of ft]arrow_forward0.2A concrete pipe culvert is to be constructed under road to carry a max. Discharge Sm /sec. if the length of pipe culvert 10m @ slope 1/100 , find the diameter of the pipe & draw the culvert between the change of discharge & the diameter.arrow_forward
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning