Question
Chapter 11, Problem 16RE
(a)
To determine
A shortest path from A to F. Arcs should be used only in the directions indicated.
Use a version of Dijkstra’s algorithm.
(b)
To determine
A critical path from A to F and determine the overall time required to complete such a project. Viewing the network as representing a type II scheduling problem and the weights as representing times in days.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A delivery person must visit each street once before returning home (node E). What ordering of the streets minimize the total distance the delivery person must travel before returning home. (The numbers next to arc indicates the distance in meters for travelling). Based on the network below;
Find the shortest path from vertex 'S' to 'T’ by Dijkstra's algorithm for the weighted graph:
3
3
d
1
4
Draw a network showing the quantities obtained in the final iteration and the optimal value of z.
Chapter 11 Solutions
Discrete Mathematics with Graph Theory (Classic Version) (3rd Edition) (Pearson Modern Classics for Advanced Mathematics Series)
Ch. 11.1 - Prob. 1TFQCh. 11.1 - Prob. 2TFQCh. 11.1 - Prob. 3TFQCh. 11.1 - In a graph G with two odd vertices, 1 and 2 , the...Ch. 11.1 - If a graph G has six odd vertices, to solve the...Ch. 11.1 - Prob. 6TFQCh. 11.1 - Prob. 7TFQCh. 11.1 - In the weighted graph the Chinese Postman Problem...Ch. 11.1 - Prob. 9TFQCh. 11.1 - In the unweighted graph n, n odd, the Chinese...
Ch. 11.1 - Solve the Chinese Postman Problem for each of the...Ch. 11.1 - Prob. 2ECh. 11.1 - 3. [BB] Solve the Chinese Postman Problem for the...Ch. 11.1 - In a graph G with two odd vertices, 1 and 2 , the...Ch. 11.1 - Solve the Chinese Postman Problem for each of the...Ch. 11.1 - Prob. 6ECh. 11.1 - Prob. 7ECh. 11.1 - Solve the Chinese Postman Problem for the weighted...Ch. 11.1 - Prob. 9ECh. 11.1 - Prob. 10ECh. 11.1 - Prob. 11ECh. 11.1 - Prob. 12ECh. 11.2 - Prob. 1TFQCh. 11.2 - Prob. 2TFQCh. 11.2 - Prob. 3TFQCh. 11.2 - Prob. 4TFQCh. 11.2 - Prob. 5TFQCh. 11.2 - Prob. 6TFQCh. 11.2 - Prob. 7TFQCh. 11.2 - Prob. 8TFQCh. 11.2 - Prob. 9TFQCh. 11.2 - Prob. 10TFQCh. 11.2 - Prob. 1ECh. 11.2 - Prob. 2ECh. 11.2 - Prob. 3ECh. 11.2 - Prob. 4ECh. 11.2 - Prob. 5ECh. 11.2 - Prob. 6ECh. 11.2 - Prob. 7ECh. 11.2 - Prob. 8ECh. 11.2 - Prob. 9ECh. 11.2 - Prove Theorem 11.2.4: A digraph is Eulerian if and...Ch. 11.2 - Prob. 11ECh. 11.2 - Prob. 12ECh. 11.2 - 13. Label the vertices of each pair of digraphs in...Ch. 11.2 - 14. Consider the digraphs , shown.
(a) Find the...Ch. 11.2 - The answers to exercises marked [BB] can be found...Ch. 11.2 - In each of the following cases, find a permutation...Ch. 11.2 - Prob. 17ECh. 11.2 - Prob. 18ECh. 11.2 - [BB] if a graph G is connected and some...Ch. 11.2 - Prob. 20ECh. 11.2 - Prob. 21ECh. 11.2 - Prob. 22ECh. 11.2 - Prob. 23ECh. 11.2 - [BB] Apply the original form of Dijkstras...Ch. 11.2 - Prob. 25ECh. 11.2 - Prob. 26ECh. 11.2 - Prob. 27ECh. 11.2 - Prob. 28ECh. 11.2 - [BB] The Bellman-Ford algorithm can be terminated...Ch. 11.2 - Prob. 30ECh. 11.2 - Prob. 31ECh. 11.2 - Prob. 32ECh. 11.2 - Prob. 33ECh. 11.3 - Prob. 1TFQCh. 11.3 - Prob. 2TFQCh. 11.3 - Prob. 3TFQCh. 11.3 - Prob. 4TFQCh. 11.3 - Prob. 5TFQCh. 11.3 - Prob. 6TFQCh. 11.3 - Prob. 7TFQCh. 11.3 - Prob. 8TFQCh. 11.3 - Prob. 9TFQCh. 11.3 - Prob. 1ECh. 11.3 - Prob. 2ECh. 11.3 - Prob. 3ECh. 11.3 - Prob. 4ECh. 11.3 - Prob. 5ECh. 11.4 - Prob. 1TFQCh. 11.4 - Prob. 2TFQCh. 11.4 - Prob. 3TFQCh. 11.4 - Prob. 4TFQCh. 11.4 - Prob. 5TFQCh. 11.4 - Prob. 6TFQCh. 11.4 - Prob. 7TFQCh. 11.4 - Prob. 8TFQCh. 11.4 - Prob. 9TFQCh. 11.4 - Prob. 10TFQCh. 11.4 - Prob. 1ECh. 11.4 - Prob. 2ECh. 11.4 - Prob. 3ECh. 11.4 - Prob. 4ECh. 11.4 - Prob. 5ECh. 11.4 - Prob. 6ECh. 11.4 - Prob. 7ECh. 11.4 - Prob. 8ECh. 11.4 - Prob. 9ECh. 11.4 - Prob. 10ECh. 11.4 - Prob. 11ECh. 11.4 - Prob. 12ECh. 11.5 - Prob. 1TFQCh. 11.5 - Prob. 2TFQCh. 11.5 - Prob. 3TFQCh. 11.5 - Prob. 4TFQCh. 11.5 - Prob. 5TFQCh. 11.5 - Prob. 6TFQCh. 11.5 - Prob. 7TFQCh. 11.5 - Prob. 8TFQCh. 11.5 - Prob. 9TFQCh. 11.5 - 10. In a type scheduling problem, a vertex that...Ch. 11.5 - Prob. 1ECh. 11.5 - [BB] The construction of a certain part in an...Ch. 11.5 - Prob. 3ECh. 11.5 - Prob. 4ECh. 11.5 - Prob. 5ECh. 11.5 - 6.(a) Find two different orientations on the edges...Ch. 11.5 - Prob. 7ECh. 11.5 - 8. Repeat Exercise 7 if, in addition to all the...Ch. 11.5 - Repeat Exercise 7 if A takes 6 months to complete...Ch. 11.5 - Prob. 10ECh. 11.5 - Prob. 11ECh. 11.5 - Prob. 12ECh. 11.5 - Prob. 13ECh. 11.5 - Prob. 14ECh. 11.5 - Prob. 15ECh. 11.5 - Prob. 16ECh. 11.5 - 17. The computer systems manager in mathematics...Ch. 11 - Solve the Chinese Postman Problem for the two...Ch. 11 - Prob. 2RECh. 11 - 3. Solve the Chinese Postman Problem for the...Ch. 11 - Prob. 4RECh. 11 - Prob. 5RECh. 11 - Prob. 6RECh. 11 - Prob. 7RECh. 11 - Prob. 8RECh. 11 - Prob. 9RECh. 11 - 11. Let and assume that the complete graph has...Ch. 11 - Prob. 11RECh. 11 - Prob. 12RECh. 11 - Prob. 13RECh. 11 - Prob. 14RECh. 11 - Use a version of Dijkstras algorithm to find a...Ch. 11 - Prob. 16RECh. 11 - Prob. 17RECh. 11 - Prob. 18RECh. 11 - Prob. 19RECh. 11 - 20. The following chart lists a number of tasks...Ch. 11 - Prob. 21RE
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, subject and related others by exploring similar questions and additional content below.Similar questions
- Given the figure below. Redraw again the figure to determine the shortest path using The Edge – Picking Algorithm/Cheapest Link Methodarrow_forwardAnalyze each graph below to determine whether it has an Euler circuit and/or an Euler trail. •If it has an Euler circuit, specify the nodes for one. •If it does not have an Euler circuit, justify why it does not. •If it has an Euler trail, specify the nodes for one. •If it does not have an Euler trail, justify why it does not.arrow_forwardUse the Program Evaluation and Review Technique to represent the project in an activity network. In conjunction with the Critical Path Method, use the activity network to find the shortest time possible to complete the project, to identify the critical jobs in the project, and to determine the earliest and latest that each activity can start and finish without making the project completion longer.arrow_forward
- Analyze each graph below to determine whether it has an Euler circuit and/or an Euler trail. •If it has an Euler circuit, specify the nodes for one.•If it does not have an Euler circuit, justify why it does not.•If it has an Euler trail, specify the nodes for one.•If it does not have an Euler trail, justify why it does not.arrow_forwardDraw the network diagram for the above project.arrow_forwardSolve the shortest path problems shown in the attached picture by hand using the original implementation of Dijkstra's algorithm. Count the number of distance updates, provide the shortest path solution and the hand-drawn trees of shortest paths for (a) and (b).arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Algebra & Trigonometry with Analytic GeometryAlgebraISBN:9781133382119Author:SwokowskiPublisher:Cengage
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:9781133382119
Author:Swokowski
Publisher:Cengage
Minimum cuts and maximum flow rate; Author: Juddy Productions;https://www.youtube.com/watch?v=ylxhl1ipWss;License: Standard YouTube License, CC-BY